GANESH PRIME VERA BUILDING A
RG-MH-27397 · RERA P52100033844 · Last updated on MahaRERA portal: 17 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 15 months past the filed date
- Completion date moved by 7 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GANESH PRIME VERA BUILDING A is a Commercial project by R D DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100033844 on 14 Mar 2022. Possession was promised by 31 Jul 2025 and is now 15 months past that date. The completion date has moved by 7 months from the original filing.
At a glance
Project
- NameGANESH PRIME VERA BUILDING A
- TypeCommercial
- Location
- AMBEGAON ROAD
- AMBEGAON BK
- Pune (M Corp.)
- Pune City
- Pune
- 411046
- Pincode411046
- RERA no.P52100033844
- ReraGenie IDRG-MH-27397
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on14 Mar 2022
- Promised completion31 Jul 2025
- Revised completionRevised to 31 Jul 2025 (originally 31 Dec 2024)
- Buildings1 building record
- Documents filed61 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GANESH PRIME VERA BUILDING A | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 17 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
GANESH PRIME VERA BUILDING A: 77% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 17 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 90% |
| Street Lighting | Yes | 90% |
| Community Buildings | Yes | 95% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 90% |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | Yes | 90% |
| Fire protection and fire safety requirements | Yes | 90% |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SUNITA GANESH GAIKWAD | Pune (M Corp.) | Pune |
| NIRMALA PANDURANG GAIKWAD | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VIKAS M DHERE |
| Engineer | P M SHELKE AND ASSOCIATES |
| Chartered Accountant | AJITSINGH K PARIHAR |
| Chartered Accountant | TANAJI KISAN CHORGHE |
| Partner | Role in project |
|---|---|
| R D DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have yet to received Completion Certificate competent authorities during this process our project date is expired on 31st December 2024 due to above we need some extra time from today till 31st July 2025 to obtain all Certificates from competent authorities
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Feb 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 Feb 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Feb 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed61
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architech certificate June 22 Commercial_compressed.pdf | 17 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Architech certificate Sep 22 Commercial_compressed.pdf | 17 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Architech certificate Dec 22 Commercial_compressed.pdf | 17 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Architech certificate Mar 23 Commercial_compressed.pdf | 17 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 Architech certificate Dec 23 Commercial_compressed.pdf | 17 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate June 22_compressed.pdf | 17 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 CA Certificate Sept 22_compressed.pdf | 17 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 CA Certificate Dec 22_compressed.pdf | 17 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 CA Certificate Mar 23_compressed.pdf | 17 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 CA Certicate Dec 23_compressed.pdf | 17 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer Certificate Jun 22 Commecial_compressed.pdf | 17 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Engineer Certificate Sep 22 Commecial_compressed.pdf | 17 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Engineer Certificate Dec 22 Commercial_compressed.pdf | 17 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Engineer Certificate Mar 23 Commercial_compressed.pdf | 17 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 Engineer Certificate Dec 23 Commercial_compressed.pdf | 17 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Quality Assurance FY 23-24.pdf | 17 Apr 2025 |
| Declaration in FORM BFile: FORM B Declaration Nilesh_compressed.pdf | 3 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_compressed.pdf | 3 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_compressed.pdf | 3 Mar 2025 |
| Declaration about Commencement CertificateFile: decalaration_commencement Commercial_compressed.pdf | 3 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Quality Assurance.pdf | 3 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2024.pdf | 3 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2024 Signed.pdf | 3 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect letter A bluiding.pdf | 18 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Comm Sep 24_compressed.pdf | 18 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Comm June 24_compressed.pdf | 18 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Comm March 24_compressed.pdf | 18 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3_Dec 24 Comm.pdf | 18 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Commercial Sept-24.pdf | 18 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Commercial June-24.pdf | 18 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Commercial Mar-24.pdf | 18 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate A building dec_compressed.pdf | 18 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Sep 24.pdf | 18 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Jun 24.pdf | 18 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Mar 24.pdf | 18 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert June 23 Ganesh PrimE Comm.pdf | 3 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert Sep 23 Ganesh Prime Comm.pdf | 3 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert Comm june 23.pdf | 3 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert Comm Sep 23.pdf | 3 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE Commercial jun 23_compressed.pdf | 3 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate commercial sep-23_compressed.pdf | 3 Jan 2024 |
| OtherFile: Development Agreement with Gaikwad Part 1.pdf | 4 Mar 2022 |
| OtherFile: Development Agreement with Gaikwad Part 2.pdf | 4 Mar 2022 |
| OtherFile: Development Agreement with Gaikwad Part 3.pdf | 4 Mar 2022 |
| Copy of the legal title reportFile: 8 Search and title Report_compressed.pdf | 26 Feb 2022 |
| Details of encumbrancesFile: Self Declaration of Encumbrances.pdf | 14 Feb 2022 |
| Declaration about Commencement CertificateFile: Declaration About Commencement Wing A.pdf | 14 Feb 2022 |
| Declaration in FORM BFile: Declaration Annexure B.pdf | 14 Feb 2022 |
| CERSAI detailsFile: Commercial CERSAI_Search_Report_200230156511_For_Asset_Based_Search_14_02_2022_13_31_26_50 | 14 Feb 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Commercial.pdf | 3 Feb 2022 |
| Layout approvalFile: Commercial Ground and 1st Floor Plan.pdf | 2 Feb 2022 |
| Building plan approvalFile: Commercial Parking Plan.pdf | 2 Feb 2022 |
| PAN CardFile: 1 Pan R D Developers.pdf | 2 Feb 2022 |
| Details of encumbrancesFile: 10 Ferfar Utara_compressed.pdf | 2 Feb 2022 |
| Copy of Layout Approval (in case of layout)File: Commercial Ground and 1st Floor Plan.pdf | 2 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Commercial Parking Plan.pdf | 2 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 12 Commencement Certificate_compressed.pdf | 2 Feb 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 17 Architect Certificate Commercial_compressed.pdf | 2 Feb 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 16 Engineer Certificate Commercial_compressed.pdf | 2 Feb 2022 |
| Proforma of Allotment letterFile: 22 Proforma Agreement_compressed.pdf | 2 Feb 2022 |
| Proforma of Allotment letterFile: 22 Allotment Letter_compressed.pdf | 2 Feb 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 61 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep GANESH PRIME VERA BUILDING A on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near AMBEGAON BK13,700+ in Pune
Sai Nagari Phase I
Saikedareshwar Developers LLP
SAI NAGARI Phase V
Saikedareshwar Developers LLP
Sai Nagari Phase II
Saikedareshwar Developers LLP
Sai Nagari Phase IV
Saikedareshwar Developers LLP
Sai Nagari Phase III
Saikedareshwar Developers LLP
Bella Casa - Phase 1
Kakkad Infra LLP
Builder: R D DEVELOPERS
R D DEVELOPERS has 3 registrations on MahaRERA, including GANESH PRIME VERA BUILDING A and GANESH PRIME VERA. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that GANESH PRIME VERA BUILDING A shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if GANESH PRIME VERA BUILDING A is delayed beyond 31 Jul 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GANESH PRIME VERA BUILDING A?
The registered promoter entity is R D DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GANESH PRIME VERA BUILDING A?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GANESH PRIME VERA BUILDING A?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GANESH PRIME VERA BUILDING A?
The professionals named in the filing: Architect: VIKAS M DHERE; Engineer: P M SHELKE AND ASSOCIATES; Chartered Accountant: AJITSINGH K PARIHAR; Chartered Accountant: TANAJI KISAN CHORGHE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GANESH PRIME VERA BUILDING A?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.