Home / Browse projects / Pune, Maharashtra / EMERALD VISTA

Completed No litigation declared Residential / Group Housing project

EMERALD VISTA

By PADMAVATI LANDMARKS

RG-MH-05626 · RERA P52100076742 · Last updated on MahaRERA portal: 11 Feb 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promisedregistration recorded completed
7 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 90%
7 of 18Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 55 documents Report an error

EMERALD VISTA is a Residential / Group Housing project by PADMAVATI LANDMARKS in Pune, Maharashtra, registered with MahaRERA as P52100076742 on 25 Jun 2024. The registration is recorded completed; possession was promised by 30 Jun 2026. 11 of the 18 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameEMERALD VISTA
  • TypeResidential / Group Housing
  • Location
    • CTS NO 366A/13
    • FINAL PLOT NO 287/8
    • GHORPADE PETH
    • EKBOTE COLONY
    • Swargate
    • Haveli
    • Pune
    • 411042
  • Pincode411042
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100076742
  • ReraGenie IDRG-MH-05626

Builder

  • NamePADMAVATI LANDMARKS
  • Entity typePartnership
  • PartnersVINITA BRIJESH BALDOTA, MAHESH SHANTILAL GANDHI, RAJUL MAHENDRA JAIN
  • Other registrations1 more →
  • Completed2 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredJun 2024PromisedJun 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on25 Jun 2024
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed55 files

Current status

61%11 of 18 units booked
98.4%Work done, per cost certificate

Figures as on 11 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
EMERALD VISTANA6618018

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

EMERALD VISTA: 80% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 11 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed15

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots15
Closed/Covered15

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area516 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
PADMAVATI LANDMARKSPune (M Corp.)Pune
NAMDEO ALIAS JAYWANT TUKARAM SONAWANEPune (M Corp.)Pune
MANGAL NAMDEO SONAWANEPune (M Corp.)Pune
SHEKHAR NAMDEO SONAWANEPune (M Corp.)Pune
SWAPNIL NAMDEO SONAWANEPune (M Corp.)Pune
VIKRAM NAMDEO SONAWANEPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI1647.3
Proposed, not sanctioned1,647 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHAVANI PETH, TIMBER MARKET ROAD, PUNE
Estimated costRs 4.56 cr
Cost incurredRs 4.49 cr
Work done98.39%
BuildingWingEstimatedIncurred
EMERALD VISTANARs 4.56 crRs 4.49 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGIRISH M KARANDE
EngineerMALHARI DHAWALE
Chartered AccountantINAMDAR BALDOTA JAIN & CO
PartnerRole in project
PADMAVATI LANDMARKS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 May 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Dec 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Dec 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed55

