Home / Browse projects / Raigarh, Maharashtra / Eshaanya Phase 1

Completed No litigation declared Plotted project

Eshaanya Phase 1

By Ashwyn Suresh Patkar

RG-MH-09691 · RERA P52000000305 · Last updated on MahaRERA portal: 24 Feb 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 29 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
5 of 49Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 137 documents Report an error

Eshaanya Phase 1 is a Plotted project by Ashwyn Suresh Patkar in Raigarh, Maharashtra, registered with MahaRERA as P52000000305 on 15 Jul 2017. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 29 months from the original filing. 44 of the 49 units on this registration are recorded sold or booked.

At a glance

Project

  • NameEshaanya Phase 1
  • TypePlotted
  • Location
    • Mechkarwadi road
    • Dhamni
    • Karjat
    • Raigarh
    • 410201
  • Pincode410201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000000305
  • ReraGenie IDRG-MH-09691

Builder

  • NameAshwyn Suresh Patkar
  • Entity typeIndividual
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2017First promiseJul 2023Revised toDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on15 Jul 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 1 Jul 2023)
  • BuildingsNot stated in filing
  • Documents filed137 files

Current status

90%44 of 49 units booked
80.9%Work done, per cost certificate

Figures as on 24 Feb 2026, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 24 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area92,316 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 Jul 2025
LandownerVillageDistrict
Suresh Madhukar PatkarDhamniRaigarh

Approvals and building plan

Sanctioning authorityCollector of Raigad
Permissible FSI13536.17
Proposed, not sanctioned13,536 sq m

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchQueens Necklace Shopping Paradise, Plot no 1, Sector 18, Sanpada, Navi Mumbai , 400705
Estimated costRs 13.60 cr
Cost incurredRs 11.00 cr
Work done80.88%
BuildingWingEstimatedIncurred
-NARs 13.60 crRs 11.00 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSoyub Talib Architects Pvt Ltd
EngineerPravin Ramkrishna Kulkarni
Chartered AccountantRJ Gandhi & Associates
Chartered AccountantA.J. Kotwal & Co. LLP
PartnerRole in project
Ashwyn Suresh Patkar-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000016683Jul 2023 → Jul 2025

Reason as filed by the promoterEshaanya Phase 1 is a Plotted development comprising of 92316 square metres Due to Nature of development, the client selects the plot and then the bungalow is made to customisation. Moreover, the bungalow is handed over to each purchaser as per terms of agreement and all common areas and amenities are completed by more than 75 % . Due to covid , there had been a slow down in work progress and sales. We have taken consent of 65 % purchasers and are content with our current work progress.

EA08092502535Jul 2023 → Dec 2025

Reason as filed by the promoterWe, Mr. Suresh Patkar and Mr. Ashwyn Patkar the Promoters of the above project, wish to submit the following for your kind consideration: We had undertaken the development of 49 Plots, out of which we have sold 44 plots. We received Occupancy Certificate on 20.07.2025 and handed over possession to 41 Allottees The original project completion date as per registration was 31.12.2025 However, due to a slight delay in obtaining the Occupancy Certificate, the process was extended. We are pleased to inform you that the project is now 100% completed. Accordingly, we request an extension of the projec

