Home / Browse projects / Pune, Maharashtra / HAPPYCITY VARALE

Registration lapsed No litigation declared Residential / Group Housing project

HAPPYCITY VARALE

By NAMRATA DEVELOPERS PVT. LTD

RG-MH-89704 · RERA P52100018045 · Last updated on MahaRERA portal: 11 Nov 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 46 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2022Possession promised46 months past this date
20 of 33Construction stages doneacross 3 buildings; furthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 133 documents Report an error

HAPPYCITY VARALE is a Residential / Group Housing project by NAMRATA DEVELOPERS PVT. LTD in Pune, Maharashtra, registered with MahaRERA as P52100018045 on 10 Oct 2018. Possession was promised by 30 Dec 2022 and is now 46 months past that date.

At a glance

Project

  • NameHAPPYCITY VARALE
  • TypeResidential / Group Housing
  • Location
    • Talegaon-Ambi Road
    • Varale Phata
    • Talegaon Dabhade (R)
    • Mawal
    • Pune
    • 410507
  • Pincode410507
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100018045
  • ReraGenie IDRG-MH-89704

Builder

  • NameNAMRATA DEVELOPERS PVT. LTD
  • Entity typeCompany
  • CINU70100PN1996PTC177310
  • GSTIN27AAACN5455H1ZE
  • Managing DirectorSHAILESH KANTILAL SHAH
  • Other registrations3 more →
  • Completed3 of 4
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

46 months past promisethis monthRegisteredOct 2018PromisedDec 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on10 Oct 2018
  • Promised completion30 Dec 2022
  • Revised completionNone
  • Buildings3 building records
  • Documents filed133 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A BUILDINGNA130000
C BUILDINGNA130000
E BUILDINGNA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 11 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 0%.

A BUILDING0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C BUILDING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E BUILDING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 11 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed70

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots70
Closed/Covered70
BuildingClosed/CoveredTotal
A BUILDING1818
C BUILDING3636
E BUILDING1616

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,907 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
Rajashree Group of CompaniesWakadPune
Rajnandini AssociatesWakadPune
Ravindra Pandharinath KalokheTalegaon Dabhade (R)Pune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority Pune
Permissible FSI22637.41
Proposed, not sanctioned18,533 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOffice No 101, 102, First Floor, Next Gen Avenue, Bahiratwadi, Off Senapati Bapat Road, Pune 411016

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA Design Studio
PartnerRole in project
NAMRATA DEVELOPERS PVT. LTD-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Sep 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Sep 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Sep 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Sep 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Jan 2023

