ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / GANESH PRIME VERA BUILDING A

Registration lapsed No litigation declared Commercial project

GANESH PRIME VERA BUILDING A

By R D DEVELOPERS

RG-MH-27397 · RERA P52100033844 · Last updated on MahaRERA portal: 17 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 15 months past the filed date
  • Completion date moved by 7 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2025Possession promised15 months past this date
4 of 11Construction stages donefurthest along: Internal walls, 90%
0Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

GANESH PRIME VERA BUILDING A is a Commercial project by R D DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100033844 on 14 Mar 2022. Possession was promised by 31 Jul 2025 and is now 15 months past that date. The completion date has moved by 7 months from the original filing.

At a glance

Project

  • NameGANESH PRIME VERA BUILDING A
  • TypeCommercial
  • Location
    • AMBEGAON ROAD
    • AMBEGAON BK
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411046
  • Pincode411046
  • RERA no.P52100033844
  • ReraGenie IDRG-MH-27397

Builder

  • NameR D DEVELOPERS
  • Entity typePartnership
  • PartnersNILESH DATTATRAY BHINTADE, DNYANOBA SHIVRAM BHINTADE
  • Other registrations2 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

15 months past promisethis monthRegisteredMar 2022First promiseDec 2024Revised toJul 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Mar 2022
  • Promised completion31 Jul 2025
  • Revised completionRevised to 31 Jul 2025 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed61 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GANESH PRIME VERA BUILDING ANA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

GANESH PRIME VERA BUILDING A: 77% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 17 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes90%
Street LightingYes90%
Community BuildingsYes95%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes90%
Energy managemcntYes90%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,150 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
SUNITA GANESH GAIKWADPune (M Corp.)Pune
NIRMALA PANDURANG GAIKWADPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPMC
Permissible FSI967.0
Proposed, not sanctioned967 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDHANAKWADI PUNE 411043

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIKAS M DHERE
EngineerP M SHELKE AND ASSOCIATES
Chartered AccountantAJITSINGH K PARIHAR
Chartered AccountantTANAJI KISAN CHORGHE
PartnerRole in project
R D DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100027380Dec 2024 → Jul 2025

Reason as filed by the promoterWe have yet to received Completion Certificate competent authorities during this process our project date is expired on 31st December 2024 due to above we need some extra time from today till 31st July 2025 to obtain all Certificates from competent authorities

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Feb 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Feb 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Feb 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architech certificate June 22 Commercial_compressed.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Architech certificate Sep 22 Commercial_compressed.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Architech certificate Dec 22 Commercial_compressed.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Architech certificate Mar 23 Commercial_compressed.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 Architech certificate Dec 23 Commercial_compressed.pdf17 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate June 22_compressed.pdf17 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 CA Certificate Sept 22_compressed.pdf17 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 CA Certificate Dec 22_compressed.pdf17 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 CA Certificate Mar 23_compressed.pdf17 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 CA Certicate Dec 23_compressed.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer Certificate Jun 22 Commecial_compressed.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Engineer Certificate Sep 22 Commecial_compressed.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Engineer Certificate Dec 22 Commercial_compressed.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Engineer Certificate Mar 23 Commercial_compressed.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 Engineer Certificate Dec 23 Commercial_compressed.pdf17 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Quality Assurance FY 23-24.pdf17 Apr 2025
Declaration in FORM BFile: FORM B Declaration Nilesh_compressed.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_compressed.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_compressed.pdf3 Mar 2025
Declaration about Commencement CertificateFile: decalaration_commencement Commercial_compressed.pdf3 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Quality Assurance.pdf3 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2024.pdf3 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2024 Signed.pdf3 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect letter A bluiding.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Comm Sep 24_compressed.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Comm June 24_compressed.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Comm March 24_compressed.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3_Dec 24 Comm.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Commercial Sept-24.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Commercial June-24.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Commercial Mar-24.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate A building dec_compressed.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Sep 24.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Jun 24.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Mar 24.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert June 23 Ganesh PrimE Comm.pdf3 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert Sep 23 Ganesh Prime Comm.pdf3 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert Comm june 23.pdf3 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert Comm Sep 23.pdf3 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE Commercial jun 23_compressed.pdf3 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate commercial sep-23_compressed.pdf3 Jan 2024
OtherFile: Development Agreement with Gaikwad Part 1.pdf4 Mar 2022
OtherFile: Development Agreement with Gaikwad Part 2.pdf4 Mar 2022
OtherFile: Development Agreement with Gaikwad Part 3.pdf4 Mar 2022
Copy of the legal title reportFile: 8 Search and title Report_compressed.pdf26 Feb 2022
Details of encumbrancesFile: Self Declaration of Encumbrances.pdf14 Feb 2022
Declaration about Commencement CertificateFile: Declaration About Commencement Wing A.pdf14 Feb 2022
Declaration in FORM BFile: Declaration Annexure B.pdf14 Feb 2022
CERSAI detailsFile: Commercial CERSAI_Search_Report_200230156511_For_Asset_Based_Search_14_02_2022_13_31_26_5014 Feb 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Commercial.pdf3 Feb 2022
Layout approvalFile: Commercial Ground and 1st Floor Plan.pdf2 Feb 2022
Building plan approvalFile: Commercial Parking Plan.pdf2 Feb 2022
PAN CardFile: 1 Pan R D Developers.pdf2 Feb 2022
Details of encumbrancesFile: 10 Ferfar Utara_compressed.pdf2 Feb 2022
Copy of Layout Approval (in case of layout)File: Commercial Ground and 1st Floor Plan.pdf2 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: Commercial Parking Plan.pdf2 Feb 2022
Commencement Certificates / NA Order for plotted developmentFile: 12 Commencement Certificate_compressed.pdf2 Feb 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 17 Architect Certificate Commercial_compressed.pdf2 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 16 Engineer Certificate Commercial_compressed.pdf2 Feb 2022
Proforma of Allotment letterFile: 22 Proforma Agreement_compressed.pdf2 Feb 2022
Proforma of Allotment letterFile: 22 Allotment Letter_compressed.pdf2 Feb 2022

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 7 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GANESH PRIME VERA BUILDING A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AMBEGAON BK13,700+ in Pune

Builder: R D DEVELOPERS

R D DEVELOPERS has 3 registrations on MahaRERA, including GANESH PRIME VERA BUILDING A and GANESH PRIME VERA. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that GANESH PRIME VERA BUILDING A shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if GANESH PRIME VERA BUILDING A is delayed beyond 31 Jul 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GANESH PRIME VERA BUILDING A?

The registered promoter entity is R D DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GANESH PRIME VERA BUILDING A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GANESH PRIME VERA BUILDING A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GANESH PRIME VERA BUILDING A?

The professionals named in the filing: Architect: VIKAS M DHERE; Engineer: P M SHELKE AND ASSOCIATES; Chartered Accountant: AJITSINGH K PARIHAR; Chartered Accountant: TANAJI KISAN CHORGHE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GANESH PRIME VERA BUILDING A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GANESH PRIME VERA BUILDING A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GANESH PRIME VERA BUILDING A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.