Registration lapsed No litigation declared Residential / Group Housing project

HARIKUNJ

By DEEPAK RADHESHYAM JHUNJHUNWALA

RG-MH-00461 · RERA P51500000992 · Last updated on MahaRERA portal: 13 Dec 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 19 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Mar 2025Possession promised19 months past this date
50 of 77Construction stages doneacross 7 buildings; furthest along: Staircases, 80%
87 of 161Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

HARIKUNJ is a Residential / Group Housing project by DEEPAK RADHESHYAM JHUNJHUNWALA in Aurangabad, Maharashtra, registered with MahaRERA as P51500000992 on 25 Jul 2017. Possession was promised by 30 Mar 2025 and is now 19 months past that date. 74 of the 161 units on this registration are recorded sold or booked, and 50 of 77 construction stages are filed complete.

At a glance

Project

  • NameHARIKUNJ
  • TypeResidential / Group Housing
  • Location
    • Paithan Road
    • Farola
    • Paithan
    • Aurangabad
    • 431105
  • Pincode431105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500000992
  • ReraGenie IDRG-MH-00461

Builder

  • NameDEEPAK RADHESHYAM JHUNJHUNWALA
  • Entity typeIndividual

Key dates

19 months past promisethis monthRegisteredJul 2017PromisedMar 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on25 Jul 2017
  • Promised completion30 Mar 2025
  • Revised completionNone
  • Buildings7 building records
  • Documents filed73 files

Current status

46%74 of 161 units booked

Figures as on 13 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROW HOUSE BUILDING ANA2216016
ROW HOUSE BUILDING BNA2216016
ROW HOUSE BUILDING CNA22808
ROW HOUSE BUILDING DNA2211011
ROW HOUSE BUILDING ENA2214014
BUILDING FNA9448048
BUILDING GNA9448048

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 13 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

50 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Staircases, at 80%.

ROW HOUSE BUILDING A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE BUILDING B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE BUILDING C71%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
ROW HOUSE BUILDING D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE BUILDING E9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING F29%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor20%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING G91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 13 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes50%
Open ParkingYes50%

Parking filed145

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots145
Closed/Covered8
Open Space137
BuildingClosed/CoveredOpen SpaceTotal
ROW HOUSE BUILDING A01616
ROW HOUSE BUILDING B01616
ROW HOUSE BUILDING C088
ROW HOUSE BUILDING D01111
ROW HOUSE BUILDING E01414
BUILDING F43640
BUILDING G43640

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,120 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Dec 2025

Approvals and building plan

Sanctioning authorityTown Planning and Valuation Department, Aurangabad
Permissible FSI7460.54
Proposed, not sanctioned7,461 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOPPOSITE DISTRICT COURT RAGHUVIR COMPLEX AURANGABAD MS

