Home / Browse projects / Pune, Maharashtra / Gandharv Mithila Building A Wing E, F, G
Gandharv Mithila Building A Wing E, F, G
By Vinayak Pandharinath Bhongale
RG-MH-37111 · RERA P52100049462 · Last updated on MahaRERA portal: 26 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 12 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Gandharv Mithila Building A Wing E, F, G is a Residential / Group Housing project by Vinayak Pandharinath Bhongale in Pune, Maharashtra, registered with MahaRERA as P52100049462 on 14 Feb 2023. Possession is promised by 31 Dec 2026.
At a glance
Project
- NameGandharv Mithila Building A Wing E, F, G
- TypeResidential / Group Housing
- Location
- Dehu Moshi Road
- Borhadewadi
- Moshi
- Haveli
- Pune
- 412105
- Pincode412105
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100049462
- ReraGenie IDRG-MH-37111
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on14 Feb 2023
- Promised completion31 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed101 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Gandharv Mithila Building A Wing E, F, G | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 26 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
Gandharv Mithila Building A Wing E, F, G: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 26 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed39
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mr Atul Ranpise |
| Engineer | Mr Vijay Pralhad Kothalkar |
| Chartered Accountant | P B Phapale |
| Partner | Role in project |
|---|---|
| Vinayak Pandharinath Bhongale | - |
Litigation declared3
| Case | Court | Status |
|---|---|---|
| 1019/2018 | Honble CJSD Court Pune | Pending |
| 141/2022 | Honble District Court Pune | Pending |
| 72/2022 | Honble CJJD Court Pune | Pending |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 Jan 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Mar 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Mar 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 17 Mar 2025
Documents filed101
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Wing EFG.pdf | 26 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate Wing EFG.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Wing EFG.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Book Wing EFG.pdf | 19 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance Wing EFG.pdf | 19 Apr 2025 |
| Layout approvalFile: Sheet 1 Sanction Plan.pdf | 17 Mar 2025 |
| Layout approvalFile: Sheet 2 Parking Plan Mithila.pdf | 17 Mar 2025 |
| Building plan approvalFile: Sheet 5 Wing EFG Floor Plan.pdf | 17 Mar 2025 |
| Copy of Layout Approval (in case of layout)File: Sheet 1 Sanction Plan.pdf | 17 Mar 2025 |
| Copy of Layout Approval (in case of layout)File: Sheet 2 Parking Plan Mithila.pdf | 17 Mar 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement certificate 18-25.pdf | 17 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Sheet 5 Wing EFG Floor Plan.pdf | 17 Mar 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate Mithila.pdf | 17 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Wing EFG.pdf | 5 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Building A Wing EFG.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Building A Wing EFG.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Book Gandharv Mithila Wing EFG.pdf | 20 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance Gandharv Mithila Wing EFG.pdf | 20 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Gandharv Mithila wing EFG.pdf | 19 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Gandharv Mithila wing EFG.pdf | 19 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Wing EFG.pdf | 22 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate_Gandharva Mithila A Wing-E,F,G.pdf | 22 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold_Booked_GandharvMithila A Wing_EFG.pdf | 22 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality_Gandharv Mithila A Wing_EFG.pdf | 22 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Wing EFG.pdf | 20 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Wing EFG.pdf | 11 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Wing EFG.pdf | 11 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance_Wing EFG.pdf | 11 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Book_wing EFG.pdf | 11 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Wing EFG.pdf | 11 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate_Gandharv Mithila EFG.pdf | 19 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_Gandharv Mithila E,F,G.pdf | 19 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality_ Assurance Gandharv Mithila_EFG.pdf | 19 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Book_Mithila EFG.pdf | 19 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_MIthila EFG.pdf | 19 Apr 2024 |
| Building plan approvalFile: Sheet 6 Elevation Wing EFG.pdf | 7 Mar 2024 |
| Layout approvalFile: Sheet 1 Sanction Layout.pdf | 7 Mar 2024 |
| Layout approvalFile: Sheet 2 Parking Floor plan.pdf | 7 Mar 2024 |
| Building plan approvalFile: Sheet 5 Floor plan Wing EFG.pdf | 7 Mar 2024 |
| Copy of Layout Approval (in case of layout)File: Sheet 1 Sanction Layout.pdf | 7 Mar 2024 |
