GOREGAON VIHAR DARSHAN CHS LTD
By SILVER LIFESPACES PRIVATE LIMITED
RG-MH-22852 · RERA P51800032448 · Last updated on MahaRERA portal: 9 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 2 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 37 months
- 5 extensions taken
- Rs 46.00 crore secured on the land, in favour of Aditya Birla Capital Limited
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GOREGAON VIHAR DARSHAN CHS LTD is a Residential / Group Housing project by SILVER LIFESPACES PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800032448 on 4 Jan 2022. Possession was promised by 17 Aug 2026 and is now 2 months past that date. The completion date has moved by 37 months from the original filing. 70 of the 85 units on this registration are recorded sold or booked, and 14 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameGOREGAON VIHAR DARSHAN CHS LTD
- TypeResidential / Group Housing
- Location
- SHRIRANG SABALE MARG
- SIDDHARTH NAGAR
- Pahadi-Goregaon
- Borivali
- Mumbai Suburban
- 400104
- Pincode400104
- RERA no.P51800032448
- ReraGenie IDRG-MH-22852
Builder
- NameSILVER LIFESPACES PRIVATE LIMITED
- Entity typeCompany
- DirectorsNANCY MUKESH MEHTA GOTHI, FORUM MUKESH MEHTA, KALPANA MUKESH MEHTA
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on4 Jan 2022
- Promised completion17 Aug 2026
- Revised completionRevised to 17 Aug 2026 (originally 23 Jul 2023)
- Buildings2 building records
- Documents filed91 files
Current status
Figures as on 9 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A WING | NA | 22 | 22 | 43 | 0 | 43 |
| B WING | NA | 22 | 22 | 42 | 0 | 42 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 9 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 95%.
A WING80%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B WING80%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 9 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 85% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 85% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 25% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed133
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A WING | 67 | 67 |
| B WING | 66 | 66 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 13.98 cr | Rs 12.84 cr |
| A WING | NA | Rs 5.52 cr | Rs 5.07 cr |
| B WING | NA | Rs 5.52 cr | Rs 5.07 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SHILP ASSOCIATES |
| Engineer | SAMISHTHI TECHNO SERVICES CONSULTANTS LLP |
| Engineer | UNISTEPS CONSULTING |
| Chartered Accountant | SABADRA & ASSOCIATES |
| Chartered Accountant | DURGESH R PANDEY & ASSOCIATES |
| Partner | Role in project |
|---|---|
| SILVER LIFESPACES PRIVATE LIMITED | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe are not able to complete project on time due to delay in COVID-19 and shortage of materials and manpower. We would like to request you to please grant us an additional extension until 31/05/2025.
Reason as filed by the promoterThe project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.
Reason as filed by the promoterSilver Lifespaces Private Limited is requesting an extension for the "GOREGAON VIHAR DARSHAN CHS LTD" project due to the following reasons: Unforeseen Geotechnical Challenges: The excavation process was delayed due to hard rock strata, requiring additional time and resources. This was confirmed by a Geotechnical Investigation Report dated August 18, 2022. Liquidity Constraints: Slower-than-expected sales and collections during the festive season impacted cash flow. Outstanding receivables of ₹18-20 crore are expected upon achieving the terrace slab stage. Revised Construction Timeline: The pro
Reason as filed by the promoterWhile the project has been progressing steadily, certain unavoidable administrative delays occurred in obtaining statutory approvals during the final stages of construction. Although our current MahaRERA registration is valid up to November 30, 2025, the Final Completion Certificate (Full CC) was received only on October 7, 2025. At present, the project is in its last stage of execution. The entire superstructure is complete, with only half a slab pending and finishing works including flooring, painting, plumbing, electrical fittings, and common area works-nearing completion. Based on the curr
Reason as filed by the promoterOC Recived
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 12762/2021 | HIGH COURT OF JUDICATURE AT BOMBAY | Disposed off |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12600990 | SIBASISH GADADHAR ACCHARYA | SILVER LIFESPACES PRIVATE LIMITED | 23/02/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 15 Dec 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 15 Dec 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 15 Dec 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Nov 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed91
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 91 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: form 1.pdf | 9 May 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 9 May 2026 |
| Withdrawal Update Form 3File: form 3 new.pdf | 9 May 2026 |
| Withdrawal Update Form 1File: FORM 1 dt 12-01-2026 VD.pdf | 6 May 2026 |
| Withdrawal Update Form 2File: FORM 2 dt 22-01-2026 VD.pdf | 6 May 2026 |
| Withdrawal Update Form 3File: FORM 3 dt 20-1-2026.pdf | 6 May 2026 |
| Withdrawal Update Form 1File: FORM 1 VD.pdf | 12 Nov 2025 |
| Withdrawal Update Form 1File: FORM 1 VD.pdf | 12 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 merged.pdf | 12 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 merged.pdf | 12 Nov 2025 |
| Withdrawal Update Form 3File: form 3 date 3-10-25 VD.pdf | 12 Nov 2025 |
| Withdrawal Update Form 3File: form 3 date 3-10-25 VD.pdf | 12 Nov 2025 |
| Withdrawal Update Form 1File: FORM 1 Serene dt 25-07-2025.pdf | 10 Oct 2025 |
| Withdrawal Update Form 2File: FORM 2 Rehab Serene dt 25-7-2025.pdf | 10 Oct 2025 |
| Withdrawal Update Form 3File: FOrm 3.pdf | 10 Oct 2025 |
| Form 1File: form 1 march 25.pdf | 4 Jun 2025 |
| Form 2File: FORM- 2 march 25.pdf | 4 Jun 2025 |
| Form 3File: VD FORM 3 04 05 2025.pdf | 4 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 march 25.pdf | 9 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM- 2 march 25.pdf | 9 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 REHAB march 25.pdf | 9 May 2025 |
| Disclosure of sold/ booked inventoryFile: VD INVENTORY (1).pdf | 9 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A 23-24.pdf | 9 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 dec 24.pdf | 7 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 dec 24 rehab.pdf | 7 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 dec 24.pdf | 7 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 23-24.pdf | 7 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate Form 1 vd.pdf | 22 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 vd 22-4-2025 (1).pdf | 22 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 vd rehab.pdf | 22 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 vd.pdf | 22 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 dec 24.pdf | 3 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 rehab.pdf | 18 Oct 2024 |
| Details of encumbrancesFile: RERA Format B - VD.pdf | 8 Oct 2024 |
| Details of encumbrancesFile: 2 Details of encumbrances.pdf | 8 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Goregoan Vihar Darshan.pdf | 21 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: final Inventory Disclosure.pdf | 20 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 23 Q4.pdf | 19 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate 23 Q4.pdf | 19 Mar 2024 |
| Details of encumbrancesFile: Encumbrance For VD for ABFL-SLPL.pdf | 19 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CA form 5 22-23.pdf | 19 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Arch Certificate dt 22-09-2023.pdf | 23 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Arch Certificate- dt 14-12-2023.pdf | 23 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineers Certificate dt 25-09-2023.pdf | 23 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineera Certificate dt 13-12-2023.pdf | 23 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 18 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 14 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 14 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf | 14 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect’s Certificate.pdf | 24 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer’s Certificate.pdf | 24 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of SOldBooked Inventory- VD_compressed.pdf | 24 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form-2-VD-RERA.pdf | 10 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5-VD-RERA.pdf | 10 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: 29 Silver Life.pdf | 12 Oct 2022 |
| OtherFile: Appointment of Architect (Shilp Associates)- For Silver Srene_compressed.pdf | 31 Mar 2022 |
| OtherFile: resignation of Ashish solanki.pdf | 31 Mar 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200228987432_For_Asset_Based_Search_28_01_2022_17_57_49_207.pdf | 26 Feb 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200226010254_For_Asset_Based_Search_16_12_2021_17_09_51_459.pdf | 16 Dec 2021 |
| Layout approvalFile: 5_compressed-compressed_compressed (3).pdf | 15 Dec 2021 |
| Layout approvalFile: 1_compressed-compressed.pdf | 15 Dec 2021 |
| Layout approvalFile: 2_compressed-compressed.pdf | 15 Dec 2021 |
| Layout approvalFile: 3_compressed-compressed.pdf | 15 Dec 2021 |
| Layout approvalFile: 4_compressed-compressed.pdf | 15 Dec 2021 |
| Building plan approvalFile: 5_compressed-compressed_compressed (3).pdf | 15 Dec 2021 |
| Building plan approvalFile: 1_compressed-compressed.pdf | 15 Dec 2021 |
| Building plan approvalFile: 2_compressed-compressed.pdf | 15 Dec 2021 |
| Building plan approvalFile: 3_compressed-compressed.pdf | 15 Dec 2021 |
| Building plan approvalFile: 4_compressed-compressed.pdf | 15 Dec 2021 |
| Copy of the legal title reportFile: title report.pdf | 15 Dec 2021 |
| Copy of Layout Approval (in case of layout)File: 5_compressed-compressed_compressed (3).pdf | 15 Dec 2021 |
| Copy of Layout Approval (in case of layout)File: 1_compressed-compressed.pdf | 15 Dec 2021 |
| Copy of Layout Approval (in case of layout)File: 2_compressed-compressed.pdf | 15 Dec 2021 |
| Copy of Layout Approval (in case of layout)File: 3_compressed-compressed.pdf | 15 Dec 2021 |
| Copy of Layout Approval (in case of layout)File: 4_compressed-compressed.pdf | 15 Dec 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 5_compressed-compressed_compressed (3).pdf | 15 Dec 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 1_compressed-compressed.pdf | 15 Dec 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 91 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GOREGAON VIHAR DARSHAN CHS LTD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SIDDHARTH NAGAR6,700+ in Mumbai Suburban
Opulence
ARIHA BUILDTECH LLP
SHEETAL KIARA
A & A Developers
4TH AVENUE Sunteck City, ODC, Goregaon West
Satguru Corporate Services Pvt. Ltd.
Narang Valora
Narang Realty Private Limited
VIVAN
GOREGAON ELECTRICAL INDUSTRIES LLP
Integrated Ramicon
Integrated Affordable Home Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: SILVER LIFESPACES PRIVATE LIMITED
SILVER LIFESPACES PRIVATE LIMITED has 2 registrations on MahaRERA, including GOREGAON VIHAR DARSHAN CHS LTD and 33 WEST. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that GOREGAON VIHAR DARSHAN CHS LTD shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if GOREGAON VIHAR DARSHAN CHS LTD is delayed beyond 17 Aug 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GOREGAON VIHAR DARSHAN CHS LTD?
The registered promoter entity is SILVER LIFESPACES PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GOREGAON VIHAR DARSHAN CHS LTD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against GOREGAON VIHAR DARSHAN CHS LTD?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for GOREGAON VIHAR DARSHAN CHS LTD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GOREGAON VIHAR DARSHAN CHS LTD?
The professionals named in the filing: Architect: SHILP ASSOCIATES; Engineer: SAMISHTHI TECHNO SERVICES CONSULTANTS LLP; Engineer: UNISTEPS CONSULTING; Chartered Accountant: SABADRA & ASSOCIATES; Chartered Accountant: DURGESH R PANDEY & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GOREGAON VIHAR DARSHAN CHS LTD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.