Godrej Woodland
RG-KA-52912 · RERA PRM/KA/RERA/1250/304/PR/210208/003856 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- Litigation declared, 1 case
- 31 complaints at RERA Karnataka
- Completion date moved by 12 months
- 1 extension taken
Clear
- Separate project account declared
Saved.
Godrej Woodland is a Plotted Development project by Godrej Properties Ltd in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/210208/003856 on 8 Feb 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 31 complaints are on record with the regulator.
At a glance
Project
- NameGodrej Woodland
- TypePlotted Development
- Location
- Hosakote
- Bengaluru Rural
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1250/304/PR/210208/003856
- ReraGenie IDRG-KA-52912
Builder
- NameGodrej Properties Ltd
- Entity typeCompany
- Authorized SignatorySiddharth Raman
- OthersMoahmmed Samiulla
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on8 Feb 2021
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
- BuildingsNot stated in filing
- Documents filed75 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Godrej Properties Limited | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 83.15 cr | Rs 97.38 cr |
| Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for construction | Rs 21.06 cr | - |
| On-site expenditure-Consultants Fees | Rs 15.43 cr | Rs 53.79 cr |
| On-site expenditure-Salaries of workers | Rs 10.25 cr | - |
| Outgoing Payment made to (Like, Water Supply, power etc.) | Rs 8.82 cr | - |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Studiopod Design Private Limited |
| Engineer | Sanjeev K Sharma |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterothers
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 207 | Senior Civil Judge and JMFC, Hoskote, Bangalore. | - |
Complaints filed with RERA Karnataka31
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CMP/211112/0008548 | - | Godrej Properties Ltd | 12/11/2021 |
| 00818/2023 | - | Godrej Properties Ltd | 23/05/2023 |
| 00315/2026 | - | Godrej Properties Ltd | 27/03/2026 |
| 00336/2026 | - | Godrej Properties Ltd | 04/04/2026 |
| 00362/2026 | - | Godrej Properties Ltd | 08/04/2026 |
| 00363/2026 | - | Godrej Properties Ltd | 08/04/2026 |
| 00373/2026 | - | Godrej Properties Ltd | 09/04/2026 |
| 00375/2026 | - | Godrej Properties Ltd | 10/04/2026 |
| 00376/2026 | - | Godrej Properties Ltd | 10/04/2026 |
| 00378/2026 | - | Godrej Properties Ltd | 10/04/2026 |
| 00379/2026 | - | Godrej Properties Ltd | 10/04/2026 |
| 00382/2026 | - | Godrej Properties Ltd | 10/04/2026 |
| 00383/2026 | - | Godrej Properties Ltd | 15/04/2026 |
| 00384/2026 | - | Godrej Properties Ltd | 15/04/2026 |
| 00415/2026 | - | Godrej Properties Ltd | 18/04/2026 |
| 00416/2026 | - | Godrej Properties Ltd | 18/04/2026 |
| 00489/2026 | - | Godrej Properties Ltd | 11/05/2026 |
| 00490/2026 | - | Godrej Properties Ltd | 11/05/2026 |
| 00491/2026 | - | Godrej Properties Ltd | 11/05/2026 |
| 00492/2026 | - | Godrej Properties Ltd | 11/05/2026 |
| 00493/2026 | - | Godrej Properties Ltd | 11/05/2026 |
| 00494/2026 | - | Godrej Properties Ltd | 11/05/2026 |
| 00495/2026 | - | Godrej Properties Ltd | 11/05/2026 |
| 00665/2026 | - | Godrej Properties Ltd | 06/06/2026 |
| 00677/2026 | - | Godrej Properties Ltd | 09/06/2026 |
| 00959/2026 | - | Godrej Properties Ltd | 05/08/2026 |
| 01058/2026 | - | Godrej Properties Ltd | 25/08/2026 |
| 01059/2026 | - | Godrej Properties Ltd | 25/08/2026 |
| 01060/2026 | - | Godrej Properties Ltd | 25/08/2026 |
| 01061/2026 | - | Godrej Properties Ltd | 25/08/2026 |
| 01093/2026 | - | Godrej Properties Ltd | 02/09/2026 |
Documents filed75
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/210208/003856 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Wood land Phase 1.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engg Ph1 - 30-Sep-26.pdf | 15 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 15 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Woodland Q1 26-27 2.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 & 5 Woodland Q1 26-27.pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 GODREJ WOODLAND-FINAL.pdf | 13 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engg Ph1 - 31-Mar-26.pdf | 13 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Woodland Phase 1.pdf | 13 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engg Ph1 - 31-Dec-25.pdf | 13 Jan 2026 |
| Arc certificate - work completed P1File: Arc certificate - work completed P1.pdf | 17 Oct 2025 |
| Arc certificate - work pending P1File: Arc certificate - work pending P1.pdf | 17 Oct 2025 |
| Engg certificate - work completed Ph 1File: Engg certificate - work completed Ph 1.pdf | 17 Oct 2025 |
| Engg certificate - work pending Ph 1File: Engg certificate - work pending Ph 1.pdf | 17 Oct 2025 |
| Extension AffidavitFile: Extension Affidavit.pdf | 17 Oct 2025 |
