Home / Browse projects / Raigarh, Maharashtra / Foothills of Matheran P - 3
Foothills of Matheran P - 3
By HOABL Impactum Land Private Limited
RG-MH-62816 · RERA P52000046022 · Last updated on MahaRERA portal: 30 Sep 2025
Source: official MahaRERA filing
Red flags
- 2 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Foothills of Matheran P - 3 is a Plotted project by HOABL Impactum Land Private Limited in Raigarh, Maharashtra, registered with MahaRERA as P52000046022 on 15 Jun 2022. The registration is recorded completed; possession was promised by 30 Jun 2025. 58 of the 174 units on this registration are recorded sold or booked. 2 complaints are on record with the regulator.
At a glance
Project
- NameFoothills of Matheran P - 3
- TypePlotted
- Location
- MDR Road
- Near Shilar River
- pimploli bk
- Karjat
- Raigarh
- 410201
- Pincode410201
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000046022
- ReraGenie IDRG-MH-62816
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on15 Jun 2022
- Promised completion30 Jun 2025
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed85 files
Current status
Figures as on 30 Sep 2025, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities16
As on 30 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 98% |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 75% |
| Street Lighting | Yes | 90% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 75% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| COMPOUND WALL | Yes | 40% |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 19.22 cr | Rs 7.38 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sanjay Jain |
| Engineer | Swapnil Jadhav |
| Engineer | Akil Ahmad |
| Chartered Accountant | Chirag Sarvaiya |
| Chartered Accountant | U S MISHRA AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| HOABL Impactum Land Private Limited | - |
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12601794 | Nikesh Shrivastava | HOABL Impactum Land Private Limited | 27/03/2026 |
| SM12600437 | Bhakti Achrekar | HOABL Impactum Land Private Limited | 28/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 1 Jun 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Sep 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 1 Jun 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 28 Jun 2024
Documents filed85
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2024-2025)File: Form 5_FHOM P3 - 2024-25.pdf | 30 Sep 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 13 Foothills of Matheran P3_Form 5_promoter signed.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 13 Foothills of Matheran P3_Form 5_promoter signed.pdf | 7 Oct 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Neral -MLP Completion Letter.pdf | 28 Jun 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4_Foothills of Matheran_P3.pdf | 28 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_Foothills of Matheran_P3.pdf | 27 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR.pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER.pdf | 20 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Foothills of Matheran P - 3.pdf | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf | 20 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Neral FHOM P3 OND23.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Neral FHOM P3 OND23.pdf | 20 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory-Foothills of Matheran P3.pdf | 20 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: H_Impactum_P3.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate FHOM P3.pdf | 22 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Phase 3 Impactum Lands Neral.pdf | 21 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate FHOM P3.pdf | 18 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Phase 3 Impactum Lands Neral.pdf | 17 Oct 2023 |
| OtherFile: Letter_P3.pdf | 17 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form5_FHOMph3.pdf | 1 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Neral Phase 3.pdf | 14 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_3.pdf | 18 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase 3_compressed.pdf | 9 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_03_compressed.pdf | 21 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_P3.pdf | 21 Jul 2023 |
| Details of encumbrancesFile: HI Financial Encumbrances - P-3.pdf | 1 Jun 2023 |
| PAN CardFile: PAN_HOABL IMPACTUM.pdf | 30 May 2023 |
| OtherFile: Name change letter_Hoabl Impactum.pdf | 4 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC P3.pdf | 31 Jan 2023 |
| Proforma of Agreement for saleFile: uploaded AFS_neral (1).pdf | 20 Jan 2023 |
| OtherFile: Declaration and COI.pdf | 27 Dec 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate P-3.pdf | 26 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_P3_compressed.pdf | 26 Dec 2022 |
| Layout approvalFile: NeralLayoutsMerged.pdf | 21 Sep 2022 |