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGANESH MHAROLKAR
EngineerPRADEEP V MOTE
Chartered AccountantMayur Bamb and Associates
Chartered AccountantAmol Kala and Associates
PartnerRole in project
DEEPAK RADHESHYAM JHUNJHUNWALA-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: 1 Form-1 Mar 25.pdf13 Dec 2025
Form 2File: 2 Form-2 Mar 25.pdf13 Dec 2025
Form 3File: 3 Form-3 Mar 25.pdf13 Dec 2025
Disclosure of Sold and Booked InventoryFile: 4 SOLD Mar 25.pdf13 Dec 2025
OthersFile: 5 Form-2A Mar 25.pdf13 Dec 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM F HARIKUNJ FY - 23-24.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 01 DATE 01 MARCH 24.pdf29 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 01 DATE -01 JUN - 24.pdf29 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 01 DATE 01 - SEP -24.pdf29 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 01 01 DEC 24.pdf29 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM -02 DATE -10-04-24.pdf29 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM -02 DATE- 15 -07 -24.pdf29 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM -02 DATE-19-10-24.pdf29 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM -02 DATE -10-01-25.pdf29 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM - 2A DATE - 15-07-22.pdf29 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM - 2A -DATE - 10-06-23.pdf29 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM - 2A - DATE - 12-08-24.pdf29 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 Form 1 - Architect's Mar-20.pdf10 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2 Form 1 - Architect's Mar-21.pdf10 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3 Form 1 - Architect's Mar-22.pdf10 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4 Form 1 - Architect's Mar-23.pdf10 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5 Form 1 - Architect's Jun-23.pdf10 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 6 Form 1 - Architect's Sep-23.pdf10 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7 Form 1 - Architect's Dec-23.pdf10 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1 Form 2 - Engineer's Mar-20.pdf10 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 Form 2 - Engineer's Mar-21.pdf10 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 Form 2 - Engineer's Mar-22.pdf10 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5 Form 2 - Engineer's Jun-23.pdf10 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5 Form 2 - Engineer's Jun-23.pdf10 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6 Form 2 - Engineer's Sep-23.pdf10 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 7 Form 2 - Engineer's Dec-23.pdf10 Apr 2024
Certificates of CA (Form 3)File: Form 3 Feb 2024.pdf28 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 FY 2019-20.pdf13 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 FY 2020-21.pdf13 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 FY 2021-22.pdf13 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 FY 2022-23.pdf13 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form2A Q1 2019-20.pdf15 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form2A Q2 2019-20.pdf15 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form2A Q3 2019-20.pdf15 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form2A Q4 2019-20.pdf15 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Q1 2020-21.pdf15 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Q2 2022-21.pdf15 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Q3 2020-21.pdf15 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Q4 2020-21.pdf15 Aug 2021
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked unsold.pdf15 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 17-18.pdf15 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2018-19.pdf15 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-20.pdf15 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate 18072017.pdf19 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 18072017.pdf19 Jul 2017
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE 18072017.pdf19 Jul 2017
Building plan approvalFile: 1 SHEET OF BUILDING PERMISSION.pdf13 Jul 2017
Building plan approvalFile: 2 SHEET OF BUILDING PERMISSION.pdf13 Jul 2017
Building plan approvalFile: 3 SHEET OF BUILDING PERMISSION.pdf13 Jul 2017
Building plan approvalFile: 4 SHEET OF BUILDING PERMISSION.pdf13 Jul 2017
Building plan approvalFile: 5 SHEET OF BUILDING PERMISSION.pdf13 Jul 2017
Building plan approvalFile: 6 SHEET OF BUILDING PERMISSION.pdf13 Jul 2017
Building plan approvalFile: 7 SHEET OF BUILDING PERMISSION.pdf13 Jul 2017
Layout approvalFile: DEMARCATED LAYOUT.pdf13 Jul 2017
Copy of Layout Approval (in case of layout)File: DEMARCATED LAYOUT.pdf13 Jul 2017
Building Plan Approval (IOD)File: 1 SHEET OF BUILDING PERMISSION.pdf13 Jul 2017
Building Plan Approval (IOD)File: 2 SHEET OF BUILDING PERMISSION.pdf13 Jul 2017
Building Plan Approval (IOD)File: 3 SHEET OF BUILDING PERMISSION.pdf13 Jul 2017
Building Plan Approval (IOD)File: 4 SHEET OF BUILDING PERMISSION.pdf13 Jul 2017
Building Plan Approval (IOD)File: 5 SHEET OF BUILDING PERMISSION.pdf13 Jul 2017
Building Plan Approval (IOD)File: 6 SHEET OF BUILDING PERMISSION.pdf13 Jul 2017
Building Plan Approval (IOD)File: 7 SHEET OF BUILDING PERMISSION.pdf13 Jul 2017
Declaration in FORM BFile: FORM B OF RERA.pdf13 Jul 2017
Details of encumbrancesFile: ECUMBRENCE SELF CERTIFICATE.pdf12 Jul 2017
PAN CardFile: PAN CARD DRJ.pdf11 Jul 2017
Proforma of Allotment letterFile: agreemenmt to sale.pdf11 Jul 2017
Copy of the legal title reportFile: title search report harikunj.pdf10 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: tp commencement certificate.pdf10 Jul 2017

How this compares with Aurangabad

46%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep HARIKUNJ on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Farola1,400+ in Aurangabad

Builder: DEEPAK RADHESHYAM JHUNJHUNWALA

DEEPAK RADHESHYAM JHUNJHUNWALA has 1 registration on MahaRERA, including HARIKUNJ. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that HARIKUNJ shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if HARIKUNJ is delayed beyond 30 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HARIKUNJ?

The registered promoter entity is DEEPAK RADHESHYAM JHUNJHUNWALA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HARIKUNJ?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for HARIKUNJ?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HARIKUNJ?

The professionals named in the filing: Architect: GANESH MHAROLKAR; Engineer: PRADEEP V MOTE; Chartered Accountant: Mayur Bamb and Associates; Chartered Accountant: Amol Kala and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HARIKUNJ?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HARIKUNJ. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HARIKUNJ to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.