Green Park
RG-MH-77840 · RERA P52100051621 · Last updated on MahaRERA portal: 17 Jul 2025
Source: official MahaRERA filing
Red flags
- Completion date moved by 5 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Green Park is a Residential / Group Housing project by Classic Developers in Pune, Maharashtra, registered with MahaRERA as P52100051621 on 27 Jun 2023. The registration is recorded completed; possession was promised by 31 May 2025. The completion date has moved by 5 months from the original filing. 28 of the 28 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.
At a glance
Project
- NameGreen Park
- TypeResidential / Group Housing
- Location
- Moshi Alandi Road
- B. K. Park
- Dudulgaon
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 412105
- Pincode412105
- RERA no.P52100051621
- ReraGenie IDRG-MH-77840
Builder
- NameClassic Developers
- Entity typePartnership
- GSTIN27AASFC1020G1ZQ
- PartnersMrs Anuradha Prakash Salvi, Mr Hirachand Mahadev Shinde, Mrs Manoja Manik Gaikwad, Mrs Neeta Mahendrasingh Thakur
- Other registrations3 more →
- Completed2 of 4
- No longer live2 lapsed, de-registered or revoked
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on27 Jun 2023
- Promised completion31 May 2025
- Revised completionRevised to 31 May 2025 (originally 31 Dec 2024)
- Buildings1 building record
- Documents filed101 files
Current status
Figures as on 17 Jul 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Green Park | NA | 7 | 7 | 28 | 0 | 28 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 17 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
Green Park: 87% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 17 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 40% |
| Storm Water Drains | Yes | 20% |
| Landscaping & Tree Planting | Yes | 20% |
| Street Lighting | Yes | 20% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 20% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 25% |
| Electrical meter room, sub-station, receiving station | Yes | 25% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership4
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Mrs Anuradha Prakash Salvi | Pune (M Corp.) | Pune |
| Mr Hirachand Mahadev Shinde | Pimpri Chinchawad (M Corp.) | Pune |
| Mrs Manoja Manik Gaikwad | Pune (M Corp.) | Pune |
| Neeta Mahendrasingh Thakur | LOHGAON | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Shikay Group |
| Engineer | Sanjay Babanrao Gadave, Proprietor of G.K.Construction |
| Chartered Accountant | Pankaj S Patil & Associates |
| Partner | Role in project |
|---|---|
| Classic Developers | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThat due to the late approval of Plans which were approved vide Revised Commencement Certificate bearing No. B.P/Dudulagaon/24/2024 dtd. 27/03/2024, issued by Pimpri Chinchwad Municipal Corporation, the Casting of 7th Floor was delayed, which has caused subsequent delay in installation of Lift Room, Overhead Water Tank, Top Floor Waterproofing, External Wall brick Work, Parapet Wall and External Plaster, However the Building Work is completed 90 % and the same can be seen vide Architect Certificate Form 1 uploaded on Green Park’s MahaRERA Project Registration Portal We hereby request to grant
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 23 Dec 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Mar 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Mar 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed101
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 16 Form 3 CA Certificate June End 2025.pdf | 17 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 Architect Certificate Quarter March 2025 End.pdf | 16 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Form 1 Architect Certificate Quarter June End 2025 End.pdf | 16 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 7 Form 3 March 2025 End CA Certificate.pdf | 16 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8 Form 3 June 2025 End CA Certificate.pdf | 16 Jul 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Form 2 Engineers Certifcate - March End 2025.pdf | 16 Jul 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 Form 2 Engineers Certifcate June End Quarter.pdf | 16 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: 14 Sold Unsold Inventory March Quarter End.pdf | 16 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: 13 Sold Unsold Inventory June Quarter End.pdf | 16 Jul 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 6 Form 2A Quality Assurance March End.pdf | 16 Jul 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 6A Form 2A Quality Assurance June End.pdf | 16 Jul 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 13 Sold Unsold Inventory June Quarter End.pdf | 16 Jul 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: 9 Form 5 CA Certificate FY 2024 to 2025.pdf | 16 Jul 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: 10 Form 5 CA Certificate Half Yearly 2025.pdf | 16 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate with Stamp- 12-01-2025.pdf | 31 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold, Booked Invetory - 05-01-2025.pdf | 31 Mar 2025 |
| Other - TechnicalFile: Schedule of Balance Work alongwith Pert Chart - 24-02-2025.pdf | 31 Mar 2025 |
| Layout approvalFile: Classic Developers Layout Plan_1_11zon.pdf | 6 Mar 2025 |
| Building plan approvalFile: Classic Developers Layout Plan_1_11zon.pdf | 6 Mar 2025 |
| Building plan approvalFile: Classic Developers Floor_2_11zon.pdf | 6 Mar 2025 |
| Copy of Layout Approval (in case of layout)File: Classic Developers Layout Plan_1_11zon.pdf | 6 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Classic Developers Layout Plan_1_11zon.pdf | 6 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Classic Developers Floor_2_11zon.pdf | 6 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: 1 - Sold Unsold Inventory - July to September 2023 - Classic Developers.pdf | 3 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: 2- Sold Unsold Inventory - October 2023 to December 2023 - Classic Developers.pdf | 3 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: 3 - Sold Unsold Inventory - January 2024 to March 2024 - Classic Developers.pdf | 3 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: 4 - Sold Unsold Inventory - April to June 2024 - Classic Developers.pdf | 3 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: 5 - Sold Unsold Inventory - July to September 2024 - Classic Developers.pdf | 3 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: 