Registration lapsed No litigation declared Others project

GREEN WORLD

By AKSHAR SPACE PVT LTD

RG-MH-19913 · RERA P51700003889 · Last updated on MahaRERA portal: 18 Jan 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 82 months past the filed date
  • 85 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2019Possession promised82 months past this date
64 of 121Construction stages doneacross 11 buildings; furthest along: Internal walls, 90%
85Complaints at MahaRERAon this registration
Jump to the 25 documents Report an error

GREEN WORLD is a Others project by AKSHAR SPACE PVT LTD in Thane, Maharashtra, registered with MahaRERA as P51700003889 on 6 Aug 2017. Possession was promised by 31 Dec 2019 and is now 82 months past that date. 85 complaints are on record with the regulator.

At a glance

Project

  • NameGREEN WORLD
  • TypeOthers
  • Location
    • Thane (M Corp.)
    • Thane
    • 400708
  • Pincode400708
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700003889
  • ReraGenie IDRG-MH-19913

Builder

  • NameAKSHAR SPACE PVT LTD
  • Entity typeCompany

Key dates

82 months past promisethis monthRegisteredAug 2017PromisedDec 2019

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on6 Aug 2017
  • Promised completion31 Dec 2019
  • Revised completionNone
  • Buildings11 building records
  • Documents filed25 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B WINGNA240000
C WINGNA240000
D WINGNA240000
H WINGNA240000
I WINGNA230000
A1 WINGNA240000
E WINGNA240000
A2 WINGNA240000
F WINGNA240000
G WINGNA240000
SHOPSNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building11

As on 18 Jan 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

64 of 121 construction stages are filed complete across 11 buildings. The stage furthest along is Internal walls, at 90%.

B WING79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
C WING79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
D WING79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
H WING79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
I WING79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
A1 WING79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
E WING79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
A2 WING79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
F WING79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
G WING79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
SHOPS73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Progress on shared amenities15

As on 18 Jan 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes75%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes85%
Street LightingYes0%
Community BuildingsYes80%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes80%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes90%

Parking filed277

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots277
Closed/Covered145
Open Space132
BuildingClosed/CoveredOpen SpaceTotal
B WING172239
C WING172239
D WING182240
H WING162238
I WING142236
A1 WING808
E WING162238
A2 WING606
F WING17017
G WING16016

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area34,817 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
MOUNT MARY BUILDERSThane (M Corp.)Thane

Approvals and building plan

Permissible FSI52225.5
Proposed, not sanctioned52,226 sq m
Buildings approved11
Buildings sanctioned11

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchANNEXE- SECTOR - 17, VASHI, NAVI MUMBAI

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectStellar Design Studio
ArchitectSatish Ahuja & Associates
ArchitectArunkumar Landscape Architect Pvt. Ltd.
EngineerStructural Concept Designs Pvt. Ltd.
PartnerRole in project
AKSHAR SPACE PVT LTD-

