Home / Browse projects / Mumbai Suburban, Maharashtra / EL SIGNORA

Registration lapsed No litigation declared Residential / Group Housing project

EL SIGNORA

By PARAS BUILDERS (1985)

RG-MH-25551 · RERA P51800005086 · Last updated on MahaRERA portal: 6 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 44 months past the filed date
  • 5 complaints at MahaRERA
  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Feb 2023Possession promised44 months past this date
14 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 60%
5Complaints at MahaRERAon this registration
Jump to the 95 documents Report an error

EL SIGNORA is a Residential / Group Housing project by PARAS BUILDERS (1985) in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800005086 on 9 Aug 2017. Possession was promised by 28 Feb 2023 and is now 44 months past that date. The completion date has moved by 11 months from the original filing. 5 complaints are on record with the regulator.

At a glance

Project

  • NameEL SIGNORA
  • TypeResidential / Group Housing
  • Location
    • OFF NEW LINK ROAD
    • ADARSH NAGAR
    • Andheri
    • Mumbai Suburban
    • 400102
  • Pincode400102
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800005086
  • ReraGenie IDRG-MH-25551

Builder

  • NamePARAS BUILDERS (1985)
  • Entity typePartnership
  • PartnersNILESH GHELABHAI SHAH, PARAG KHIMJI SHAH, GELABHAI DAYABHAI SHAH

Key dates

44 months past promisethis monthRegisteredAug 2017First promiseMar 2022Revised toFeb 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion28 Feb 2023
  • Revised completionRevised to 28 Feb 2023 (originally 30 Mar 2022)
  • Buildings2 building records
  • Documents filed95 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHIV SFURTI SRA CHS LTD REHAB BLDG NO 2NA240000
EL SIGNORA SALE BLDG 3NA260000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 6 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 60%.

SHIV SFURTI SRA CHS LTD REHAB BLDG NO 256%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
EL SIGNORA SALE BLDG 391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 6 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes70%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes60%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed51

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots51
Closed/Covered51

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,950 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
M/s. Paradigm Evolvers LLPAndheriMumbai Suburban

Approvals and building plan

Permissible FSI11942.77
Proposed, not sanctioned10,060 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSana Building, Linking Road, Santacruz West, Mumbai - 400 054

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGRIHA RACHANA
EngineerFAKHRI A HASAMWALA AND ASSOCIATES
PartnerRole in project
PARAS BUILDERS (1985)-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800011548Mar 2022 → Feb 2023

Reason as filed by the promoterThe Developer is implementing the slum rehabilitation scheme by constructing 2 rehab buildings and one Sale building No. 3 (“EL Signora Project”). The completion of the scheme has been delayed over a period of time essentially due to the current force majeure event, i.e. outbreak of COVID-19 pandemic, due to which there has not only been a disruption in the smooth functioning of the real estate sector but also a disruption in the day to day functioning of the planning authorities due to which considerable time was taken by the team of architects & liasoning officers to get the plans approved &

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC006000000198929Prakash Vishram BaneParas Builder (1985)10/11/2021
CC006000000209767Mr. Shivanna M ShettyM/s Paras Builders (1985)29/01/2022
CC006000000209724PARADIGM EVOLVERS LLPRONGOM TAGORE MUKERJI04/02/2022
CC006000000333839Mr Rongom Tagore MukherjiParadigm Evolvers LLP30/12/2022
CC006000000375126Paras Builders 1985Manoj Kumar Pandey12/04/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 May 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jul 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed95