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 24 Feb 2026

Documents filed137

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 137 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Completion CertificateFile: Email 1 OC No 13 OC Dt 03 03 2020.pdf24 Feb 2026
Completion CertificateFile: Email 2 OC No 15 OC Dt 21 04 2022.pdf24 Feb 2026
Completion CertificateFile: Email 3 OC No 28 OC Dt 28 04 2023.pdf24 Feb 2026
Completion CertificateFile: Email 4 OC No 50 OC Dt 28 06 2023.pdf24 Feb 2026
Completion CertificateFile: Email 5 OC No 68 OC Dt 27 06 2024.pdf24 Feb 2026
Completion CertificateFile: Email 6 OC No 66 OC Dt 20 09 2024.pdf24 Feb 2026
Completion CertificateFile: Email 7 OC No 38 OC Dt 24 10 2025.pdf24 Feb 2026
Completion CertificateFile: ESHAANYA OC LIST.pdf24 Feb 2026
Form 5 (FY 2017-2018)File: FORM 5 F Y 2017 18.pdf22 Dec 2025
Form 5 (FY 2018-2019)File: FORM 5 F Y 2018 19.pdf22 Dec 2025
Form 5 (FY 2020-2021)File: Form 5 FY 2020 21.pdf22 Dec 2025
Form 5 (FY 2022-2023)File: Form 5 FY 2022 23.pdf22 Dec 2025
Form 5 (FY 2023-2024)File: Form 5 FY 2023 24.pdf22 Dec 2025
Form 5 (FY 2019-2020)File: Form 5 FY 2019 20.pdf22 Dec 2025
Form 5 (FY 2021-2022)File: Form 5 FY 2021 22.pdf22 Dec 2025
Form 5 (FY 2024-2025)File: FORM 5.pdf19 Dec 2025
Completion CertificateFile: OC 2 Dt 21 04 2022.pdf18 Dec 2025
Completion CertificateFile: OC 1 Dt 03 03 2020.pdf18 Dec 2025
Completion CertificateFile: OC 3 Dt 28 04 2023.pdf18 Dec 2025
Completion CertificateFile: OC 4 Dt 28 06 2023.pdf18 Dec 2025
Completion CertificateFile: OC 5 Dt 27 06 2024.pdf18 Dec 2025
Completion CertificateFile: OC 6 Dt 20 09 2024.pdf18 Dec 2025
Completion CertificateFile: OC 7 Dt 24 10 2025.pdf18 Dec 2025
Withdrawal Update Form 1File: FORM-1.pdf15 Oct 2025
Withdrawal Update Form 2File: FORM-2.pdf15 Oct 2025
Withdrawal Update Form 3File: FORM-3.pdf15 Oct 2025
Withdrawal Update Form 1File: Architects Certificate 22.pdf6 Oct 2025
Withdrawal Update Form 2File: Engineering Certificate 23 (JUNE 24).pdf6 Oct 2025
Withdrawal Update Form 3File: CA certifiate -30 Eshaanya.pdf6 Oct 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1.pdf15 Apr 2025
Certificates of CA (Form 3)File: FORM-3.pdf15 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2.pdf15 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 (2).pdf30 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 (2).pdf30 Dec 2024
Certificates of CA (Form 3)File: FORM 3.pdf18 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf18 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf18 Nov 2024
Certificates of CA (Form 3)File: FORM 3.pdf18 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 23 (JUNE 24).pdf15 Jul 2024
Certificates of CA (Form 3)File: CA certifiate -30 Eshaanya.pdf15 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 22.pdf17 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 22.pdf17 Apr 2024
Certificates of CA (Form 3)File: CA certifiate -29 Eshaanya.pdf17 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 20 (july,2023 to Sept,2023) - Phase -1.pdf31 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 21.pdf31 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 17 (Oct,2022 To Dec,2022) Phase -1.pdf31 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 18 (Jan,2023 To March,2023) Phase -1.pdf31 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 19 (April,2023 To June,2023) Phase -1.pdf31 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 20.pdf31 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 21 (October,2023 To December,2023) Phase-1.pdf31 Jan 2024
Certificates of CA (Form 3)File: CA certifiate -28 Eshaanya.pdf31 Jan 2024
Certificates of CA (Form 3)File: CA certifiate -25 Eshaanya.pdf11 Nov 2023
Certificates of CA (Form 3)File: CA certifiate -26 Eshaanya.pdf11 Nov 2023
Certificates of CA (Form 3)File: CA certifiate -27 Eshaanya.pdf11 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Eshaanya Phase 1.pdf9 Nov 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold inventory P1 -15 MAY 23.pdf27 May 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold inventory P1 -15 MAY 23.pdf27 May 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Form -A - Phase -1.pdf27 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 1 - (Sept,2018 To Dec,2018) Phase - I.pdf22 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 2 - (Jan,2019 To March,2019) Phase - I.pdf22 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 3 - (April,2019 To June,2019) Phase - I.pdf22 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 4 - (July,2019 To Sept,2019) Phase - I.pdf22 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 5 - (Oct,2019 To Dec,2019) Phase - I.pdf22 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 6 - (Jan,2020 To March,2020) Phase - I.pdf22 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 7 - (April,2020 To June,2020) Phase - I.pdf22 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 9 - (Oct,2020 To Dec,2020) Phase - I.pdf22 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 10 - (Jan,2021 To March,2021) Phase-1.pdf22 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 11 - (April,2021 To June,2021) Phase-1.pdf22 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 12 - (July,2021 To Sept,2021) Phase - I.pdf22 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 13 - (Oct,2021 To Dec,2021) Phase - I.pdf22 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 14 (January,2022 to March,2022) - Phase -1.pdf22 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 15 (April,2022 to June,2022) - Phase - 1.pdf22 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 16 (July,2022 To September,2022) Phase -1.pdf22 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 17 (October,2022 To December,2022) Phase -1.pdf22 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 18 (January,2023 to March,2023) - Phase -1_compressed (1).pdf22 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 1 (Sept,2018 To Dec,2018) Phase - I.pdf22 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 2 (Jan,2019 to March 2019) - Phase - 1.pdf22 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 3 (April,2019 to June,2019) - Phase - 1.pdf22 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 4 (July,2019 to Sept,2019) - Phase - 1.pdf22 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 5 (Oct,2019 to Dec,2019) - Phase - 1.pdf22 May 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
VishwamukhaVishwamukha Plot No 89 Sector 50 Nerul Navi Mumbai 40070639CompletedApr 2017Late, Apr 2017

How this compares with Raigarh

90%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 29 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Eshaanya Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dhamni5,900+ in Raigarh

Builder: Ashwyn Suresh Patkar

Ashwyn Suresh Patkar has 1 registration on MahaRERA, including Eshaanya Phase 1. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Eshaanya Phase 1 is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Eshaanya Phase 1?

The registered promoter entity is Ashwyn Suresh Patkar, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Eshaanya Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Eshaanya Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Eshaanya Phase 1?

The professionals named in the filing: Architect: Soyub Talib Architects Pvt Ltd; Engineer: Pravin Ramkrishna Kulkarni; Chartered Accountant: RJ Gandhi & Associates; Chartered Accountant: A.J. Kotwal & Co. LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Eshaanya Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Eshaanya Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Eshaanya Phase 1 to a free account