Litigation declared1

CaseCourtStatus
116/2014/2014Honourable Thane CourtAMENDED PLAINT

Complaints filed with MahaRERA85

Case no.ComplainantRespondentFiled
CC006000000055144Pritam Vilas MurudkarM/s Mount Mary Builders26/07/2018
CC006000000000089VENKATA PHANINDRA KUMAR VALLURIM/S AKSHAR SPACE PRIVATE LIMITED30/09/2017
CC006000000057099KARUNAKAR GOVIND SHETTYGREEN WORLD DEVELOPERS PVT. LTD.29/11/2018
CC006000000057103RATNAKAR GOVIND SHETTYMount Mary Builders30/11/2018
CC006000000057112KARUNAKAR GOVIND SHETTYMOUNT MARY BUILDERS30/11/2018
CC006000000089795SANA HOSPITALITY SERVICES PVT. LTD.SUSHILA SURESHBABU MALGE, PROPRIETOR OF MOUNT MARY BUILDERS19/06/2019
CC006000000054976DR. CHARUSHEELA ASHWIN GAJRAM/S MOUNT MARY BUILDERS PVT LTD AND AKSHAR SPACE PVT LTD18/06/2018
CC006000000000977Ramesh P SinghM/S AKSHAR SPACE PVT LIMITED30/09/2017
CC006000000000733SANDIP NAMDEO SHERKARAksharSpace Pvt ltd.30/09/2017
CC006000000000987Somaji KubalAkshar Space Pvt Ltd30/09/2017
CC006000000000870Abhijit JadhavM/S Akshar Space Private Limited30/09/2017
CC006000000000950HARSH KURRA & NEETU KURRAM/SAKSHAR SPACE PRIVATE LIMITED30/09/2017
CC006000000000985P V S S VARMAAkshar Space Pvt. Ltd30/09/2017
CC006000000001014Lalit BhosaleM/s Akshar Space Pvt Ltd11/10/2017
CC006000000001092Deepa DalviMount mary builders & Akshar21/05/2018
CC006000000001737Richa AgrawalM/s Mount Mary Builders20/12/2017
CC006000000012758P SatyanarayanAkshar Space Pvt Ltd09/01/2018
CC006000000001294Prashant PandeyMount Mary Builders11/08/2018
CC006000000078624Prashant PandeyMount Mary Builders23/03/2019
CC006000000001407HARVINDAR SINGH GAMBHIRM/s AKSHAR SPACE PVT. LTD.26/10/2017
CC006000000001573Dhansukhlal K. MorabiaAkshar Space Pvt.Ltd.30/10/2017
CC006000000001581Rajesh Ramchandra MahadikAkshar Space Pvt. Ltd30/10/2017
CC006000000001586Amit Shankar BhalotiaAkshar Space pvt. ltd30/10/2017
CC006000000001597Rajkishor RajakMRS. Sushila Sureshbabu Malge10/11/2017
CC006000000001720Sayee SubramanianAkshar Space Private Limited17/05/2018
CC006000000055452Sayee SubramanianAkshar Space Private Limited26/07/2018
CC006000000012669Manojkumar Lalbahadur SinghHari B Mujat of Akshar Space Pvt Ltd.29/12/2017
CC006000000012750Nitin J JaigudeAkshar Space Pvt Ltd09/06/2018
CC006000000022905Farzana ShaikhAkshar Space pvt ltd16/03/2018
CC006000000022920Vishal BhosaleAkshar SpacePvt. Ltd.05/03/2018
CC006000000022978Souvik DasAkshar Space Pvt Ltd18/01/2018
CC006000000023649Shrikant MuthineniMount Mary01/04/2018
CC006000000023859Deepak AnandAkshar space pvt. ltd. & mount mary builders23/03/2018
CC006000000023844Possession delayedM/S.MOUNT MARY BUILDERS29/04/2018
CC006000000023887Niladri SenHari B. Mujat for Akshar Space Pvt Ltd06/10/2018
CC006000000023869Varghese SamuelM/s Mount Mary Builders and M/s Akshar Space Pvt Ltd23/06/2018
CC006000000023880Tirupati KodariSURESH BABU MALGE - MOUNT MARY BUILDER25/06/2018
CC006000000054842Aditi MazumderMount Mary Builders & akshar Space Pvt Ltd09/06/2018
CC006000000195420Sandeep DagaAkshar Space Private Limited28/12/2020
CC006000000055516CC006000000055516sureshbabu ganpat malge13/08/2018
CC006000000054816ABODH KUMAR PATHAK AND ANUPAMA A PATHAKM/S MOUNT MARY BUILDERS07/06/2018
CC006000000054663Vinod KanjanMount Mary Builders & Akshar Space Pvt Ltd29/05/2018
CC006000000054837RAMESH JADHAVmount mary builders & akshar space pvt ltd08/06/2018
CC006000000054969VISHAL NALKURMount Mary Builders & Akshar Space Pvt Ltd17/06/2018
CC006000000054995manoj kumar singhmount mary builders & akshar space pvt ltd19/06/2018
CC006000000055000Mr. Irfan GoundiMount mary builders & Akshar Space pvt ltd20/06/2018
CC006000000055006Prathamesh Vijay TernikarAkshar Space Pvt Ltd20/06/2018
CC006000000055015Pranav Sawantmount mary builders22/06/2018
CC006000000055254ASHISH KESHAVPRASAD CHATURVEDIMRS SUSHILA SURESHBABU MALGE OF M/S MOUNT MARY BUILDERS05/07/2018
CC006000000055331Mr. Ramdas DateMr. Sureshbhau Malge22/07/2018
CC006000000055342Reshma Ritesh ShettyMount Mary Builders and Akshar Space Pvt Ltd13/07/2018
CC006000000055426Anis Abdul Kader KhanM/s Mount Mary Builders21/07/2018
CC006000000110676Anis Abdul Kader KhanMount Marry Builders03/09/2019
CC006000000055404Mr.Samson PandiAkshar Space Pvt.Ltd.19/07/2018
CC006000000055418Patel Anjali Suryaprakash ReddySURESH BABU MALGE-MOUNT MARY BUILDERS21/07/2018
CC006000000055476JITENDRA SWARNKARHARI B MUJAT23/07/2018
CC006000000055774Narendra KumarMount Mary Builders16/08/2018
CC006000000056366Rohan TadkeMount Mary Builders28/09/2018
CC006000000056364zahid patelmount mary developers29/09/2018
CC006000000057363Amit KiteyMr Sureshbabu Malge - Mount Mary Builders18/12/2018

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 18 Jan 2023

Documents filed25

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.pdf18 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Architect Completion Certificate.pdf18 Jan 2023
Certificates of CA (Form 5)File: FORM 5 greenworld.pdf14 Oct 2019
Certificates of CA (Form 5)File: akshar space Pvt Ltd From 5.pdf15 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1.pdf17 Aug 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf17 Aug 2018
Certificates of CA (Form 3)File: Form 3.pdf16 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: From-1 Architect Certificate 2-4-18.pdf10 Apr 2018
Certificates of CA (Form 3)File: FORM 3 - GREEN WORL - FEB 18.pdf29 Mar 2018
Layout approvalFile: Layout Plan with Phases.pdf31 Jul 2017
PAN CardFile: MALGE PAN.pdf31 Jul 2017
Details of encumbrancesFile: DETAILS_OF_ENCUMBRANCES_FINAL.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Plan with Phases.pdf31 Jul 2017
Declaration in FORM BFile: Form B - Affidavit Rev-compressed.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: From-1 Architect Certificate New.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate - Revised.pdf31 Jul 2017
Certificates of CA (Form 3)File: Revised_Form_3_MOUNT_MARY.pdf31 Jul 2017
Certificates of CA (Form 3)File: FORM_3_GW_REVISED.pdf31 Jul 2017
Proforma of Allotment letterFile: RERA_AGREEMENT_-_FINAL_DRAFT_GW.pdf31 Jul 2017
Building plan approvalFile: CC PLAN MERGED-compressed.pdf27 Jul 2017
Copy of the legal title reportFile: Title Report.pdf27 Jul 2017
Building Plan Approval (IOD)File: CC PLAN MERGED-compressed.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: C C-GW-compressed.pdf26 Jul 2017
Proforma of Allotment letterFile: Allotment Letter-Green World - RERA DRAFT-GW.pdf26 Jul 2017
PAN CardFile: AKSHAR SPACE PVT LTD_PAN CARD.pdf22 Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GREEN WORLD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Thane (M Corp.)7,600+ in Thane

2 kmGREEN WORLDCompleted 7Lapsed / revoked 2Other 17Dot size: filed unitsN

Filed coordinates, straight-line distance. 26 registered projects within 2 km.

Builder: AKSHAR SPACE PVT LTD

AKSHAR SPACE PVT LTD has 1 registration on MahaRERA, including GREEN WORLD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that GREEN WORLD shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if GREEN WORLD is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GREEN WORLD?

The registered promoter entity is AKSHAR SPACE PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GREEN WORLD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GREEN WORLD?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for GREEN WORLD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GREEN WORLD?

The professionals named in the filing: Architect: Stellar Design Studio; Architect: Satish Ahuja & Associates; Architect: Arunkumar Landscape Architect Pvt. Ltd.; Engineer: Structural Concept Designs Pvt. Ltd.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GREEN WORLD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GREEN WORLD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GREEN WORLD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.