| Copy of Layout Approval (in case of layout)File: Sheet 2 Parking Floor plan.pdf | 7 Mar 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Sheet 5 Floor plan Wing EFG.pdf | 7 Mar 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Sheet 6 Elevation Wing EFG.pdf | 7 Mar 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement Certificate 08-2024.pdf | 7 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Gandharv Mithila EFG.pdf | 10 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Mithila EFG.pdf | 18 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Mithila EFG.pdf | 18 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Certificate Mithila EFG.pdf | 18 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Book Mithila - E,F,G.pdf | 18 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Mithila - EFG.pdf | 18 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certicate - EFG.pdf | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Building A Wing E, F, G.pdf | 19 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Gandharv Mithila Building A Wing E, F, G.pdf | 19 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: sold Book EFG.pdf | 19 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Mithila A Wing E, F, G.pdf | 19 Oct 2023 |
| Proforma of Agreement for saleFile: Gandharv Mithila Building A Wing E,F,G Final.pdf | 14 Oct 2023 |
| Layout approvalFile: Revised Sanction Layout 1.pdf | 11 Oct 2023 |
| Layout approvalFile: Revised Sanction Layout 2.pdf | 11 Oct 2023 |
| Building plan approvalFile: Elevation Plan Wing EFG.pdf | 11 Oct 2023 |
| Building plan approvalFile: Floor Plan Wing EFG.pdf | 11 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: Revised Sanction Layout 1.pdf | 11 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: Revised Sanction Layout 2.pdf | 11 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Elevation Plan Wing EFG.pdf | 11 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Floor Plan Wing EFG.pdf | 11 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Mithila Revised Commencement 65-2023.pdf | 11 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mithila EFG.pdf | 21 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Sold EFG.pdf | 21 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archi EFG.pdf | 18 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certi EFG.pdf | 18 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Gandharv mithila EFG.pdf | 29 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Gandharv mithila A Wing E G F.pdf | 24 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Gandharav Mithila A Wing E F G.pdf | 24 May 2023 |
| Disclosure of sold/ booked inventoryFile: Gandharv Mithila A Wing E F G.pdf | 24 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate wing EFG_compressed.pdf | 19 May 2023 |
| Proforma of Agreement for saleFile: Gandharv Mithila Building A Wing E,F,G.pdf | 13 Apr 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation report with respect to model copy of Agreement.pdf | 18 Jan 2023 |
| Copy of the legal title reportFile: Legal Title Report.pdf | 9 Jan 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_120.pdf | 9 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf | 9 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: Encumbrances concerned to finance.pdf | 7 Jan 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Gandharv Excellence | Gat No 155 156 3 near Modern college of pharmacy Moshi Dehu Road Borhadewadi Moshi Pune 411070 | 184 | Completed | Jun 2017 | Jun 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 12 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 101 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Gandharv Mithila Building A Wing E, F, G on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Borhadewadi13,700+ in Pune
Filed coordinates, straight-line distance. 231 registered projects within 2 km.
TANISH PARK
TANISH DEVELOPERS
Ajinkya Towers
APAK Bussiness Innovation Pvt Ltd
SILVER GARDENIA
SILVER PROMOTERS AND DEVELOPERS
Mangalam Life Park
Mangalam Buildcorp
SingaPune Ph 3
Xrbia Mirth Properties LLP
SingaPune Ph 2
Xrbia Mirth Properties LLP
Builder: Vinayak Pandharinath Bhongale
Vinayak Pandharinath Bhongale has 13 registrations on MahaRERA, including Gandharva Excellence Project II and Gandharva Nagari Phase II, Project II, G-12. Its filings disclose 6 earlier MahaRERA projects: declares 6 of 6 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Gandharv Mithila Building A Wing E, F, G is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Gandharv Mithila Building A Wing E, F, G?
The registered promoter entity is Vinayak Pandharinath Bhongale, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Gandharv Mithila Building A Wing E, F, G?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Gandharv Mithila Building A Wing E, F, G?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Gandharv Mithila Building A Wing E, F, G?
The professionals named in the filing: Architect: Mr Atul Ranpise; Engineer: Mr Vijay Pralhad Kothalkar; Chartered Accountant: P B Phapale. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Gandharv Mithila Building A Wing E, F, G?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback