Home / Browse projects / Raigarh, Maharashtra / HOLIDAY MAIYAAN KARJAT
HOLIDAY MAIYAAN KARJAT
By B QUBES
RG-MH-08439 · RERA P52000000477 · Last updated on MahaRERA portal: 22 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 1 case
- Completion date moved by 116 months
- 3 extensions taken
Clear
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
HOLIDAY MAIYAAN KARJAT is a Others project by B QUBES in Raigarh, Maharashtra, registered with MahaRERA as P52000000477 on 18 Jul 2017. Possession is promised by 31 Dec 2028. The completion date has moved by 116 months from the original filing. 131 of the 132 units on this registration are recorded sold or booked, and 32 of 44 construction stages are filed complete.
At a glance
Project
- NameHOLIDAY MAIYAAN KARJAT
- TypeOthers
- Location
- Chaudhar Road
- Chaudhar Wadi
- Dhamni
- Karjat
- Raigarh
- 410201
- Pincode410201
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000000477
- ReraGenie IDRG-MH-08439
Builder
- NameB QUBES
- Entity typePartnership
- PartnersGANEISH KALLAPA, AMIT SUDHIR GHARPURE
- Other registrations2 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on18 Jul 2017
- Promised completion31 Dec 2028
- Revised completionRevised to 31 Dec 2028 (originally 30 Apr 2019)
- Buildings4 building records
- Documents filed124 files
Current status
Figures as on 22 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| D1 | NA | 3 | 3 | 24 | 0 | 24 |
| D2 | NA | 3 | 3 | 12 | 0 | 12 |
| A2 | NA | 3 | 3 | 48 | 0 | 48 |
| A3 | NA | 3 | 3 | 48 | 0 | 48 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 22 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
32 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Basement (if any), at 0%.
D173%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
D273%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A273%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A373%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 22 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 70% |
| Open Parking | Yes | 70% |
Parking filed276
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| D1 | 56 | 56 |
| D2 | 28 | 28 |
| A2 | 96 | 96 |
| A3 | 96 | 96 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| D1 | NA | Rs 2.80 cr | Rs 2.80 cr |
| A2 | NA | Rs 2.80 cr | Rs 2.80 cr |
| A3 | NA | Rs 2.80 cr | Rs 2.80 cr |
| D2 | NA | Rs 1.40 cr | Rs 1.40 cr |
| - | NA | Rs 1.20 cr | Rs 1.20 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Trupti Panchal |
| Engineer | StructonEngineeringServices |
| Engineer | Rohit Mahadev Sadigale |
| Chartered Accountant | NimeshDiyoraANDassociates |
| Chartered Accountant | KLBJ & Co. |
| Partner | Role in project |
|---|---|
| B QUBES | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterTo, The Hon. Chairman, Maharashtra Real Estate Regulatory Authority, Mumbai Subject: Request for project extension for Holiday Maiyaan Karjat Phase 2, MahaRERA Registration NO. P52000000477, Situated at Sr. No. 185/1 to 185/6, Vil. Dhamni, Taluka Karjat, Dist Raigarh Respected Honourable Chairman, MahaRERA, This is in reference to our above mentioned project Holiday Maiyaan Karjat which is registered with the MahaRERA authority under the number: P52000000477 By an email received from MahaRERA authority on 11/04/23, and further our reply on 12th May 2023, We were informed and further instructed
Reason as filed by the promoterTo The Hon. Chairman, Maharashtra Real Estate Regulatory Authority, Mumbai Subject : Request for Project Extension for Holiday Maiyaan Karjat, MahaRERA Registration No. P52000000477) situated at Sr. No. 185/1 to 185/6, Vil Dhamani, Tal Karjat, Dist. Raigarh Respected Hon. Chairman, MahaRERA, This is in reference to our above mentioned project Holiday Maiyaan Karjat (phase 1) which is registered with the MAHARERA authority under the number: P52000000477 We would like to state that the construction on site is almost 85% completed including RCC superstructure and major finishing works like painti
Reason as filed by the promotera) The project site’s remote location-approximately 25 kilometres from Karjat station-poses logistical challenges in material delivery and labour/staff mobilization, further affecting the construction timeline. b) Despite these hurdles, we have continued to make consistent efforts to ensure quality development and timely delivery. We remained committed in completing the work in the feasible timeline, without compromising on the standards. We have obtained completion certificate from Group Grampanchayat Mograj dated 10/11/2020. However, occupancy certificate from Town and Country Planning Depar
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 184/2019/2019 | Civil Judge Junior Division karjat Court | Ongoing |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Oct 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 15 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 15 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 3 Mar 2023
Documents filed124
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 124 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Ph-1 Form-1.pdf | 22 May 2026 |
| Withdrawal Update Form 1File: Ph-1 Form-1.pdf | 22 May 2026 |
| Withdrawal Update Form 2File: Ph-1 Form-2.pdf | 22 May 2026 |
| Withdrawal Update Form 2File: Ph-1 Form-2.pdf | 22 May 2026 |
| Withdrawal Update Form 3File: Ph-1 Form -3.pdf | 22 May 2026 |
| Withdrawal Update Form 3File: Ph-1 Form -3.pdf | 22 May 2026 |
| Form 2A (FY 2017-2018)File: Form 2A-2018.pdf | 22 May 2026 |
| Form 2A (FY 2018-2019)File: Form 2A -2019.pdf | 22 May 2026 |
| Form 2A (FY 2019-2020)File: Form 2A -2020.pdf | 22 May 2026 |
| Form 2A (FY 2020-2021)File: Form 2A -2021.pdf | 22 May 2026 |
| Form 2A (FY 2021-2022)File: Form 2A -2022.pdf | 22 May 2026 |
| Form 2A (FY 2022-2023)File: Form 2A -2023.pdf | 22 May 2026 |
| Form 2A (FY 2023-2024)File: Form 2A -2024.pdf | 22 May 2026 |
| Form 2A (FY 2024-2025)File: Form 2A -2025.pdf | 22 May 2026 |
| Form 2A (FY 2025-2026)File: Form 2A -2026.pdf | 22 May 2026 |
| Form 1File: Ph-1 Form -1 Sep-24.pdf | 9 May 2026 |
| Form 2File: Ph-1 Form -2 Sep-24.pdf | 9 May 2026 |
| Form 3File: ph-1 Form-3 Sep-24.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Ph-1 Sold unsold -Sep 24.pdf | 9 May 2026 |
| Form 1File: Ph-1 Form -1 June-24.pdf | 9 May 2026 |
| Form 2File: Ph-1 Form -2 June-24.pdf | 9 May 2026 |
| Form 3File: Form-3 Ph-1 June-24.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Ph-1 Sold unsold-June -24.pdf | 9 May 2026 |
| Form 1File: Form-1 Ph-1 DEC-23 (1).pdf | 9 May 2026 |
| Form 2File: FORM-2 PH-1 DEC-23 (1).pdf | 9 May 2026 |
| Form 3File: Form-3 Ph-1 Dec-23.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Ph-1 Sold unsold-Dec 23.pdf | 9 May 2026 |
| Form 1File: Form-1 Ph-1 June-23.pdf | 9 May 2026 |
| Form 2File: FORM-2 PH-1 June-23.pdf | 9 May 2026 |
| Form 3File: Form-3 Ph-1 June-23.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Ph-1 Sold unsold-June 23.pdf | 9 May 2026 |
| Form 1File: Ph 1 Form 1 Dec 24.pdf | 8 May 2026 |
| Form 2File: Ph 1 Form 2 Dec 24.pdf | 8 May 2026 |
| Form 3File: Ph 1 Form 3 Dec 24.pdf | 8 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Ph 1 Sold Unsold Dec 24.pdf | 8 May 2026 |
| Form 1File: PH 1 FORM 1 MARCH 24.pdf | 8 May 2026 |
| Form 2File: ph-1 form 2 March 24.pdf | 8 May 2026 |
| Form 3File: Ph 1 Form 3 Mar 24.pdf | 8 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Ph-1 sold unsold March 24.pdf | 8 May 2026 |
| Form 1File: FORM 1 PH 1 SEP 23.pdf | 8 May 2026 |
| Form 2File: FORM 2 PH 1 SEP 23.pdf | 8 May 2026 |
| Form 3File: Ph 1 Form 3 Sep 23.pdf | 8 May 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD PH 1 SEP 23.pdf | 8 May 2026 |
| Withdrawal Update Form 1File: Ph-1 Form-1.pdf | 27 Apr 2026 |
| Withdrawal Update Form 2File: Ph-1 Form-2.pdf | 27 Apr 2026 |
| Withdrawal Update Form 3File: Ph-1 Form -3.pdf | 27 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 Ph-1.pdf | 12 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 PH-1.pdf | 12 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 Ph1 fi.pdf | 12 Feb 2026 |
