Home / Browse projects / Ratnagiri, Maharashtra / GARGI APARTMENT
GARGI APARTMENT
RG-MH-82194 · RERA P52800034510 · Last updated on MahaRERA portal: 27 Mar 2023
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.
See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GARGI APARTMENT is a Residential / Group Housing project by Anil Vithoba Kasar in Ratnagiri, Maharashtra, registered with MahaRERA as P52800034510 on 11 Apr 2022. The registration is recorded completed; possession was promised by 31 Dec 2022.
At a glance
Project
- NameGARGI APARTMENT
- TypeResidential / Group Housing
- Location
- Guhagar Bijapur Higfhway
- Shringartali
- Guhagar
- Ratnagiri
- 415724
- Pincode415724
- RERA no.P52800034510
- ReraGenie IDRG-MH-82194
Builder
- NameAnil Vithoba Kasar
- Entity typeIndividual
- Other registrations1 more →
- Completed1 of 2
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on11 Apr 2022
- Promised completion31 Dec 2022
- Revised completionNone
- Buildings1 building record
- Documents filed19 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GARGI APARTMENT | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
GARGI APARTMENT: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 27 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Nilesh Narayan Patil | Mumbai City | Mumbai City |
| Nilam Narayan Patil | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NN Architecture and Developer |
| Engineer | NN Architecture and Developer |
| Chartered Accountant | Karmarkar Naik & Associates |
| Partner | Role in project |
|---|---|
| Anil Vithoba Kasar | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Apr 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Mar 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Mar 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 27 Mar 2023
Documents filed19
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: GARGI OC.pdf | 27 Mar 2023 |
| Architect’s Certificate on Completion of Project (Form 4)File: GARGI FORM 4.pdf | 27 Mar 2023 |
| Copy of the legal title reportFile: Kasar.pdf | 5 Apr 2022 |
| Layout approvalFile: Blueprint_KASAR-1.pdf | 24 Mar 2022 |
| Building plan approvalFile: Blueprint_KASAR-1.pdf | 24 Mar 2022 |
| PAN CardFile: PAN Card.pdf | 24 Mar 2022 |
| Details of encumbrancesFile: Encumbrance Certificate.pdf | 24 Mar 2022 |
| Copy of Layout Approval (in case of layout)File: Blueprint_KASAR-1.pdf | 24 Mar 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Blueprint_KASAR-1.pdf | 24 Mar 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement.pdf | 24 Mar 2022 |
| Declaration about Commencement CertificateFile: Format D.pdf | 24 Mar 2022 |
| Declaration in FORM BFile: Form B Promoter.pdf | 24 Mar 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 24 Mar 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf | 24 Mar 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200233242676_For_Asset_Based_Search_24_03_2022_09_04_23_375.pdf | 24 Mar 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 24 Mar 2022 |
| Proforma of Allotment letterFile: Proforma Agreement For Sale.pdf | 24 Mar 2022 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 24 Mar 2022 |
| OtherFile: POA.pdf | 24 Mar 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ratnagiri
Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 19 filed documents as one ZIP, foldered, with a manifest
Keep GARGI APARTMENT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shringartali1,100+ in Ratnagiri
GOLDEN HEIGHTS
Qaisar Qasim Chunawala
SAMARTH SAI PRASAD APARTMENT-4 BUILDING NO 2
SAI PRASAD BUILDERS & DEVELOPERS
SAMARTH SAI PRASAD APARTMENT-4
SAI PRASAD BUILDERS & DEVELOPERS
VITHAI BUILDING A
SARITA CORPORATION
Maitri Park
Sanjana Laxman Lohkare
GOVINDA HEIGHTS
RAHUL MANGESH SHETYE
See every Ratnagiri project, with the district possession charts
Builder: Anil Vithoba Kasar
Anil Vithoba Kasar has 2 registrations on MahaRERA, including GARGI APARTMENT and VITHOBA RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ratnagiri district page.
Frequently asked questions
What are my rights if GARGI APARTMENT is delayed beyond 31 Dec 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GARGI APARTMENT?
The registered promoter entity is Anil Vithoba Kasar, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GARGI APARTMENT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GARGI APARTMENT?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GARGI APARTMENT?
The professionals named in the filing: Architect: NN Architecture and Developer; Engineer: NN Architecture and Developer; Chartered Accountant: Karmarkar Naik & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GARGI APARTMENT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback