Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
May 2027Possession promisedno revision filed
2 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 50%
16 of 16Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 75 documents Report an error

GOVINDKUNJ AND SHYAMKUNJ is a Others project by KAVERI RADHESHAM SOMANI in Pune, Maharashtra, registered with MahaRERA as P52100077116 on 23 Jul 2024. Possession is promised by 30 May 2027. 0 of the 16 units on this registration are recorded sold or booked, and 2 of 22 construction stages are filed complete.

At a glance

Project

  • NameGOVINDKUNJ AND SHYAMKUNJ
  • TypeOthers
  • Location
    • -
    • Jalochi Tal Baramati
    • Jalochi
    • Baramati
    • Pune
    • 413102
  • Pincode413102
  • RERA no.P52100077116
  • ReraGenie IDRG-MH-05707

Builder

  • NameKAVERI RADHESHAM SOMANI
  • Entity typeIndividual

Key dates

this monthRegisteredJul 2024PromisedMay 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Jul 2024
  • Promised completion30 May 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed75 files

Current status

0%0 of 16 units booked
26.8%Work done, per cost certificate

Figures as on 31 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GOVINDKUNJNA44909
SHYAMKUNJNA55077

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 31 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 50%.

GOVINDKUNJ18%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SHYAMKUNJ18%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 31 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed40

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots40
Open Space40
BuildingOpen SpaceTotal
GOVINDKUNJ66
SHYAMKUNJ3434

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area558 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on31 Mar 2026

Approvals and building plan

Sanctioning authorityBaramati Nagar parishad Baramati
Permissible FSI1249.48
Proposed, not sanctioned1,249 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHIGWAN CHOWK A/P and TAL BARAMATI DIST PUNE
Estimated costRs 2.27 cr
Cost incurredRs 60.81 lakh
Work done26.79%
BuildingWingEstimatedIncurred
SHYAMKUNJNARs 1.25 crRs 25.74 lakh
GOVINDKUNJNARs 1.02 crRs 35.08 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGAIKWAD ASSOCIATES THROUGH PROPRIETOR MR PRASAD L GAIKWAD
EngineerGAIKWAD ASSOCIATES THROUGH PROPRIETOR MR PRASAD L GAIKWAD
Chartered AccountantSAMRAT ASHOK SOMANI
Chartered AccountantHitesh Chhajed
PartnerRole in project
KAVERI RADHESHAM SOMANI-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 May 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Jul 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Jun 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 May 2027

Documents filed75

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Architech Certificate22112024_compressed.pdf31 Mar 2026
Form 2File: Engineer Certificate22112024_compressed.pdf31 Mar 2026
Form 3File: Architech Certificate22112024_compressed.pdf31 Mar 2026
Disclosure of Sold and Booked InventoryFile: Inventory.pdf31 Mar 2026
Form 1File: Architech Certificate 22032025.pdf31 Mar 2026
Form 2File: Engineer Certificate-22032025.pdf31 Mar 2026
Form 3File: CA24032025.pdf31 Mar 2026
Disclosure of Sold and Booked InventoryFile: Book Inventory.pdf31 Mar 2026
Withdrawal Update Form 1File: Architech Certficate.pdf31 Mar 2026
Withdrawal Update Form 1File: Architech Certificate Shyamkunj.pdf31 Mar 2026
Withdrawal Update Form 2File: Engineer Certifiacte Govindkunj.pdf31 Mar 2026
Withdrawal Update Form 2File: Engineer Certificate Govindkunj.pdf31 Mar 2026
Withdrawal Update Form 3File: CA Certificate.pdf31 Mar 2026
Withdrawal Update Form 3File: CA Certficate.pdf31 Mar 2026
Form 2A (FY 2024-2025)File: Form 2A.pdf31 Mar 2026
Form 5 (FY 2024-2025)File: CA Form 5.pdf31 Mar 2026
Form 1File: Architech Certificate 28072025.pdf30 Mar 2026
Form 2File: Engineer Certificate.pdf30 Mar 2026
Form 3File: CA Certificate 30 07 2025.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Inventory.pdf30 Mar 2026
Withdrawal Update Form 1File: Architech Certificate- Govind kunj.pdf30 Mar 2026
Withdrawal Update Form 1File: Architech Certificate 10042025_compressed.pdf30 Mar 2026
Withdrawal Update Form 2File: Engineer Certificate-Shyamkunj.pdf30 Mar 2026
Withdrawal Update Form 2File: Engineer Crtificate 0042025.pdf30 Mar 2026
Withdrawal Update Form 3File: C A Certificate Govindkunj.pdf30 Mar 2026
Withdrawal Update Form 3File: CA Certificate 12042025_compressed.pdf30 Mar 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate-Govindkunj.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate-Shyamkunj.pdf18 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate -Govindkunj.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Shyamkunj.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-Govindkunj.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate-Sjyamkunj.pdf28 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate-Sjyamkunj.pdf28 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate- Govindkunj.pdf28 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate-Shyam Govindkunj.pdf28 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certficate- Shyamkunj.pdf28 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-GovindKunj.pdf28 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecht Certificate- Shyamkunj.pdf27 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecht Certificate-Govindkunj.pdf27 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate- Shyamkunj Govindkunj.pdf27 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Govindkunj.pdf27 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-Shyamkunj.pdf27 Nov 2024
Layout approvalFile: Sanction Building Plan.pdf10 Jul 2024
Copy of Layout Approval (in case of layout)File: Sanction Building Plan.pdf10 Jul 2024
Other - LegalFile: Screeshot- Govindkunj.pdf26 Jun 2024
Other - LegalFile: Declaration about Commencement- Govindkunj.pdf26 Jun 2024
Building plan approvalFile: Sanctio Plan-Govindkunj.pdf5 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Sanctio Plan-Govindkunj.pdf5 Jun 2024
Other - LegalFile: EXTRACT.pdf5 Jun 2024
Other - TechnicalFile: Screen Shot.pdf5 Jun 2024
Copy of the legal title reportFile: Search Report- Govind kunj Shyam Kunj.pdf17 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate- Govind kunj.pdf17 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-Shyamkunj.pdf17 May 2024
Layout approvalFile: Lay Out.pdf15 May 2024
Copy of Layout Approval (in case of layout)File: Lay Out.pdf15 May 2024
Declaration in FORM BFile: Form B.pdf15 May 2024
Proforma of Allotment letterFile: Model form of Allotment Letter.pdf15 May 2024
Proforma of Agreement for saleFile: Annexure A- Model Form Of AFS Govind Kunj.pdf15 May 2024
Proforma of Agreement for saleFile: Annexure A- Model Form Of AFS Shyam Kunj.pdf15 May 2024
Other - LegalFile: Annexure A.pdf15 May 2024
Details of encumbrances concerned to FinanceFile: Encumbrance concern to finance.pdf14 May 2024
Details of encumbrances concerned to FinanceFile: Encumbrances To Legal.pdf14 May 2024
Details of encumbrances concerned to LegalFile: Encumbrance concern to finance.pdf14 May 2024
Details of encumbrances concerned to LegalFile: Encumbrances To Legal.pdf14 May 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement-Kaveri_Somani.pdf14 May 2024
Declaration about Commencement CertificateFile: Format D.pdf14 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf14 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf14 May 2024
CERSAI detailsFile: Cersai_Search_Report.pdf14 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate Govindkunj.pdf14 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclouser Intrest Real Estate Organization.pdf14 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate Bank Account.pdf14 May 2024
Deviation Report with respect to Allotment letterFile: Daviation Report -Allotment Latter.pdf14 May 2024
Deviation Report with respect to model copy of AgreementFile: Daviation Report -Agreement to sale.pdf14 May 2024
PAN CardFile: Pan-Kaveri Somani.pdf23 Apr 2024

How this compares with Pune

0%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GOVINDKUNJ AND SHYAMKUNJ on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Jalochi Tal Baramati13,700+ in Pune

Builder: KAVERI RADHESHAM SOMANI

KAVERI RADHESHAM SOMANI has 1 registration on MahaRERA, including GOVINDKUNJ AND SHYAMKUNJ. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if GOVINDKUNJ AND SHYAMKUNJ is delayed beyond 30 May 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GOVINDKUNJ AND SHYAMKUNJ?

The registered promoter entity is KAVERI RADHESHAM SOMANI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GOVINDKUNJ AND SHYAMKUNJ?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GOVINDKUNJ AND SHYAMKUNJ?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GOVINDKUNJ AND SHYAMKUNJ?

The professionals named in the filing: Architect: GAIKWAD ASSOCIATES THROUGH PROPRIETOR MR PRASAD L GAIKWAD; Engineer: GAIKWAD ASSOCIATES THROUGH PROPRIETOR MR PRASAD L GAIKWAD; Chartered Accountant: SAMRAT ASHOK SOMANI; Chartered Accountant: Hitesh Chhajed. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GOVINDKUNJ AND SHYAMKUNJ?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GOVINDKUNJ AND SHYAMKUNJ. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GOVINDKUNJ AND SHYAMKUNJ to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.