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 95 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: El Signora sold unsold till Dec 2024.pdf6 Feb 2025
Disclosure of sold/ booked inventoryFile: El-Signora sold unsold till sept 2024.pdf30 Oct 2024
Disclosure of sold/ booked inventoryFile: EL- Signora sold unsold till june 2024.pdf5 Aug 2024
Disclosure of sold/ booked inventoryFile: El Signora sold unsold inventory Mar 2024.pdf5 Jun 2024
Disclosure of sold/ booked inventoryFile: El signora sold unsold inventory till sept 2023.pdf28 Feb 2024
Disclosure of sold/ booked inventoryFile: EL Signora sold unsold - Dec 2023.pdf28 Feb 2024
Disclosure of sold/ booked inventoryFile: EL Signora Sold Unsold June 2023.pdf18 Aug 2023
Details of encumbrancesFile: EL Signora no encumbrance 07062023.pdf7 Jun 2023
Disclosure of sold/ booked inventoryFile: March 2023 Sold-Unsold Inventory.pdf15 May 2023
Certificates of CA (Form 3)File: Dec 18.pdf15 May 2023
Certificates of CA (Form 3)File: Mar 19.pdf15 May 2023
Certificates of CA (Form 3)File: June 19.pdf15 May 2023
Certificates of CA (Form 3)File: Sep 19.pdf15 May 2023
Certificates of CA (Form 3)File: Dec 19.pdf15 May 2023
Certificates of CA (Form 3)File: Mar 20.pdf15 May 2023
Certificates of CA (Form 3)File: Jun 20.pdf15 May 2023
Certificates of CA (Form 3)File: Sep 20.pdf15 May 2023
Certificates of CA (Form 3)File: Dec 20.pdf15 May 2023
Certificates of CA (Form 3)File: Mar 21.pdf15 May 2023
Certificates of CA (Form 3)File: Jun 21.pdf15 May 2023
Certificates of CA (Form 3)File: Sep 21.pdf15 May 2023
Certificates of CA (Form 3)File: Dec 21.pdf15 May 2023
Disclosure of sold/ booked inventoryFile: EL Signora Sold Unsold Dec, 2021.pdf13 Feb 2023
Disclosure of sold/ booked inventoryFile: EL Signora Sold Unsold March, 2022.pdf13 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect's Certificate 2023.PDF10 Feb 2023
Disclosure of sold/ booked inventoryFile: El-Signora Sold Unsold Sept, 2022.PDF10 Feb 2023
Disclosure of sold/ booked inventoryFile: El-Signora Sold Unsold Dec, 2022.PDF10 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Signed Form 5 EL Signora FY 2019-20.pdf10 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Signed Form 5 EL Signora FY 2020-21.pdf10 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Signed Form 5 EL Signora FY 2021-22.pdf10 Feb 2023
Form 2AFile: QUALITY ASSURANCE FORM 2A RERA Oct-Dec 2022.pdf4 Feb 2023
Form 2AFile: FORM 2A FOR QUATER ENDING SEP 2022.pdf3 Feb 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD DISCLOSURE UPTIL 30TH JUNE, 2022_compressed.pdf25 Jul 2022
Form 2AFile: QUALITY ASSURANCE FORM 2A RERA July-Sept 2021.pdf7 Jul 2022
Form 2AFile: QUALITY ASSURANCE FORM 2A RERA Oct-Dec 2021.pdf7 Jul 2022
Form 2AFile: QUALITY ASSURANCE FORM 2A RERA Jan-March 2022.pdf7 Jul 2022
OtherFile: Part OC.pdf7 Jul 2022
Disclosure of sold/ booked inventoryFile: sold unsold elsignora.pdf22 Oct 2021
Form 2AFile: Form 2A (December2020).pdf27 Aug 2021
Form 2AFile: Form 2A (March2021).pdf27 Aug 2021
Form 2AFile: Form 2A (September2020).pdf27 Aug 2021
Form 2AFile: Form 2A(June2021).pdf27 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.PDF21 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.PDF21 Jun 2021
Details of encumbrancesFile: Declaration on Encumbrance.pdf5 Mar 2021
Proforma of Allotment letterFile: RERA Agreement (2).pdf5 Mar 2021
Proforma of Allotment letterFile: RERA AGREEMENT.pdf22 Sep 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Certificate 14-8-2020_compressed.pdf20 Aug 2020
Form 2AFile: QUALITY ASSURANCE FORM 2A RERA 20-7-2020_compressed.pdf20 Aug 2020
Building plan approvalFile: IOA (2).pdf29 Jul 2020
Building Plan Approval (IOD)File: IOA (2).pdf29 Jul 2020
Commencement Certificates / NA Order for plotted developmentFile: CC Sale Building.pdf29 Jul 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Paradigm Evolvers LLP.pdf6 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Sep.pdf29 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec.pdf29 Jan 2020
Form 2AFile: Form 2A Sep.pdf29 Jan 2020
Form 2AFile: Form 2A Dec.pdf29 Jan 2020
Details of encumbrancesFile: Declration on Encumbrance on the Project_07_10_2019.pdf12 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Certificate_Shivsfurti_2019_compressed.pdf20 Aug 2019
Form 2AFile: Form 2A June'19 Certi.pdf20 Aug 2019
OtherFile: Revised LOI dated 16 May 2019.pdf3 Jun 2019
Copy of the legal title reportFile: Title Certificate_07-12-2018_compressed.pdf31 May 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA FORM 1.pdf31 May 2019
Form 2AFile: QUALITY ASSURANCE March'19 Certi.pdf31 May 2019
Proforma of Allotment letterFile: AFS.pdf31 May 2019
Details of encumbrancesFile: Decleration of Encumbrance_PELLP_26-04-2019.pdf6 May 2019
Form 2AFile: Jamsandekar.PDF12 Mar 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - El-Signora-min.pdf10 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Form 2.pdf10 Dec 2018
Certificates of CA (Form 3)File: CA Certificate_Form 3.pdf10 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf12 Nov 2018
Details of encumbrancesFile: No Encumbrance Declaration.PDF29 Oct 2018
Certificates of CA (Form 5)File: FORM 5 PARAS.pdf11 Oct 2018
Building plan approvalFile: IOD Latter (1).pdf19 Sep 2018
Building plan approvalFile: IOD Latter (1).pdf19 Sep 2018
Building Plan Approval (IOD)File: IOD Latter (1).pdf19 Sep 2018
Building Plan Approval (IOD)File: IOD Latter (1).pdf19 Sep 2018
Layout approvalFile: LAYOUT PLAN 110518.pdf25 Jul 2018
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN 110518.pdf25 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: CC OF Rehab Bldg No 2 DTD 220618.pdf25 Jul 2018

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 11 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep EL SIGNORA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ADARSH NAGAR6,700+ in Mumbai Suburban

2 kmEL SIGNORACompleted 94Lapsed / revoked 49Abeyance 1Other 113Dot size: filed unitsN

Filed coordinates, straight-line distance. 257 registered projects within 2 km.

Builder: PARAS BUILDERS (1985)

PARAS BUILDERS (1985) has 1 registration on MahaRERA, including EL SIGNORA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that EL SIGNORA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if EL SIGNORA is delayed beyond 28 Feb 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of EL SIGNORA?

The registered promoter entity is PARAS BUILDERS (1985), a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in EL SIGNORA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against EL SIGNORA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for EL SIGNORA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at EL SIGNORA?

The professionals named in the filing: Architect: GRIHA RACHANA; Engineer: FAKHRI A HASAMWALA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EL SIGNORA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EL SIGNORA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EL SIGNORA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.