Home / Browse projects / Raigarh, Maharashtra / HOLIDAY MAIYAAN KARJAT PHASE II

Registered Litigation declared Others project

HOLIDAY MAIYAAN KARJAT PHASE II

By B QUBES

RG-MH-10943 · RERA P52000000479 · Last updated on MahaRERA portal: 10 Aug 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 3 complaints at MahaRERA
  • Completion date moved by 98 months
  • 4 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 98 months from the original
18 of 33Construction stages doneacross 4 buildings; furthest along: Installation of Lifts, 98%
7 of 150Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 156 documents Report an error

HOLIDAY MAIYAAN KARJAT PHASE II is a Others project by B QUBES in Raigarh, Maharashtra, registered with MahaRERA as P52000000479 on 18 Jul 2017. Possession is promised by 31 Dec 2028. The completion date has moved by 98 months from the original filing. 143 of the 150 units on this registration are recorded sold or booked, and 18 of 33 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameHOLIDAY MAIYAAN KARJAT PHASE II
  • TypeOthers
  • Location
    • chaudhar Road
    • chaudhar wadi
    • Dhamni
    • Karjat
    • Raigarh
    • 410201
  • Pincode410201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000000479
  • ReraGenie IDRG-MH-10943

Builder

  • NameB QUBES
  • Entity typePartnership
  • PartnersGANEISH KALLAPA, AMIT SUDHIR GHARPURE
  • Other registrations2 more →

Key dates

this monthRegisteredJul 2017First promiseOct 2020Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Jul 2017
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 30 Oct 2020)
  • Buildings4 building records
  • Documents filed156 files

Current status

95%143 of 150 units booked
72.4%Work done, per cost certificate

Figures as on 10 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1NA3348048
CNA3348048
D3NA3324024
ENA3330030

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 10 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 33 construction stages are filed complete across 4 buildings. The stage furthest along is Installation of Lifts, at 98%.

A1100%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%
C11%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
D3100%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
E71%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises45%
Sanitary Fittings within the flats / premises35%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%

Progress on shared amenities15

As on 10 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes92%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes80%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceYes70%
Open ParkingYes70%

Parking filed168

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots168
Open Space168
BuildingOpen SpaceTotal
A14848
C4848
D33232
E4040

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area15,054 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Jun 2025

Approvals and building plan

Sanctioning authorityHon. Collector & Hon. Town Planning Authority Raigad District
Permissible FSI7167.55
Proposed, not sanctioned7,168 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 16-17, SIDHHACHAL PH IV, NEAR VASANT VIHAR, POKHRAN ROAD II, THANE WEST, 400610
Estimated costRs 23.00 cr
Cost incurredRs 16.64 cr
Work done72.36%
BuildingWingEstimatedIncurred
ENARs 6.43 crRs 5.15 cr
A1NARs 4.63 crRs 4.54 cr
CNARs 4.63 crRs 9.26 lakh
D3NARs 4.37 crRs 4.37 cr
-NARs 2.93 crRs 2.49 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTrupti Panchal
EngineerStructonEngineeringServices
EngineerRohit Mahadev Sadigale
EngineerJayesh Rambhau Gaikwad
Chartered AccountantNimeshDiyoraANDassociates
Chartered AccountantKLBJ & Co.
Chartered AccountantMulraj D Gala & Co.
PartnerRole in project
B QUBES-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000012058Oct 2020 → Apr 2025

Reason as filed by the promoterTo, The Hon. Chairman, Maharashtra Real Estate Regulatory Authority, Mumbai Subject: Request for project extension for Holiday Maiyaan Karjat Phase 2, MahaRERA Registration NO. P52000000479, Situated at Sr. No. 185/1 to 185/6, Vil. Dhamni, Taluka Karjat, Dist Raigarh Respected Honourable Chairman, MahaRERA, We would like to mention that there are total 4 number of buildings in the said Phase, namely A1, D3, C and E. A. The construction and Sales for two buildings (A1 and D3) was started before covid. During covid period we could undertake construction activities at a bare minimum speed due to

EXT52000011470Oct 2020 → Apr 2022

Reason as filed by the promoterTo, The Hon. Charman, Maharashtra Real Estate Regulatory Authority, Mumbai Subject: Request for project extension for Holiday Miyaan Karjat, MahaRERA Registration No. P52000000479, Situated at Sr. No. 185/1 to 185/6, Vil. Dhamni, Tal. Karjat, Dist. Raigarh Respected Honourable Chairman, MahaRERA This is in reference to our above mentioned project Holiday Maiyaan Karjat (Phase 2) which is registered with the MahaRERA authority under the number: P52000000479 We would like to mention that the construction on site for the said buildings is almost 60% completed nearing up to the second slab level f

