Completed No litigation declared Residential / Group Housing project

Govindbaug

By M/S PIONEER DEVELOPERS

RG-MH-08971 · RERA P52100001469 · Last updated on MahaRERA portal: 2 Nov 2023

Source: official MahaRERA filing

Red flags

  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
14 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 70%
0Complaints at MahaRERAon this registration
Jump to the 74 documents Report an error

Govindbaug is a Residential / Group Housing project by M/S PIONEER DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100001469 on 28 Jul 2017. The registration is recorded completed; possession was promised by 31 Dec 2021.

At a glance

Project

  • NameGovindbaug
  • TypeResidential / Group Housing
  • Location
    • Alandi Moshi Road
    • Dudulgaon
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001469
  • ReraGenie IDRG-MH-08971

Builder

  • NameM/S PIONEER DEVELOPERS
  • Entity typePartnership
  • PartnersMahesh Murlidhar Shinde, Santosh Dhondiba Gavhane, Sopan Mahadev Landge

Key dates

this monthRegisteredJul 2017First promiseDec 2022Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on28 Jul 2017
  • Promised completion31 Dec 2021
  • Revised completionRevised to 31 Dec 2021 (originally 30 Dec 2022)
  • Buildings2 building records
  • Documents filed74 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA140000
BNA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 2 Nov 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 70%.

A62%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
B82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 2 Nov 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed115

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots115
Closed/Covered61
Open Space54
BuildingClosed/CoveredOpen SpaceTotal
A252752
B362763

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,550 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Pioneer DevelopersPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Permissible FSI6090.89
Proposed, not sanctioned2,566 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBhosari, Pune-411039

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSunil Rambhau Nawale
EngineerRamchandra krishnarao Randhave
Chartered AccountantAVINASH BHOR
Chartered AccountantPRAKASH SUNEJA
PartnerRole in project
M/S PIONEER DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100013139Dec 2022 → May 2023

Reason as filed by the promoterThe two buildings A & B in the project Govindbaug separated from each other. Building B already completed and obtained a completion certificate from PCMC vide certificate No 188/2021 dated 18/05/2021. Building A is also completed in all respect and we are in the process to obtain a completion certificate from PCMC. Since the process will take some time we require to obtain an extension from Maha Rera authorities and hence this application. Since we have the completion certificate for Building B we have obtained the consent of 57.97 % of allottees from Building A only.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 26 Jun 2023

Documents filed74

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 22 23 pioneer.pdf2 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form-1 architect certificate.pdf26 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form-2.pdf26 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf26 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: completion certificate (A wing).pdf26 Jun 2023
Architect’s Certificate on Completion of Project (Form 4)File: form-4 architect certificate.pdf26 Jun 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate.pdf26 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form52122.pdf16 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf15 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf15 Dec 2022
Form 2AFile: FORM 2A.pdf15 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf15 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM5.pdf12 Apr 2022
Layout approvalFile: scan.pdf23 Mar 2022
Building plan approvalFile: scan0121.pdf23 Mar 2022
Building plan approvalFile: scan0122.pdf23 Mar 2022
Building plan approvalFile: scan0123.pdf23 Mar 2022
Copy of Layout Approval (in case of layout)File: scan.pdf23 Mar 2022
Building Plan Approval (IOD)File: scan0121.pdf23 Mar 2022
Building Plan Approval (IOD)File: scan0122.pdf23 Mar 2022
Building Plan Approval (IOD)File: scan0123.pdf23 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: SCAN 24 09 21.pdf23 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certifictae Form 1.pdf31 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate Form1.pdf31 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1.pdf31 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificte form 2 2021 (2).pdf31 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2.pdf31 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2.pdf31 Aug 2021
Certificates of CA (Form 3)File: RERA_compressed.pdf31 Aug 2021
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMECEMENT CERTIFICATE.pdf30 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: quality assurance certificate form 2A 2021.pdf30 Aug 2021
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD DISCLOSURE (2).pdf30 Aug 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: B building completion certificate.pdf30 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM51920.pdf22 May 2021
Layout approvalFile: Layout.pdf18 Feb 2020
Building plan approvalFile: plan 2-4.pdf18 Feb 2020
Building plan approvalFile: plan 5-7.pdf18 Feb 2020
Building plan approvalFile: plan 8-9.pdf18 Feb 2020
Building plan approvalFile: plan 10.pdf18 Feb 2020
Copy of Layout Approval (in case of layout)File: Layout.pdf18 Feb 2020
Building Plan Approval (IOD)File: plan 2-4.pdf18 Feb 2020
Building Plan Approval (IOD)File: plan 5-7.pdf18 Feb 2020
Building Plan Approval (IOD)File: plan 8-9.pdf18 Feb 2020
Building Plan Approval (IOD)File: plan 10.pdf18 Feb 2020
Commencement Certificates / NA Order for plotted developmentFile: commicement certificate.pdf18 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 PIONEER.pdf13 Dec 2019
Form 2AFile: FORM 2A018.pdf17 Jun 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate dec 18.pdf2 Mar 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate dec-18.pdf2 Mar 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate dec 18.pdf14 Feb 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate dec-18.pdf14 Feb 2019
Certificates of CA (Form 5)File: FORM 5 PIONEER.pdf30 Sep 2018
Layout approvalFile: Layout.pdf22 Mar 2018
Building plan approvalFile: Plan 2-3.pdf22 Mar 2018
Building plan approvalFile: Plan 4,5,6.pdf22 Mar 2018
Copy of Layout Approval (in case of layout)File: Layout.pdf22 Mar 2018
Building Plan Approval (IOD)File: Plan 2-3.pdf22 Mar 2018
Building Plan Approval (IOD)File: Plan 4,5,6.pdf22 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: Commecement Certificate.pdf22 Mar 2018
Layout approvalFile: Layout plan.pdf21 Jul 2017
Building plan approvalFile: Building Plan-1.pdf21 Jul 2017
Building plan approvalFile: Building Plan-2.pdf21 Jul 2017
Details of encumbrancesFile: No Encumbarnce Certificate.pdf21 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout plan.pdf21 Jul 2017
Building Plan Approval (IOD)File: Building Plan-1.pdf21 Jul 2017
Building Plan Approval (IOD)File: Building Plan-2.pdf21 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate-form 1.pdf21 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate.pdf21 Jul 2017
Certificates of CA (Form 3)File: CA Certificate -Form 3.pdf21 Jul 2017
Proforma of Allotment letterFile: Allotment Letter And Agreement to Sale.pdf21 Jul 2017
Declaration in FORM BFile: Form B-Affadavit of Promoter.pdf12 Jul 2017
PAN CardFile: PAN CARD.pdf8 Jul 2017
Copy of the legal title reportFile: Search and Title Report.pdf8 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf8 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Govindbaug on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dudulgaon13,700+ in Pune

2 kmGovindbaugCompleted 38Lapsed / revoked 20Other 61Dot size: filed unitsN

Filed coordinates, straight-line distance. 119 registered projects within 2 km.

Builder: M/S PIONEER DEVELOPERS

M/S PIONEER DEVELOPERS has 1 registration on MahaRERA, including Govindbaug. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Govindbaug is delayed beyond 31 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Govindbaug?

The registered promoter entity is M/S PIONEER DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Govindbaug?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Govindbaug?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Govindbaug?

The professionals named in the filing: Architect: Sunil Rambhau Nawale; Engineer: Ramchandra krishnarao Randhave; Chartered Accountant: AVINASH BHOR; Chartered Accountant: PRAKASH SUNEJA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Govindbaug?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Govindbaug. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Govindbaug to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.