6- Sold Unsold Inventory - October to December 2024 - Classic Developers.pdf | 3 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1- Certificate 12-01-2025 - Classic Developers.pdf | 25 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: From 1 - Architecte Certficate - 05-10-2023.pdf | 24 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: From 1 - Architecte Certficate - 05-04-2024.pdf | 24 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: From 1 - Architecte Certficate - 05-10-2024.pdf | 24 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA - For Quarter ended March, 2024.pdf | 24 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA - For Quarter ended December, 2024.pdf | 24 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA - For Quarter ended September, 2023.pdf | 24 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engeer's Certificate - for Quarter ended March, 2024.pdf | 24 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engeer's Certificate - for Quarter ended December, 2024.pdf | 24 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engeer's Certificate - for Quarter ended September, 2024.pdf | 24 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineers Certificate Form 2 Quarter End June -2024.pdf | 24 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engeer's Certificate - for Quarter ended March, 2024 - 04-04-2024.pdf | 24 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engeer's Certificate - for Quarter ended December, 2023.pdf | 24 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engeer's Certificate - for Quarter ended September, 2023.pdf | 24 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Sold or Booked Inventory - 26-11-2024.pdf | 24 Feb 2025 |
| Declaration about Commencement CertificateFile: Declaration About Commencement Cerftificate - 18-07-2024.pdf | 24 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Engeer's Certificate for Quality Assurances - 01-04-2024.pdf | 24 Feb 2025 |
| Copy of the legal title reportFile: Supp Search Report - 26-11-2024_11zon.pdf | 23 Dec 2024 |
| Declaration in FORM BFile: Declaration - 26-11-2024_0001.pdf | 23 Dec 2024 |
| Declaration in FORM BFile: Affidavit Cum Declaration - 18-12-2024.pdf | 23 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1 - 2024.pdf | 23 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Form 3.pdf | 23 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate 2024.pdf | 23 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate - 16-12-2024_0001.pdf | 23 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Revise Commencement Certificate -2024.pdf | 23 Dec 2024 |
| Other - LegalFile: TDR Transfer Deed Slum-2024_1_11zon.pdf | 23 Dec 2024 |
| Other - LegalFile: TDR Transfer Deed (Regular) -2024_2_11zon.pdf | 23 Dec 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: C A Form 3.pdf | 23 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A -Quality Assurance Certificate - 16-12-2024.pdf | 23 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Engineers Certificate for Quality Assurance FY 2024.pdf | 21 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineers Certificate Form 2 2024.pdf | 21 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineers Certificate Form 2 2024.pdf | 21 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Engineers Certificate for Quality Assurance FY 2024.pdf | 21 Nov 2024 |
| Layout approvalFile: Approved Plan -1 - 2024_compressed.pdf | 13 Aug 2024 |
| Building plan approvalFile: Approved Plan -2 -2024.pdf | 13 Aug 2024 |
| Copy of Layout Approval (in case of layout)File: Approved Plan -1 - 2024_compressed.pdf | 13 Aug 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Approved Plan -2 -2024.pdf | 13 Aug 2024 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate - 2024.pdf | 13 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1 -06-07-2024.pdf | 13 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate -2024.pdf | 13 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - CA Certificate - FY-2023-2024.pdf | 13 Aug 2024 |
| Copy of the legal title reportFile: Supplementary Search and Title Report Classic Developers.pdf | 27 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate Green Park Project Classic Developers 2024.pdf | 7 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form -1 - Green Park Project - Classic Developers -2024.pdf | 6 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Classic Developers - Quality Assurance Certificate -First Quarter - 2024.pdf | 6 Mar 2024 |
| Details of encumbrances concerned to FinanceFile: Non-Encumbrance Related to Finance.pdf | 14 Jun 2023 |
| Details of encumbrances concerned to LegalFile: Non-Encumbrance Related to Finance.pdf | 14 Jun 2023 |
| CERSAI detailsFile: Undertaking for CERSAI Report.pdf | 14 Jun 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report-Agreement to Sale - Green Park Project -Classic Developers.pdf | 24 May 2023 |
| Details of encumbrances concerned to FinanceFile: Non-Emcumbrance Related to Legal.pdf | 18 May 2023 |
| Details of encumbrances concerned to LegalFile: Non-Emcumbrance Related to Legal.pdf | 18 May 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations, which the RERA portal never shows together
- All 101 filed documents as one ZIP, foldered, with a manifest
Keep Green Park on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near B. K. Park, Dudulgaon13,700+ in Pune
TANISH PARK
TANISH DEVELOPERS
Ajinkya Towers
APAK Bussiness Innovation Pvt Ltd
SILVER GARDENIA
SILVER PROMOTERS AND DEVELOPERS
Mangalam Life Park
Mangalam Buildcorp
SingaPune Ph 3
Xrbia Mirth Properties LLP
SingaPune Ph 2
Xrbia Mirth Properties LLP
Builder: Classic Developers
CLASSIC DEVELOPERS has 4 registrations on MahaRERA, including CLASSIC NIYATI and CLASSIC RESIDENCY. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Green Park is delayed beyond 31 May 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Green Park?
The registered promoter entity is Classic Developers, a partnership as per the filing. Its GSTIN 27AASFC1020G1ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Green Park?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Green Park?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Green Park?
The professionals named in the filing: Architect: Shikay Group; Engineer: Sanjay Babanrao Gadave, Proprietor of G.K.Construction; Chartered Accountant: Pankaj S Patil & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Green Park?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.