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Rera Mail.pdf11 Feb 2026
Occupational CertificateFile: OC Emerald vista.pdf31 Jan 2026
Withdrawal Update Form 1File: Architect Certificate-2.pdf20 Jan 2026
Withdrawal Update Form 2File: Engineer Certificate-1.pdf20 Jan 2026
Withdrawal Update Form 3File: CA Certificate-1.pdf20 Jan 2026
Withdrawal Update Form 1File: Architect Certificate.pdf18 Oct 2025
Withdrawal Update Form 2File: Eningeer Certificate.pdf18 Oct 2025
Withdrawal Update Form 3File: CA Certificate.pdf18 Oct 2025
Form 5 (FY 2024-2025)File: DocScanner 30 Sept 2025 3-26 pm.pdf23 Jul 2025
Withdrawal Update Form 1File: Architect Certificate.pdf19 Jul 2025
Withdrawal Update Form 1File: Architect Certificate.pdf19 Jul 2025
Withdrawal Update Form 1File: Architect Certificate.pdf19 Jul 2025
Withdrawal Update Form 2File: Engineer Certificate.pdf19 Jul 2025
Withdrawal Update Form 2File: Engineer Certificate.pdf19 Jul 2025
Withdrawal Update Form 2File: Engineer Certificate.pdf19 Jul 2025
Withdrawal Update Form 3File: CA Certificate.pdf19 Jul 2025
Withdrawal Update Form 3File: CA Certificate.pdf19 Jul 2025
Withdrawal Update Form 3File: CA Certificate.pdf19 Jul 2025
Commencement certificateFile: Commencement Certificate.pdf8 Jul 2025
Form 1File: Architect Certificate.pdf4 Jun 2025
Form 2File: Engineer Certificate.pdf4 Jun 2025
Form 3File: CA Certificate.pdf4 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold & Unsold Inventory.pdf4 Jun 2025
Layout approvalFile: Revised Sanction Plan.pdf11 Dec 2024
Building plan approvalFile: Revised Sanction Plan.pdf11 Dec 2024
Copy of Layout Approval (in case of layout)File: Revised Sanction Plan.pdf11 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PADMAVATI LANDMARKS - ARCHITECT LETTER.pdf11 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form3.pdf11 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf11 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: Revised Sanction Plan.pdf11 Dec 2024
Details of encumbrances concerned to FinanceFile: No financial and legal emcumberce.pdf20 May 2024
Details of encumbrances concerned to LegalFile: No financial and legal emcumberce.pdf20 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA certificate.pdf20 May 2024
Other - TechnicalFile: Annexure A declaration cum undertaking.pdf9 May 2024
Layout approvalFile: RERA NEW PLAN.pdf4 May 2024
Copy of Layout Approval (in case of layout)File: RERA NEW PLAN.pdf4 May 2024
Deviation Report with respect to Allotment letterFile: deviation letter with allotment letter.pdf4 May 2024
Deviation Report with respect to model copy of AgreementFile: NEW Deviation letter with agreement sale.pdf4 May 2024
Building plan approvalFile: RERA NEW PLAN.pdf2 May 2024
PAN CardFile: PAN cards promoter and landlords.pdf2 May 2024
Copy of the legal title reportFile: legal title report.pdf2 May 2024
Details of encumbrances concerned to FinanceFile: No financial and legal emcumberce.pdf2 May 2024
Details of encumbrances concerned to LegalFile: No financial and legal emcumberce.pdf2 May 2024
Building Plan Approval / NA Order for plotted developmentFile: RERA NEW PLAN.pdf2 May 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf2 May 2024
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf2 May 2024
Declaration in FORM BFile: form B.pdf2 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE.pdf2 May 2024
CERSAI detailsFile: CERSAI undertaking letter.pdf2 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Mahesh Gandhi disclosure of interest in other real estate organization.pdf2 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Vinita Baldota disclosure of interest in other real estate organization.pdf2 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Rajul Jain disclosure of interest in other real estate organization.pdf2 May 2024
Proforma of Agreement for saleFile: NEW RERA AGREEMENT.pdf2 May 2024
Proforma of Allotment letterFile: Allotment Letter -RERA-.pdf2 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A Declaration about Separate Bank Account.pdf2 May 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
NAKSHATRA710A8 GURUNANKNAGAR18CompletedJun 2023May 2023

How this compares with Pune

61%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep EMERALD VISTA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near EKBOTE COLONY13,700+ in Pune

2 kmEMERALD VISTACompleted 49Lapsed / revoked 46Other 90Dot size: filed unitsN

Filed coordinates, straight-line distance. 185 registered projects within 2 km.

Builder: PADMAVATI LANDMARKS

PADMAVATI LANDMARKS has 2 registrations on MahaRERA, including NAKSHATRA and EMERALD VISTA. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if EMERALD VISTA is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of EMERALD VISTA?

The registered promoter entity is PADMAVATI LANDMARKS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in EMERALD VISTA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for EMERALD VISTA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at EMERALD VISTA?

The professionals named in the filing: Architect: GIRISH M KARANDE; Engineer: MALHARI DHAWALE; Chartered Accountant: INAMDAR BALDOTA JAIN & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EMERALD VISTA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EMERALD VISTA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EMERALD VISTA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.