| Legible and Certified Conversion Order AttachedFile: Certified Conversion Order.pdf | 18 Jan 2021 |
| EC for Sy.No. 25 AttachedFile: Final EC - Uptodate - Sy.No. 25.pdf | 18 Jan 2021 |
| KSPCB NoC attachedFile: CFE - Godrej Woodland.pdf | 18 Jan 2021 |
| Panchayath Water Commitment Letter AttachedFile: Panchayath - Water Commitment.pdf | 18 Jan 2021 |
| BESCOM NoC AttachedFile: BESCOM - NoC.pdf | 18 Jan 2021 |
| CA DIN NumberFile: CA DIN number.pdf | 11 Jan 2021 |
| Conversion OrderFile: conversion orders.pdf | 11 Jan 2021 |
| KSPCB ClearanceFile: KSPCB NOC.PDF | 11 Jan 2021 |
| Land Owner DetailsFile: Land ownwr details.pdf | 11 Jan 2021 |
| Project SpecificationsFile: Specification.pdf | 11 Jan 2021 |
| Water and Power ClearanceFile: water and power approval.pdf | 11 Jan 2021 |
| Amount paid towards 30% of Statutory Deposit and the appeal is admitted. No order is passed.File: Payment - Appeal - Transaction.pdf | 30 Dec 2020 |
| CertificateFile: Certificate of Incorporation-GPL-New.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: Arc certificate - work completed P1.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Engg certificate - work completed Ph 1.pdf | - |
| CA Certificate for Funds UtilizationFile: GODREJ WOODLAND FORM Ex-3.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Arc certificate - work pending P1.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Engg certificate - work pending Ph 1.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: GODREJ WOODLAND FORM Ex-4.pdf | - |
| AffidavitFile: Extension Affidavit.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: Sold and Unsold Phase 1.pdf | - |
| Document 1File: Woodland_Phase1_Final Release Order.pdf | - |
| Layout Approval - commencement certificate | - |
| Layout plan | - |
| AFS | - |
| sale deed & rtc | - |
| allotment letter | - |
| Woodland brochure | - |
| EC - Godrej Woodland | - |
| Affidavit - Declaration Section(3) | - |
| rtc | - |
| legal declaration | - |
| conversion orders_upload | - |
| Registered Relinquishment Deed | - |
| Unnamed document | - |
| Layout plan | - |
| title report | - |
| Balance Sheet 2019 - 2020File: balancesheet 19-20.pdf | - |
| Balance Sheet 2018 - 2019File: Balance sheet 18-19.pdf | - |
| Balance Sheet 2017 - 2018File: balance sheet 17-18.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: P&L 19-20.pdf | - |
| Audited Profit and Loss Statement 2018 - 2019File: P&l 18-19.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: profit & loss statement 17-18_compressed.pdf | - |
| Director's Report 2019 - 2020File: Directors Report 2020.pdf | - |
| Director's Report 2018 - 2019File: Director Report 2018-19.pdf | - |
| Director's Report 2017 - 2018File: Director Report - 2017-18.pdf | - |
| Cash Flow Statement 2019 - 2020File: cash flow 19-20.pdf | - |
| Cash Flow Statement 2018 - 2019File: cash flow 18-19.pdf | - |
| Auditor's Report 2019 - 2020File: auditor report 19-20.pdf | - |
| Auditor's Report 2018 - 2019File: Auditor report 18-19.pdf | - |
| Auditor's Report 2017 - 2018File: Auditor report 17-18.pdf | - |
| Income Tax Return Acknowledgement 2018 - 2019File: REVISED ITR 6 - GPL - AY 19-20.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: GPL ITR Ack AY 2018-19.pdf | - |
| Form-B | - |
| Prospectus/BrochureFile: Godrej Woodland flipchart.pdf | - |
| Plot Excel SheetFile: PRM_KA_RERA_1250_304_PR_210208_003856 - woodland.xlsx | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Godrej Aqua | - | Ongoing | Jan 2024 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Rural
Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.
Keep Godrej Woodland on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Rural650+ in Bengaluru Rural
BARCA AT GODREJ MSR CITY
M S RAMAIAH VENTURES LLP
Ozone Urbana
Ozone Urbana Infra Developers Pvt Ltd
Pashmina Brookwoods
Shashwati Realty Pvt Ltd
Godrej Royale Woods
Godrej Projects North Star LLP
Prestige Jindal City-Phase II
PRESTIGE SOUTHCITY HOLDINGS
Provident Botanico
Provident Housing Limited
See every Bengaluru Rural project, with the district possession charts
Builder: Godrej Properties Ltd
Godrej Properties Ltd has 1 registration on RERA Karnataka, including Godrej Woodland. Its filings declare 1 earlier project, none of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Rural district page.
Frequently asked questions
What are my rights if Godrej Woodland is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Godrej Woodland?
The registered promoter entity is Godrej Properties Ltd, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Godrej Woodland?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Godrej Woodland?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at Godrej Woodland?
The professionals named in the filing: Architect: Studiopod Design Private Limited; Engineer: Sanjeev K Sharma. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Godrej Woodland?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on.