Home / Browse projects / Mumbai Suburban, Maharashtra / Hill Casa

Registered No litigation declared Residential / Group Housing project

Hill Casa

By HUSAIN TAHER PATNI

RG-MH-73031 · RERA P51800018188 · Last updated on MahaRERA portal: 22 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 54 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 54 months from the original
10 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 95%
22 of 26Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 125 documents Report an error

Hill Casa is a Residential / Group Housing project by HUSAIN TAHER PATNI in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800018188 on 15 Oct 2018. Possession is promised by 31 Dec 2026. The completion date has moved by 54 months from the original filing. 4 of the 26 units on this registration are recorded sold or booked, and 10 of 22 construction stages are filed complete.

At a glance

Project

  • NameHill Casa
  • TypeResidential / Group Housing
  • Location
    • BORAN ROAD
    • BANDRA
    • Andheri
    • Mumbai Suburban
    • 400050
  • Pincode400050
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800018188
  • ReraGenie IDRG-MH-73031

Builder

  • NameHUSAIN TAHER PATNI
  • Entity typeIndividual
  • GSTIN27ALLPP8191R1ZV

Key dates

this monthRegisteredOct 2018First promiseJun 2022Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Oct 2018
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2022)
  • Buildings2 building records
  • Documents filed125 files

Current status

15%4 of 26 units booked
47.3%Work done, per cost certificate

Figures as on 22 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A wingNA65808
B WingNA5518018

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 22 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 95%.

A wing78%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B Wing76%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area624 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Oct 2024

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI1263.93
Proposed, not sanctioned936 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchS V Road, Santacruz West Mumbai
Estimated costRs 5.70 cr
Cost incurredRs 2.69 cr
Work done47.27%
BuildingWingEstimatedIncurred
A wingNARs 1.93 crRs 1.35 cr
B WingNARs 1.93 crRs 1.35 cr
-NARs 1.84 cr-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectObaid Pettiwala The Design Studio
ArchitectSohil Hajiani
EngineerFurkaan Pettiwala FRAMES
Chartered AccountantSandip Yajnik & Associates
Chartered AccountantB M Chauhan & Company
Chartered AccountantRSPH and Associates
PartnerRole in project
HUSAIN TAHER PATNI-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800012362Jun 2022 → Jun 2023

Reason as filed by the promoterDue to covid-19pandemic/lockdown and also there was a shortage of labour therefore so the construction work has been delayed estimated time frame, so we require more time to complete the project .

EXT51800016719Jun 2022 → Dec 2023

Reason as filed by the promoterThere is unexpected delay on account of receiving permissions from the competent authorities. And after Covid the material supply chain is disrupted and we are trying over level best to complete the work faster.

EXT51800024857Jun 2022 → Dec 2025

Reason as filed by the promoterDue to COVID-19, the regular flow of work was hampered and there was shortage of labour. Also, there are limitations in construction on daily basis due to residential area which hampers continue of work on regular basis. Also, please refer to our attached detailed request letter.

EA07032620131Jun 2022 → Dec 2026

Reason as filed by the promotera) As the entire country including Mumbai Suburban were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to curb the spread of the COVID-19. In view of the curbs and measures imposed by the Governments, I stopped work till such time as the said lockdowns, curbs and measures were relaxed by the respective Governments. b) Inspite of best efforts, the said project was adversely affected due to unprecedented COVID-19 Pandemic which lasted for more than 2 years and are st

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Sep 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Sep 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Sep 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed125

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 125 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Hill Casa Architect Certificate March 2026.pdf22 May 2026
Withdrawal Update Form 2File: Hill Casa Engineer Certificate March 2026 .pdf22 May 2026
Withdrawal Update Form 3File: Hill Casa CA Certificate March 2026.pdf22 May 2026
Form 1File: AR-Sep-2024.pdf14 Mar 2026
Form 2File: ER-Sept-2024.pdf14 Mar 2026
Form 3File: CA-Sept-2024.pdf14 Mar 2026
Disclosure of Sold and Booked InventoryFile: Dislosure-Sept-2024.pdf14 Mar 2026
Form 2A (FY 2018-2019)File: Form 2A - March 19 .pdf14 Mar 2026
Form 2A (FY 2019-2020)File: Form 2A - March 20 .pdf14 Mar 2026
Form 2A (FY 2020-2021)File: Form 2A - March 21 .pdf14 Mar 2026
Form 2A (FY 2021-2022)File: Form 2A - March 22 .pdf14 Mar 2026
Form 2A (FY 2022-2023)File: Form 2A - March 23 .pdf14 Mar 2026
Form 2A (FY 2023-2024)File: Form 2A - March 24 .pdf14 Mar 2026
Form 2A (FY 2024-2025)File: Form 2A - March 25 .pdf14 Mar 2026
Form 5 (FY 2022-2023)File: RA Audit Signed copy 22-23.pdf14 Mar 2026
Form 5 (FY 2023-2024)File: RA Audit Signed copy 23-24.pdf14 Mar 2026
Form 5 (FY 2019-2020)File: 2019-20.pdf14 Mar 2026
Form 5 (FY 2018-2019)File: 2018-19.pdf14 Mar 2026
Form 5 (FY 2020-2021)File: 2020-21.pdf14 Mar 2026
Form 5 (FY 2021-2022)File: 2021-22.pdf14 Mar 2026
Form 5 (FY 2024-2025)File: RERA Audit Report FY 24-25.pdf13 Mar 2026
Form 2File: ER - December 2024.pdf16 Feb 2026
Form 3File: CA Certificate Dec 2024.pdf16 Feb 2026
Form 1File: AR - Dec 24.pdf16 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Dec 2024.pdf16 Feb 2026
Form 1File: AR - March 25.pdf16 Feb 2026
Form 2File: ER - March 25 .pdf16 Feb 2026
Form 3File: CA Certificate March 2025.pdf16 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure March 2025.pdf16 Feb 2026
Form 1File: AR - June 25.pdf16 Feb 2026
Form 2File: ER - June 25 .pdf16 Feb 2026
Form 3File: CA Certificate June 2025.pdf16 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure June 2025.pdf16 Feb 2026
Form 1File: AR - Sep 25.pdf16 Feb 2026
Form 2File: ER - Sept 25 .pdf16 Feb 2026
Form 3File: CA Certificate Sep 2025.pdf16 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Sept 2025.pdf16 Feb 2026
Form 1File: AR - Dec 25.pdf16 Feb 2026
Form 2File: ER - Dec 25 .pdf16 Feb 2026
Form 3File: CA Certificate Dec 2025.pdf16 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Dec 2025.pdf16 Feb 2026
Disclosure of sold/ booked inventoryFile: document_1.pdf23 Oct 2024
Declaration in FORM BFile: Form B-Hill Casa.pdf21 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: 0408 Further CC Approval.pdf21 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RA Audit Signed copy 22-23.pdf21 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RA Audit Signed copy 23-24.pdf21 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1-Architect Certificate.pdf11 Oct 2024
Certificates of CA (Form 3)File: Rera Quarterly Certificate (2).pdf11 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2-Engineer Certificate.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certiifcate -A- June 2023.pdf31 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certiifcate -B- June 2023.pdf31 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certiifcate -A- Sept 2023.pdf31 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certiifcate -B- Sept 2023.pdf31 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certiifcate -A- Sept 2023.pdf31 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certiifcate -B- Sept 2023.pdf31 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certiifcate -A- March 2024.pdf31 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certiifcate -B- March 2024.pdf31 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certifiacte - June 2023.pdf31 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certifiacte - Sept 2023.pdf31 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certifiacte - Dec 2023.pdf31 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certifiacte - March 2024.pdf31 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assuarnce Certiifcate - March 2023.pdf31 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assuarnce Certiifcate - March 2024.pdf31 Jul 2024
Certificates of CA (Form 3)File: CA Certiifcate - June 2023.pdf31 Jul 2024
Certificates of CA (Form 3)File: CA Certiifcate - Sept 2023.pdf31 Jul 2024
Certificates of CA (Form 3)File: CA Certiifcate - Sept 2023.pdf31 Jul 2024
Certificates of CA (Form 3)File: CA Certiifcate - March 2024.pdf31 Jul 2024
Declaration in FORM BFile: Form B.pdf12 Jun 2023
Declaration in FORM BFile: corrected form B.pdf8 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate A wing_compressed.pdf17 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate B wing_compressed.pdf17 May 2023
Certificates of CA (Form 3)File: CA Certificate - 1.pdf17 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch certificate A wing.pdf13 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch certificate B Wing.pdf13 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng certificate_compressed.pdf13 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi Certificate - 2018-19.pdf7 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi Certificate - 2019-20.pdf7 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi Certificate - 2020-21.pdf7 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi Certificate - 2021-22.pdf7 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi Certificate - Dec 22.pdf7 Apr 2023

How this compares with Mumbai Suburban

15%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 54 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Hill Casa on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BANDRA6,700+ in Mumbai Suburban

2 kmHill CasaCompleted 84Lapsed / revoked 42Other 118Dot size: filed unitsN

Filed coordinates, straight-line distance. 244 registered projects within 2 km.

Builder: HUSAIN TAHER PATNI

HUSAIN TAHER PATNI has 1 registration on MahaRERA, including Hill Casa. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Hill Casa is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Hill Casa?

The registered promoter entity is HUSAIN TAHER PATNI, an individual as per the filing. Its GSTIN 27ALLPP8191R1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Hill Casa?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Hill Casa?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Hill Casa?

The professionals named in the filing: Architect: Obaid Pettiwala The Design Studio; Architect: Sohil Hajiani; Engineer: Furkaan Pettiwala FRAMES; Chartered Accountant: Sandip Yajnik & Associates; Chartered Accountant: B M Chauhan & Company; Chartered Accountant: RSPH and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Hill Casa?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Hill Casa. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Hill Casa to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.