Documents filed133

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 133 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Happycity Varale Form_4_C and E BLDG_26042024.pdf11 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold_Booked Inventory_08112024.pdf11 Nov 2024
Certificates of CA (Form 3)File: 3543_001.pdf4 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: HCV Form1_29102024.pdf29 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Happycity Varale Engg Certificate_29102024.pdf29 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: HCV_ACE BLDG_Form 5_FY 2023_24.pdf22 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: HCV_Engg Cert Form 2_June 2023.pdf11 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: HCV_Engg Cert Form 2_Sept 2023.pdf11 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: HCV_Engg Cert Form 2_Dec 2023.pdf11 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: HCV Engg Certificate_March 2024.pdf11 Jun 2024
Certificates of CA (Form 3)File: HCV CA Certificate_June 2023.pdf11 Jun 2024
Certificates of CA (Form 3)File: HCV CA Certificate_Sept 2023.pdf11 Jun 2024
Certificates of CA (Form 3)File: HCV_CA Certificate_Dec 2023.pdf11 Jun 2024
Certificates of CA (Form 3)File: HCV_CA _March 2024.pdf11 Jun 2024
Certificates of CA (Form 3)File: RERA HAPPYCITY VARALE AS ON 311221_compressed.pdf3 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Dec 2021.pdf28 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: HCV_Architect Cert_Form1_Sept 2022.pdf28 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: HCV_Architect Cert_Form1_Dec 2022.pdf28 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: HCV_Architect Cert_Form1_March 2023.pdf28 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: HCV_Architect Cert_Form1_June 2023.pdf28 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: HCV_Architect Cert_Form1_Sept 2023.pdf28 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: HCV_Architect Cert_Form1_Dec 2023.pdf28 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: HCV_Architect Cert_March 2024.pdf28 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: HCV_Engg Certificate_June 2019.pdf28 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: HCV_Engg Certificate_Sept 2019.pdf28 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: HCV_Engg Certificate_March 2020.pdf28 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: HCV_Engg Certificate_Form 2_June 2020.pdf28 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: HCV Engg Cert_DEc 2021.pdf28 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: HCV_Engg Certificate_Sept 2022.pdf28 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: HCV_Engg Certificate_Dec 2022.pdf28 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: HCV_Engg Certificate_March 2023.pdf28 May 2024
Certificates of CA (Form 3)File: HCV_CA Certificate_Dec 2018.pdf28 May 2024
Certificates of CA (Form 3)File: HCV_CA Cert_June 2019.pdf28 May 2024
Certificates of CA (Form 3)File: HCV_CA Certificate_Sept 2019.pdf28 May 2024
Certificates of CA (Form 3)File: HCV_CA Certificate_March 2020.pdf28 May 2024
Certificates of CA (Form 3)File: HCV_CA Certificate_June 2020.pdf28 May 2024
Certificates of CA (Form 3)File: HCV_CA Certificate_June 2021.pdf28 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: HCV Engg Certificate_March 2024.pdf20 May 2024
Certificates of CA (Form 3)File: HCV_CA _March 2024.pdf20 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Happycity Varale_Form 2A_2019-20.pdf6 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Happycity Varale_Form 2A_2020-21.pdf6 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Happycity Varale_Form 2A_2021-22.pdf6 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Happycity Varale_Form 2A_2022-23.pdf6 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Happycity Varale Form 5 FY 2022_23.pdf30 Jan 2024
Certificates of CA (Form 3)File: RERA HAPPY CITY VARALE_12052023.pdf15 May 2023
Disclosure of sold/ booked inventoryFile: Happycity Varale Sold and unsold inventory_09052023.pdf12 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Happycity Varale Form 5 _2021-22_compressed.pdf6 Mar 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Happy City varale OC.pdf19 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Happycity Varale Arch Cert-June 2022 New.pdf17 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: HCV Engg Small June 2022.pdf17 Aug 2022
Certificates of CA (Form 3)File: Happycity Varale CA June 2022.pdf17 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Happycity Varale Arch Certificate_March 2022_compressed.pdf6 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: HCV Engineers Certificate 31 march 2022_compressed.pdf6 May 2022
Certificates of CA (Form 3)File: Happycity Varale CA Cert_MArch 2022.pdf6 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: HCV Architect Cert_March 2022_compressed.pdf21 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Happycity Varale Form 5.pdf10 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Happy City Varale (1).pdf3 Feb 2022
Certificates of CA (Form 3)File: Happy City Varale Annexure D (1).pdf3 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Happycity Varale Arch Cert_Sept 2021.pdf9 Nov 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Happycity Varale Engg Certificate_Sept 2021.pdf9 Nov 2021
Certificates of CA (Form 3)File: Happycity Varale CA Cert_Sept 2021.pdf9 Nov 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Happycity Varale engg certifiacte_July 2021.pdf24 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: HappyCity Varale_Architect Cert_June 2021.pdf9 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Happy City Varale Architect Certificate 31 march 2021.pdf15 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Happy City Varale Engineers certificate 31-03-2021.pdf15 Jun 2021
Certificates of CA (Form 3)File: CA Certificate_Happycity Varale March 2021.pdf15 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Happycity Varale CA Certifiacte Form 5.pdf25 Mar 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Happycity Varale Rera Architect Cert-Form 1_Dec 2020 .pdf22 Jan 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Happycity Varale Engg Cert_Dec 2020.pdf22 Jan 2021
Certificates of CA (Form 3)File: CA Certificate - Happycity Varale_Dec 2020.pdf22 Jan 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Happycity Varale Architect Certifiacte_Sept 2020.pdf22 Oct 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Happycity Varale Engg Certificate_Sept 2020.pdf22 Oct 2020
Certificates of CA (Form 3)File: Happycity Varale CA Certificate_Sept 2020.pdf22 Oct 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Varale_March_Min.pdf20 Jul 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Varale_June_Min.pdf20 Jul 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Happycity Varale Engg Certificate_Dec 2019 (1).pdf13 Jan 2020
Certificates of CA (Form 3)File: CA PArt1.pdf13 Jan 2020
Certificates of CA (Form 3)File: Ca Part 2.pdf13 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Happycity Varale Architect Cert-Dec 2019.pdf9 Jan 2020
Certificates of CA (Form 3)File: Happycity Varale CA Certificate_Sept 2019 (1).pdf31 Oct 2019

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
WEEKENDER BIRDS VIEWSURVEY NO 117-2 VIL-KHADKALE TAL.-MAVAL DIST. - PUNE258CompletedDec 2017Late, Jul 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep HAPPYCITY VARALE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Varale Phata13,700+ in Pune

2 kmHAPPYCITY VARALECompleted 37Lapsed / revoked 24Other 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 100 registered projects within 2 km.

Builder: NAMRATA DEVELOPERS PVT. LTD

NAMRATA DEVELOPERS PVT. LTD has 4 registrations on MahaRERA, including Namrata Eco City 2.0 and WEEKENDER BIRDS VIEW. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that HAPPYCITY VARALE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if HAPPYCITY VARALE is delayed beyond 30 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HAPPYCITY VARALE?

The registered promoter entity is NAMRATA DEVELOPERS PVT. LTD, a company as per the filing. Its CIN U70100PN1996PTC177310 and GSTIN 27AAACN5455H1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HAPPYCITY VARALE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for HAPPYCITY VARALE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HAPPYCITY VARALE?

The professionals named in the filing: Architect: A Design Studio. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HAPPYCITY VARALE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HAPPYCITY VARALE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HAPPYCITY VARALE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.