| Copy of Layout Approval (in case of layout)File: NeralLayoutsMerged.pdf | 21 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 20220825 PIMPLOLI NA ORDER_NERAL_compressed-1-2.pdf | 19 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 20220825 PIMPLOLI NA ORDER_NERAL_compressed-3-4.pdf | 19 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 20220825 PIMPLOLI NA ORDER_NERAL_compressed-3-6.pdf | 19 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 20220825 PIMPLOLI NA ORDER_NERAL_compressed-7-8.pdf | 19 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 20220825 PIMPLOLI NA ORDER_NERAL_compressed-9-10.pdf | 19 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 20220825 PIMPLOLI NA ORDER_NERAL_compressed-11-12.pdf | 19 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 20220825 PIMPLOLI NA ORDER_NERAL_compressed-12-14.pdf | 19 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 20220825 PIMPLOLI NA ORDER_NERAL_compressed-15-16.pdf | 19 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 20220825 PIMPLOLI NA ORDER_NERAL_compressed-17-18.pdf | 19 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 20220825 PIMPLOLI NA ORDER_NERAL_compressed-19-20.pdf | 19 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 20220825 PIMPLOLI NA ORDER_NERAL_compressed-21-22.pdf | 19 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 20220825 PIMPLOLI NA ORDER_NERAL_compressed-23-24.pdf | 19 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 20220825 PIMPLOLI NA ORDER_NERAL_compressed-25-26.pdf | 19 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 20220825 PIMPLOLI NA ORDER_NERAL_compressed-27-28.pdf | 19 Sep 2022 |
| Layout approvalFile: Provisional Plan P3 07072022.pdf | 8 Jul 2022 |
| Details of encumbrancesFile: encumbrance certificate_ 07072022-3.pdf | 8 Jul 2022 |
| Copy of Layout Approval (in case of layout)File: Provisional Plan P3 07072022.pdf | 8 Jul 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: NA Order Compressed part 1.pdf | 3 Jun 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: NA Order Compressed part 2.pdf | 3 Jun 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: NA Order Compressed Part 3.pdf | 3 Jun 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: NA Declaration.pdf | 3 Jun 2022 |
| Layout approvalFile: NA Declaration.pdf | 1 Jun 2022 |
| Layout approvalFile: NA Plan Compressed 1.pdf | 1 Jun 2022 |
| Building plan approval or NA orderFile: NA Order Compressed part 1.pdf | 1 Jun 2022 |
| Building plan approval or NA orderFile: NA Order Compressed part 2.pdf | 1 Jun 2022 |
| Building plan approval or NA orderFile: NA Order Compressed Part 3.pdf | 1 Jun 2022 |
| Layout approvalFile: 2022 06 01_NE_Phase-3.pdf | 1 Jun 2022 |
| PAN CardFile: Impactum PAN.pdf | 1 Jun 2022 |
| Copy of the legal title reportFile: Title P1.pdf | 1 Jun 2022 |
| Copy of the legal title reportFile: Title P2.pdf | 1 Jun 2022 |
| Copy of the legal title reportFile: Title P3.pdf | 1 Jun 2022 |
| Details of encumbrancesFile: Encumbrance P3.pdf | 1 Jun 2022 |
| Copy of Layout Approval (in case of layout)File: NA Plan Compressed 1.pdf | 1 Jun 2022 |
| Copy of Layout Approval (in case of layout)File: 2022 06 01_NE_Phase-3.pdf | 1 Jun 2022 |
| Copy of Layout Approval (in case of layout)File: NA Declaration.pdf | 1 Jun 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: NA Order Compressed part 1.pdf | 1 Jun 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: NA Order Compressed part 2.pdf | 1 Jun 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: NA Order Compressed Part 3.pdf | 1 Jun 2022 |
| Declaration about Commencement CertificateFile: CC Decalaration.pdf | 1 Jun 2022 |
| Declaration in FORM BFile: Form B P3.pdf | 1 Jun 2022 |
| CERSAI detailsFile: 133 1 2.pdf | 1 Jun 2022 |
| CERSAI detailsFile: 133 3 to 40.pdf | 1 Jun 2022 |
| CERSAI detailsFile: 133 41 to 80.pdf | 1 Jun 2022 |
| CERSAI detailsFile: 133 81 to 120.pdf | 1 Jun 2022 |
| CERSAI detailsFile: 133 121 to 150.pdf | 1 Jun 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 7 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 85 filed documents as one ZIP, foldered, with a manifest
Keep Foothills of Matheran P - 3 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Shilar River5,900+ in Raigarh
Filed coordinates, straight-line distance. 38 registered projects within 2 km.
Bellezza Woods
DOTOM BUILD SQUARE
Winds of Calm
Eiffel Lifespaces Pvt Ltd
PURANIK CITY SECTOR 2
Puranik Builders Limited
Foothills of Matheran P - 2
HOABL Impactum Land Private Limited
FLORENCE TOWN
BRIGHT DEVELOPERS
The Destination
DOVE BUILDMART PRIVATE LIMITED
See every Raigarh project, with the district possession charts
Builder: HOABL Impactum Land Private Limited
HOABL Impactum Land Private Limited has 8 registrations on MahaRERA, including Foothills of Matheran P - 1 and Foothills of Matheran P - 2. Its filings disclose 16 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Foothills of Matheran P - 3 is delayed beyond 30 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Foothills of Matheran P - 3?
The registered promoter entity is HOABL Impactum Land Private Limited, a company as per the filing. Its CIN U70109MH2022PTC374991 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Foothills of Matheran P - 3?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Foothills of Matheran P - 3?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Foothills of Matheran P - 3?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Foothills of Matheran P - 3?
The professionals named in the filing: Architect: Sanjay Jain; Engineer: Swapnil Jadhav; Engineer: Akil Ahmad; Chartered Accountant: Chirag Sarvaiya; Chartered Accountant: U S MISHRA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Foothills of Matheran P - 3?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback