Registration approved No litigation declared Mixed Development project

ICON PLANET

By HNGC BUILDERS AND DEVELOPERS

RG-KA-61175 · RERA PRM/KA/RERA/1257/334/PR/180722/005075 · Last updated on RERA Karnataka portal: 7 Jul 2022

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Sep 2024Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 111 documents Report an error

ICON PLANET is a Mixed Development project by HNGC BUILDERS AND DEVELOPERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/180722/005075 on 18 Jul 2022. Possession is promised by 30 Sep 2024.

At a glance

Project

  • NameICON PLANET
  • TypeMixed Development
  • Location
    • Mangalore
    • Dakshina Kannada
    • 575014
  • Pincode575014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/180722/005075
  • ReraGenie IDRG-KA-61175

Builder

  • NameHNGC BUILDERS AND DEVELOPERS
  • Entity typePartnership Firm
  • GSTIN29AAHFH6398B1Z3
  • Authorized SignatoryK HUSSAIN ABBAS
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2022PromisedSep 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on18 Jul 2022
  • Promised completion30 Sep 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed111 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ICON PLANET-----25

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 7 Jul 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 7 Jul 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesYes-
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesYes-
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areasYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area849 sq m
Named landowners1
LandownerVillageDistrict
HNGC BUILDERS AND DEVELOPERS--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 2.24 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 2.24 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectABDUL JALEEL MH
EngineerABDUL JALEEL MH
Chartered AccountantRAVINDRA SHENOY

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed111

As listed on the registration, under the names the promoter filed them with; the newest 80 of 111 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/180722/005075 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RTCFile: RTC.pdf7 Jul 2022
MR COPYFile: MR COPY.pdf7 Jul 2022
TITLE DEEDFile: TITLE DEED.pdf7 Jul 2022
LEGAL HERIS RELATED TO TITLE DEEDFile: LEGALHEIRS OF TITLE DEED.pdf7 Jul 2022
SANCTION PLANFile: sanction plan_compressed.pdf7 Jul 2022
SECTION ELEVATION PLANFile: ELEVATION AND SECTION PLAN.pdf7 Jul 2022
TYPICAL FLOOR PLANFile: FLOOR PLAN.pdf7 Jul 2022
MASTER PLANFile: MASTER PLAN.pdf7 Jul 2022
LOCATIONFile: Location.pdf7 Jul 2022
ENGINEER CERTFICATE AS PER RERAFile: engineer certificate form 3.pdf7 Jul 2022
MESCOM NOCFile: MESCOM NOC.pdf7 Jul 2022
FEE RECEIPT MESCOM NOCFile: Power NOC FEE Receipt.pdf7 Jul 2022
WATER NOCFile: Water NOC.pdf7 Jul 2022
PROFORMA AOSFile: proforma AOS.pdf7 Jul 2022
STP DRAWINGFile: STP DRAWING.pdf7 Jul 2022
BROCUHERFile: broucher.pdf7 Jul 2022
PROFORMA ALLOTMENT LETTERFile: profroma allottment letter.pdf7 Jul 2022
CLARIFICATIONFile: clarification on Notice.pdf7 Jul 2022
Upload chartered accountant certificate in prescribed format form-01.File: form 1 new format HNGC.pdf19 Apr 2022
non litigation affidavitFile: non litigation new HNGC.pdf19 Apr 2022
RTCFile: RTC.pdf19 Apr 2022
need sale deed / title deed for project land owner.File: SALEDEED.pdf19 Apr 2022
upload all Original and Clear sanctioned drawings including Floor plans, sectional drawings and elFile: Plan 1.PDF19 Apr 2022
FULL PLANFile: Plan 2.PDF19 Apr 2022
FLOOR PLANSFile: FLOOR PLANS.pdf19 Apr 2022
Upload Original and Clear Development / single layout Plan.File: SINGLELAYOUT20211113_12030340.pdf19 Apr 2022
Upload Change of land use/ certified Extract of Master Plan.File: CONVERTION.pdf19 Apr 2022
COA Number of the architect.File: Eng Certificate.pdf19 Apr 2022
Engineer certificateFile: form3-hngc_compressed.pdf19 Apr 2022
form 2File: Form 2.pdf19 Apr 2022
acknowledgement number and upload the original copy of section 3(1) notarized affidavit.File: notarized affidavit 3(i) HNGC new.pdf19 Apr 2022
attested copy of Power supply NOCFile: Electricity NOC.pdf19 Apr 2022
water supply NOC attestedFile: Water NOC.pdf19 Apr 2022
proforma of AOSFile: AOS HNGC NEW.pdf19 Apr 2022
attested copy of Fire force NOC.File: Fire NOC.pdf19 Apr 2022
Proforma of Allotment.File: ALLOTMENT.pdf19 Apr 2022
RTC, survey 40/1A2(P)-
Mutation, survey 40/1A2(P)-
Encumbrance Certificate, survey 40/1A2(P)-
Conversion/Alienation Order, survey 40/1A2(P)-
Sale/Title/Gift Deed, survey 40/1A2(P)-
Khatha, survey 40/1A2(P)-
Registration CertificateFile: CERTIFICATE.pdf-
Partnership DeedFile: PARTNERSHIP DEED20211113_11554222.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: form 1 new format HNGC_compressed.pdf-
Certificate issued by Architect Form 2File: architect certficate form 2.pdf-
Certificate issued by Engineer Form 3File: engineer certificate form 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: non litigation.pdf-
Certificate from Chartered AccountFile: form 1 new format HNGC_compressed.pdf-
Balance Sheet 2020 - 2021File: BS 2021.pdf-
Balance Sheet 2019 - 2020File: hngc BS 2020.pdf-
Balance Sheet 2018 - 2019File: hngc BS 2019.pdf-
Audited Profit and Loss Statement 2020 - 2021File: PL 2021.pdf-
Audited Profit and Loss Statement 2019 - 2020File: hngc PL 2020.pdf-
Audited Profit and Loss Statement 2018 - 2019File: hngc PL 2019.pdf-
Auditor's Report 2020 - 2021File: AUDIT REPORT 21.pdf-
Auditor's Report 2019 - 2020File: Audit report20.pdf-
Auditor's Report 2018 - 2019File: audit report 19.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR 21.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR20.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR19.pdf-
LICENCE-
Planet Mescom permission-
MCC water permission-
icon planet plan-
icon planet plan-
Planet Plan 2-
icon planet plan-
Planet Plan 1-
Specifications HNGC-
Planet Plan 2-
Planet Plan 2-
Planet Plan 2-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
ICON TOWERNH66 IDDYA VILLAGE SURATHKALCompleted-No date filed

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep ICON PLANET on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

Builder: HNGC BUILDERS AND DEVELOPERS

HNGC BUILDERS AND DEVELOPERS has 1 registration on RERA Karnataka, including ICON PLANET. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if ICON PLANET is delayed beyond 30 Sep 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ICON PLANET?

The registered promoter entity is HNGC BUILDERS AND DEVELOPERS, a partnership firm as per the filing. Its GSTIN 29AAHFH6398B1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ICON PLANET?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ICON PLANET?

The professionals named in the filing: Architect: ABDUL JALEEL MH; Engineer: ABDUL JALEEL MH; Chartered Accountant: RAVINDRA SHENOY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ICON PLANET?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ICON PLANET. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ICON PLANET to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.