EXT52000008429Oct 2020 → Apr 2021

Reason as filed by the promoterTo The Hon. Chairman, Maharashtra Real Estate Regulatory Authority, Mumbai Subject : Request for Project Extension for Holiday Maiyaan Karjat, MahaRERA Registration No. P52000000479) situated at Sr. No. 185/1 to 185/6, Vil Dhamani, Tal Karjat, Dist. Raigarh Respected Hon. Chairman, MahaRERA, This is in reference to our above mentioned project Holiday Maiyaan Karjat (phase 1) which is registered with the MAHARERA authority under the number: P52000000479 We would like to state that the construction on site is almost 85% completed including RCC superstructure and major finishing works like painti

EA28062501837Oct 2020 → Dec 2028

Reason as filed by the promotera) As the entire country including Raigarh District were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to curb the spread of the COVID-19. In view of the curbs and measures imposed by the Governments, I stopped work till such time as the said lockdowns, curbs and measures were relaxed by the respective Governments. b) Inspite of best efforts, the said project was adversely affected due to unprecedented COVID-19 Pandemic which lasted for more than 2 years and are s

Litigation declared1

CaseCourtStatus
184/2019/2019Civil Judge Junior Division Karjat CourtOngoing

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC12400131Khaleeque Ahmed SaiyedB QUBES17/09/2024
CC12400138Jasmine Gurcharan Singh BediB QUBES17/09/2024
CC12502028Manasi Munesh KumarB QUBES21/06/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Oct 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Aug 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Aug 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed156