| Form 5 (FY 2024-2025)File: Form 5 Ph -1 FY 24-25.pdf | 12 Dec 2025 |
| Withdrawal Update Form 1File: P-1-Form 1 (3).pdf | 25 Oct 2025 |
| Withdrawal Update Form 1File: P-1-Form 1 (3).pdf | 25 Oct 2025 |
| Withdrawal Update Form 2File: PH 1 Form 2 Sep 25 (5).pdf | 25 Oct 2025 |
| Withdrawal Update Form 2File: PH 1 Form 2 Sep 25 (5).pdf | 25 Oct 2025 |
| Withdrawal Update Form 3File: PH 1 FROM 3 SEP 25 (4).pdf | 25 Oct 2025 |
| Withdrawal Update Form 3File: PH 1 FROM 3 SEP 25 (4).pdf | 25 Oct 2025 |
| Form 1File: AR PH 1 MARCH 25.pdf | 4 Jul 2025 |
| Form 2File: ER PH 1 MARCH 25.pdf | 4 Jul 2025 |
| Form 3File: CA - March 25_compressed.pdf | 4 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - March 25.pdf | 4 Jul 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM2A-PH1-23-24.pdf | 20 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ph-1 Form -1.pdf | 4 Feb 2025 |
| Certificates of CA (Form 3)File: PH-1 Form-3 Dec-24.pdf | 4 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ph-1 Form -2.pdf | 4 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: pH -1 Sold Unsold-Dec-24.pdf | 4 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: PH-1 Form 5 FY 23-24.pdf | 4 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PH 1 FORM 1 MARCH 24.pdf | 15 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PH1 F2 MAR24.pdf | 15 May 2024 |
| Certificates of CA (Form 3)File: PH1 F3 MAR24_compressed.pdf | 15 May 2024 |
| Certificates of CA (Form 3)File: FORM 3 UPTO DEC 2023_compressed-2.pdf | 28 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 PH 1 FY 21-22.pdf | 28 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 PH 1 FY 22-23.pdf | 28 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A PH 1 21-22.pdf | 4 Nov 2023 |
| Copy of the legal title reportFile: TITLE SEARCH REPORT 02_compressed-2.pdf | 26 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD PH 1 SEP 23 UPLOAD.pdf | 26 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 PH 1 SEP 23 UPLOAD_compressed.pdf | 23 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 PH 1 SEP 23 UPLOAD.pdf | 23 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A PH 1 MAR 23 UPLOAD.pdf | 23 Oct 2023 |
| Details of encumbrances concerned to FinanceFile: ENCUMBRANCES DETAILS.pdf | 4 Jul 2023 |
| Details of encumbrances concerned to LegalFile: ENCUMBRANCES DETAILS.pdf | 4 Jul 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 124 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep HOLIDAY MAIYAAN KARJAT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chaudhar Wadi5,900+ in Raigarh
Filed coordinates, straight-line distance. 3 registered projects within 2 km.
Bellezza Woods
DOTOM BUILD SQUARE
Winds of Calm
Eiffel Lifespaces Pvt Ltd
PURANIK CITY SECTOR 2
Puranik Builders Limited
Foothills of Matheran P - 2
HOABL Impactum Land Private Limited
FLORENCE TOWN
BRIGHT DEVELOPERS
The Destination
DOVE BUILDMART PRIVATE LIMITED
See every Raigarh project, with the district possession charts
Builder: B QUBES
B QUBES has 3 registrations on MahaRERA, including HOLIDAY MAIYAAN KARJAT and HOLIDAY MAIYAAN KARJAT PHASE II. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if HOLIDAY MAIYAAN KARJAT is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of HOLIDAY MAIYAAN KARJAT?
The registered promoter entity is B QUBES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in HOLIDAY MAIYAAN KARJAT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for HOLIDAY MAIYAAN KARJAT?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at HOLIDAY MAIYAAN KARJAT?
The professionals named in the filing: Architect: Trupti Panchal; Engineer: StructonEngineeringServices; Engineer: Rohit Mahadev Sadigale; Chartered Accountant: NimeshDiyoraANDassociates; Chartered Accountant: KLBJ & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in HOLIDAY MAIYAAN KARJAT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback