Home / Browse projects / Mumbai Suburban, Maharashtra / GLORY HEIGHTS

Registered No litigation declared Residential / Group Housing project

GLORY HEIGHTS

By ANMOLNIRMITEE HOMES

RG-MH-18000 · RERA P51800076844 · Last updated on MahaRERA portal: 22 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months, 4 of them under MahaRERA's automatic 4-month extension
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Sep 2027Possession promisedmoved 18 months from the original
2 of 11Construction stages donefurthest along: Slabs of Super Structure, 85%
8 of 11Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 93 documents Report an error

GLORY HEIGHTS is a Residential / Group Housing project by ANMOLNIRMITEE HOMES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800076844 on 28 Jun 2024. Possession is promised by 30 Sep 2027. The completion date has moved by 18 months from the original filing, 4 of them under MahaRERA's automatic 4-month extension for the West Asia conflict. 3 of the 11 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete.

At a glance

Project

  • NameGLORY HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • RAM MANDIR ROAD
    • MALVANI
    • MALAD (WEST)
    • MUMBAI
    • Malvani
    • Borivali
    • Mumbai Suburban
    • 400095
  • Pincode400095
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800076844
  • ReraGenie IDRG-MH-18000

Builder

  • NameANMOLNIRMITEE HOMES
  • Entity typePartnership
  • GSTIN27ACDFA5068M1Z2
  • PartnersSUSHIL KAMALAKAR VENGURLEKAR, SANDEEP BALKRISHNA PAGAR

Key dates

this monthRegisteredJun 2024First promiseMar 2026Revised toSep 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Jun 2024
  • Promised completion30 Sep 2027
  • Revised completionRevised to 30 Sep 2027 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed93 files

Current status

27%3 of 11 units booked
60.9%Work done, per cost certificate

Figures as on 22 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GLORY HEIGHTSNA151011011

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 85%.

GLORY HEIGHTS: 39% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor60%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Closed/Covered1
Open Space2

Land and ownership5

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area525 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Sep 2026
LandownerVillageDistrict
SUDESHCHANDRA NARENDRA BHOSLEGoregaonMumbai Suburban
VIJAYKUMAR JAGANNATH SONAWANEGoregaonMumbai Suburban
ANJALI ANAND BHALWANKARGoregaonMumbai Suburban
SWAROOP ANAND BHALWANKARGoregaonMumbai Suburban
BHALCHANDRA AMRITLAL BRAHMBHATTGoregaonMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI579.45
Proposed, not sanctioned579 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch11 ANJANA APT S V ROAD SHIMPOLI JUNCTION BORIVALI WEST MUMBAI 400092
Estimated costRs 8.50 cr
Cost incurredRs 5.18 cr
Work done60.94%
BuildingWingEstimatedIncurred
GLORY HEIGHTSNARs 7.00 crRs 5.18 cr
-NARs 1.50 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNIRMITEE CREATION
EngineerSSCONS CONSULTING STRUCTURAL ENGINEERS
Chartered AccountantPHIRODIA BAFNA AND ASSOCIATES
Chartered AccountantJAYESH J GUJARATHI
PartnerRole in project
ANMOLNIRMITEE HOMES-

Extensions2

A revised date filed with the regulator does not change the possession date in your agreement for sale. Commentary on the order notes that a buyer's right to interest for delay under section 18 of RERA may still stand; that question has not been tested.

MahaRERA order of 7 Aug 2026Mar 2026 → Jul 2026

Granted by MahaRERA, not applied for by the promoterMahaRERA's order of 7 August 2026 extended the completion date of eligible registered projects by four months, treating the West Asia conflict as force majeure. Promoters did not have to apply for it.