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 156 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Building plan approvalFile: A1 copy Final.pdf10 Aug 2026
Building plan approvalFile: C copy final.pdf10 Aug 2026
Building plan approvalFile: D3-Sheet No 09.pdf10 Aug 2026
Building plan approvalFile: E copy Final.pdf10 Aug 2026
Building plan approvalFile: Masterplan copy.pdf10 Aug 2026
Layout approvalFile: Masterplan copy.pdf10 Aug 2026
Withdrawal Update Form 1File: Form-1 Phase-2 June 26.pdf5 Aug 2026
Withdrawal Update Form 2File: Form-2 Phase-2- June 26-.pdf5 Aug 2026
Withdrawal Update Form 3File: CA Certificate_Phase II June 26-6.pdf5 Aug 2026
Building plan approvalFile: A1-PH2.pdf7 Jul 2026
Building plan approvalFile: C-PH2.pdf7 Jul 2026
Building plan approvalFile: D3-PH2.pdf7 Jul 2026
Building plan approvalFile: E-PH2.pdf7 Jul 2026
Building plan approvalFile: Masterplan-T-PH2.pdf7 Jul 2026
Layout approvalFile: A1-PH2.pdf7 Jul 2026
Layout approvalFile: C-PH2.pdf7 Jul 2026
Layout approvalFile: D3-PH2.pdf7 Jul 2026
Layout approvalFile: E-PH2.pdf7 Jul 2026
Layout approvalFile: Masterplan-T-PH2.pdf7 Jul 2026
Form 2A (FY 2017-2018)File: Form 2A -2018.pdf4 Jul 2026
Form 2A (FY 2018-2019)File: Form 2A -2019.pdf4 Jul 2026
Form 2A (FY 2019-2020)File: Form 2A -2020.pdf4 Jul 2026
Form 2A (FY 2020-2021)File: Form 2A -2021.pdf4 Jul 2026
Form 2A (FY 2021-2022)File: Form 2A -2022.pdf4 Jul 2026
Form 2A (FY 2022-2023)File: Form 2A -2023.pdf4 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A -2026.pdf3 Jul 2026
Withdrawal Update Form 1File: Ph-2 Form-1.pdf27 Apr 2026
Withdrawal Update Form 2File: Ph-2 Form-2.pdf27 Apr 2026
Withdrawal Update Form 3File: Ph 2- Form-3.pdf27 Apr 2026
Withdrawal Update Form 1File: Form 1 PH 2.pdf13 Feb 2026
Withdrawal Update Form 2File: Form 2 PH-2.pdf13 Feb 2026
Withdrawal Update Form 3File: Form 3 PH-2.pdf13 Feb 2026
Form 5 (FY 2024-2025)File: Form -5 Ph-2 FY 24-25 (1).pdf12 Dec 2025
Withdrawal Update Form 1File: PH 2 FORM 1 MARCH 24.pdf25 Oct 2025
Withdrawal Update Form 2File: PH 2 Form 2 Sep 25 (1).pdf25 Oct 2025
Withdrawal Update Form 3File: Form 3 Ph 2 Sep 25.pdf25 Oct 2025
Form 2A (FY 2023-2024)File: FORM 2A PH 2 23-24.pdf24 Jul 2025
Form 5 (FY 2022-2023)File: FORM 5 PH 2 FY 22-23.pdf24 Jul 2025
Form 5 (FY 2021-2022)File: FORM 5 PH 2 FY 21-22 R1.pdf24 Jul 2025
Form 5 (FY 2023-2024)File: FORM 5 PH 2 FY 23-24.pdf23 Jul 2025
Form 1File: Architech Crtificate FORM 1 PH 2 JUNE 2025.pdf18 Jul 2025
Form 2File: Enginer Certificate FORM 2 PH 2 JUNE 2025 (1).pdf18 Jul 2025
Form 3File: CA Certificate FORM 3 PH 2 JUNE 2025_compressed.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD PH 2 JUNE 2025.pdf18 Jul 2025
Form 1File: DECEMBER 2024.pdf18 Jul 2025
Form 2File: 31 Dec 2024.pdf18 Jul 2025
Form 3File: DECEMBER 2024.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Ph-2 Sold Unsold- Dec-24.pdf18 Jul 2025
Form 1File: FROM 1 PH 2 SEP 24.pdf18 Jul 2025
Form 2File: FROM 2 PH 2 SEP 24.pdf18 Jul 2025
Form 3File: FORM 3 PH 2 SEP 24_compressed.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD PH 2 SEP 24.pdf18 Jul 2025
Form 1File: FORM 1 PH 2 JUNE 24.pdf18 Jul 2025
Form 2File: FROM 2 PH 2 JUNE 24.pdf18 Jul 2025
Form 3File: FROM 3 PH 2 JUNE 24_compressed.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD PH 2 JUNE 24.pdf18 Jul 2025
Form 1File: MARCH 2024.pdf18 Jul 2025
Form 2File: 31 Mar 2024.pdf18 Jul 2025
Form 3File: MARCH 2024.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD PH 2 MAR 24.pdf18 Jul 2025
Form 1File: SEPTEMBER 2023.pdf18 Jul 2025
Form 2File: 31 Sep 23.pdf18 Jul 2025
Form 3File: SEPTEMBER 2023.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: SEP 23 - 30-09-23.pdf18 Jul 2025
Form 1File: MARCH 2023.pdf18 Jul 2025
Form 2File: 31 Mar 2023.pdf18 Jul 2025
Form 3File: MARCH 2023 R2.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD PH 2 MAR 23.pdf18 Jul 2025
Form 1File: FORM 1 PH 2 MARCH 25.pdf28 Jun 2025
Form 2File: FORM 2 PH 2 MARCH 25.pdf28 Jun 2025
Form 3File: CA - MARCH 25.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure -MARCH 25.pdf28 Jun 2025
Form 2A (FY 2024-2025)File: FORM 2A PH2 24-25.pdf28 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM2A-PH2-23-24.pdf20 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ph-2 -Form-1.pdf4 Feb 2025
Certificates of CA (Form 3)File: ph-2 Form -3 Dec -24.pdf4 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ph-2 Form 2.pdf4 Feb 2025
Disclosure of sold/ booked inventoryFile: Ph-2 Sold Unsold- Dec-24.pdf4 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ph-2 Form-5 FY 23-24.pdf4 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PH 2 FORM 1 MARCH 24.pdf15 May 2024

How this compares with Raigarh

95%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 98 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep HOLIDAY MAIYAAN KARJAT PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near chaudhar wadi5,900+ in Raigarh

2 kmHOLIDAY MAIYAAN KARJAT PLapsed / revoked 1Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: B QUBES

B QUBES has 3 registrations on MahaRERA, including HOLIDAY MAIYAAN KARJAT and HOLIDAY MAIYAAN KARJAT PHASE II. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if HOLIDAY MAIYAAN KARJAT PHASE II is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HOLIDAY MAIYAAN KARJAT PHASE II?

The registered promoter entity is B QUBES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HOLIDAY MAIYAAN KARJAT PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against HOLIDAY MAIYAAN KARJAT PHASE II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for HOLIDAY MAIYAAN KARJAT PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HOLIDAY MAIYAAN KARJAT PHASE II?

The professionals named in the filing: Architect: Trupti Panchal; Engineer: StructonEngineeringServices; Engineer: Rohit Mahadev Sadigale; Engineer: Jayesh Rambhau Gaikwad; Chartered Accountant: NimeshDiyoraANDassociates; Chartered Accountant: KLBJ & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HOLIDAY MAIYAAN KARJAT PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HOLIDAY MAIYAAN KARJAT PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HOLIDAY MAIYAAN KARJAT PHASE II to a free account