EA23092638967Mar 2026 → Sep 2027

Reason as filed by the promoterThe construction timeline of the 'Glory Heights' project was extended due to cumulative external factors, including unforeseen raw material market volatility, temporary real estate market stagnation resulting in slower capital inflows, localized institutional liquidity constraints, statutory delays in procuring required professional audit certificates, and administrative challenges associated with the regulatory transition and migration to the new MahaRERA/MahaCRITI portal.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 May 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Sep 2027

Documents filed93

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Architect Certificate - March 2026.pdf22 Sep 2026
Withdrawal Update Form 1File: Form 1 - Architect Certificate - March 2026.pdf22 Sep 2026
Withdrawal Update Form 2File: Form 2 - Engineer Certificate - March 2026.pdf22 Sep 2026
Withdrawal Update Form 2File: Form 2 - Engineer Certificate - March 2026.pdf22 Sep 2026
Withdrawal Update Form 3File: Form 3 - CA Certificate - March 2026.pdf22 Sep 2026
Withdrawal Update Form 3File: Form 3 - CA Certificate - March 2026.pdf22 Sep 2026
Withdrawal Update Form 1File: Form 1 - Architect Certificate - June 2025.pdf9 Sep 2026
Withdrawal Update Form 1File: Form 1 - Architect Certificate - September 2025.pdf9 Sep 2026
Withdrawal Update Form 1File: Form 1 - Architect Certificate - December 2025.pdf9 Sep 2026
Withdrawal Update Form 1File: Form 1 - Architect Certificate - March 2026.pdf9 Sep 2026
Withdrawal Update Form 1File: Form 1 - Architect Certificate - March 2026.pdf9 Sep 2026
Withdrawal Update Form 2File: Form 2 - Engineer Certificate - June 2025.pdf9 Sep 2026
Withdrawal Update Form 2File: Form 2 - Engineer Certificate - September 2025.pdf9 Sep 2026
Withdrawal Update Form 2File: Form 2 - Engineer Certificate - December 2025.pdf9 Sep 2026
Withdrawal Update Form 2File: Form 2 - Engineer Certificate - March 2026.pdf9 Sep 2026
Withdrawal Update Form 2File: Form 2 - Engineer Certificate - March 2026.pdf9 Sep 2026
Withdrawal Update Form 3File: Form 3 - CA Certificate - June 2025.pdf9 Sep 2026
Withdrawal Update Form 3File: Form 3 - CA Certificate - September 2025.pdf9 Sep 2026
Withdrawal Update Form 3File: Form 3 - CA Certificate - December 2025.pdf9 Sep 2026
Withdrawal Update Form 3File: Form 3 - CA Certificate - March 2026.pdf9 Sep 2026
Withdrawal Update Form 3File: Form 3 - CA Certificate - March 2026.pdf9 Sep 2026
Form 1File: Form 1 - Architect Certificate - June 2024.pdf8 Sep 2026
Form 2File: Form 2 - Engineer Certificate - June 2024.pdf8 Sep 2026
Form 3File: Form 3 - CA Certificate - June 2024.pdf8 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Booked Inventory - June 2024.pdf8 Sep 2026
Self-declaration of Quarterly ProgressFile: Self-declaration of Quarterly Progress - June 2024.pdf8 Sep 2026
Form 1File: Form 1 - Architect Certificate - September 2024.pdf8 Sep 2026
Form 2File: Form 2 - Engineer Certificate - September 2024.pdf8 Sep 2026
Form 3File: Form 3 - CA Certificate - September 2024.pdf8 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Booked Inventory - September 2024.pdf8 Sep 2026
Self-declaration of Quarterly ProgressFile: Self-declaration of Quarterly Progress - September 2024.pdf8 Sep 2026
Form 1File: Form 1 - Architect Certificate - December 2024.pdf8 Sep 2026
Form 2File: Form 2 - Engineer Certificate - December 2024.pdf8 Sep 2026
Form 3File: Form 3 - CA Certificate - December 2024.pdf8 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Booked Inventory - December 2024.pdf8 Sep 2026
Self-declaration of Quarterly ProgressFile: Self-declaration of Quarterly Progress - December 2024.pdf8 Sep 2026
Form 1File: Form 1 - Architect Certificate - March 2025.pdf8 Sep 2026
Form 2File: Form 2 - Engineer Certificate - March 2025.pdf8 Sep 2026
Form 3File: Form 3 - CA Certificate - March 2025.pdf8 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Booked Inventory - March 2025.pdf8 Sep 2026
Self-declaration of Quarterly ProgressFile: Self-declaration of Quarterly Progress - March 2025.pdf8 Sep 2026
Form 2A (FY 2024-2025)File: Form 2A - Engineer Certificate for QA - 2024-2025.pdf8 Sep 2026
Form 2A (FY 2025-2026)File: Form 2A - Engineer Certificate for QA - 2025-2026.pdf8 Sep 2026
Form 5 (FY 2024-2025)File: Form 5 - Annual Report on Statement of Accounts - 2024-2025.pdf8 Sep 2026
Form 5 (FY 2025-2026)File: Form 5 - Annual Report on Statement of Accounts - 2025-2026.pdf8 Sep 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - ARCHITECT'S CERTIFICATE [MARCH 2025].pdf19 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - CA CERTIFICATE [MARCH 2025].pdf19 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - ENGINEER'S CERTIFICATE [MARCH 2025].pdf19 May 2025
Building plan approvalFile: Amended Approved Plan.pdf11 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Amended Approved Plan.pdf11 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - ARCHITECT'S CERTIFICATE [DECEMBER 2024].pdf6 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - CA CERTIFICATE [DECEMBER 2024].pdf6 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - ENGINEER'S CERTIFICATE [DECEMBER 2024].pdf6 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: Further Commencement Certificate.pdf6 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - ARCHITECT'S CERTIFICATE [SEPTEMBER 2024].pdf20 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - ENGINEER'S CERTIFICATE [SEPTEMBER 2024].pdf20 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - CA CERTIFICATE [SEPTEMBER 2024].pdf20 Nov 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format 'B' [Opening of RERA Bank Account].pdf20 Nov 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Separate Bank Account.pdf20 Nov 2024
Other - LegalFile: Annexure 'A'.pdf20 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - ARCHITECT'S CERTIFICATE [SEPTEMBER 2024].pdf20 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - CA CERTIFICATE [SEPTEMBER 2024].pdf20 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - ENGINEER'S CERTIFICATE [SEPTEMBER 2024].pdf20 Nov 2024
Other - LegalFile: Annexure 'A'.pdf20 Nov 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Separate Bank Account.pdf20 Nov 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format 'B' [Opening of RERA Bank Account].pdf20 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - ARCHITECT'S CERTIFICATE [JUNE 2024].pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - CA CERTIFICATE [JUNE 2024].pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - ENGINEER'S CERTIFICATE [JUNE 2024].pdf18 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: Further Commencement Certificate.pdf3 Jul 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report wrt Model Agreement for Sale.pdf19 Jun 2024
Copy of the legal title reportFile: Legal Title Certificate.pdf29 May 2024
Other - TechnicalFile: Declaration-cum-Undertaking [Annexure A].pdf18 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form_3_CA_Certificate.pdf7 May 2024
Proforma of Agreement for saleFile: Proforma of Agreement for Sale.pdf18 Apr 2024
Details of encumbrances concerned to FinanceFile: No Financial Encumbrance.pdf2 Apr 2024
Details of encumbrances concerned to LegalFile: No Financial Encumbrance.pdf2 Apr 2024
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf2 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A -Disclosure of Interest in Other Real Estate Organizations.pdf2 Apr 2024
Proforma of Allotment letterFile: Proforma - Allotment Letter.pdf2 Apr 2024

How this compares with Mumbai Suburban

27%of this project is bookeddistrict median 29%
35%of Mumbai Suburban projects moved their completion datethis one moved by 18 months
20%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,900+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GLORY HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MALVANI, MALAD (WEST), MUMBAI6,900+ in Mumbai Suburban

2 kmGLORY HEIGHTSCompleted 9Lapsed / revoked 10Other 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 44 registered projects within 2 km.

Builder: ANMOLNIRMITEE HOMES

ANMOLNIRMITEE HOMES has 1 registration on MahaRERA, including GLORY HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if GLORY HEIGHTS is delayed beyond 30 Sep 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GLORY HEIGHTS?

The registered promoter entity is ANMOLNIRMITEE HOMES, a partnership as per the filing. Its GSTIN 27ACDFA5068M1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GLORY HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GLORY HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GLORY HEIGHTS?

The professionals named in the filing: Architect: NIRMITEE CREATION; Engineer: SSCONS CONSULTING STRUCTURAL ENGINEERS; Chartered Accountant: PHIRODIA BAFNA AND ASSOCIATES; Chartered Accountant: JAYESH J GUJARATHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GLORY HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GLORY HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GLORY HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.