EL SIGNORA
RG-MH-25551 · RERA P51800005086 · Last updated on MahaRERA portal: 6 Feb 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 44 months past the filed date
- 5 complaints at MahaRERA
- Completion date moved by 11 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
EL SIGNORA is a Residential / Group Housing project by PARAS BUILDERS (1985) in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800005086 on 9 Aug 2017. Possession was promised by 28 Feb 2023 and is now 44 months past that date. The completion date has moved by 11 months from the original filing. 5 complaints are on record with the regulator.
At a glance
Project
- NameEL SIGNORA
- TypeResidential / Group Housing
- Location
- OFF NEW LINK ROAD
- ADARSH NAGAR
- Andheri
- Mumbai Suburban
- 400102
- Pincode400102
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800005086
- ReraGenie IDRG-MH-25551
Builder
- NamePARAS BUILDERS (1985)
- Entity typePartnership
- PartnersNILESH GHELABHAI SHAH, PARAG KHIMJI SHAH, GELABHAI DAYABHAI SHAH
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on9 Aug 2017
- Promised completion28 Feb 2023
- Revised completionRevised to 28 Feb 2023 (originally 30 Mar 2022)
- Buildings2 building records
- Documents filed95 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHIV SFURTI SRA CHS LTD REHAB BLDG NO 2 | NA | 24 | 0 | 0 | 0 | 0 |
| EL SIGNORA SALE BLDG 3 | NA | 26 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 6 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 60%.
SHIV SFURTI SRA CHS LTD REHAB BLDG NO 256%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 55% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
EL SIGNORA SALE BLDG 391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 6 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 70% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 60% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed51
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M/s. Paradigm Evolvers LLP | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | GRIHA RACHANA |
| Engineer | FAKHRI A HASAMWALA AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| PARAS BUILDERS (1985) | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Developer is implementing the slum rehabilitation scheme by constructing 2 rehab buildings and one Sale building No. 3 (“EL Signora Project”). The completion of the scheme has been delayed over a period of time essentially due to the current force majeure event, i.e. outbreak of COVID-19 pandemic, due to which there has not only been a disruption in the smooth functioning of the real estate sector but also a disruption in the day to day functioning of the planning authorities due to which considerable time was taken by the team of architects & liasoning officers to get the plans approved &
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000198929 | Prakash Vishram Bane | Paras Builder (1985) | 10/11/2021 |
| CC006000000209767 | Mr. Shivanna M Shetty | M/s Paras Builders (1985) | 29/01/2022 |
| CC006000000209724 | PARADIGM EVOLVERS LLP | RONGOM TAGORE MUKERJI | 04/02/2022 |
| CC006000000333839 | Mr Rongom Tagore Mukherji | Paradigm Evolvers LLP | 30/12/2022 |
| CC006000000375126 | Paras Builders 1985 | Manoj Kumar Pandey | 12/04/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 May 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Jul 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Jul 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed95
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 95 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: El Signora sold unsold till Dec 2024.pdf | 6 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: El-Signora sold unsold till sept 2024.pdf | 30 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: EL- Signora sold unsold till june 2024.pdf | 5 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: El Signora sold unsold inventory Mar 2024.pdf | 5 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: El signora sold unsold inventory till sept 2023.pdf | 28 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: EL Signora sold unsold - Dec 2023.pdf | 28 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: EL Signora Sold Unsold June 2023.pdf | 18 Aug 2023 |
| Details of encumbrancesFile: EL Signora no encumbrance 07062023.pdf | 7 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: March 2023 Sold-Unsold Inventory.pdf | 15 May 2023 |
| Certificates of CA (Form 3)File: Dec 18.pdf | 15 May 2023 |
| Certificates of CA (Form 3)File: Mar 19.pdf | 15 May 2023 |
| Certificates of CA (Form 3)File: June 19.pdf | 15 May 2023 |
| Certificates of CA (Form 3)File: Sep 19.pdf | 15 May 2023 |
| Certificates of CA (Form 3)File: Dec 19.pdf | 15 May 2023 |
| Certificates of CA (Form 3)File: Mar 20.pdf | 15 May 2023 |
| Certificates of CA (Form 3)File: Jun 20.pdf | 15 May 2023 |
| Certificates of CA (Form 3)File: Sep 20.pdf | 15 May 2023 |
| Certificates of CA (Form 3)File: Dec 20.pdf | 15 May 2023 |
| Certificates of CA (Form 3)File: Mar 21.pdf | 15 May 2023 |
| Certificates of CA (Form 3)File: Jun 21.pdf | 15 May 2023 |
| Certificates of CA (Form 3)File: Sep 21.pdf | 15 May 2023 |
| Certificates of CA (Form 3)File: Dec 21.pdf | 15 May 2023 |
| Disclosure of sold/ booked inventoryFile: EL Signora Sold Unsold Dec, 2021.pdf | 13 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: EL Signora Sold Unsold March, 2022.pdf | 13 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect's Certificate 2023.PDF | 10 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: El-Signora Sold Unsold Sept, 2022.PDF | 10 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: El-Signora Sold Unsold Dec, 2022.PDF | 10 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Signed Form 5 EL Signora FY 2019-20.pdf | 10 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Signed Form 5 EL Signora FY 2020-21.pdf | 10 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Signed Form 5 EL Signora FY 2021-22.pdf | 10 Feb 2023 |
| Form 2AFile: QUALITY ASSURANCE FORM 2A RERA Oct-Dec 2022.pdf | 4 Feb 2023 |
| Form 2AFile: FORM 2A FOR QUATER ENDING SEP 2022.pdf | 3 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD DISCLOSURE UPTIL 30TH JUNE, 2022_compressed.pdf | 25 Jul 2022 |
| Form 2AFile: QUALITY ASSURANCE FORM 2A RERA July-Sept 2021.pdf | 7 Jul 2022 |
| Form 2AFile: QUALITY ASSURANCE FORM 2A RERA Oct-Dec 2021.pdf | 7 Jul 2022 |
| Form 2AFile: QUALITY ASSURANCE FORM 2A RERA Jan-March 2022.pdf | 7 Jul 2022 |
| OtherFile: Part OC.pdf | 7 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: sold unsold elsignora.pdf | 22 Oct 2021 |
| Form 2AFile: Form 2A (December2020).pdf | 27 Aug 2021 |
| Form 2AFile: Form 2A (March2021).pdf | 27 Aug 2021 |
| Form 2AFile: Form 2A (September2020).pdf | 27 Aug 2021 |
| Form 2AFile: Form 2A(June2021).pdf | 27 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.PDF | 21 Jun 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.PDF | 21 Jun 2021 |
| Details of encumbrancesFile: Declaration on Encumbrance.pdf | 5 Mar 2021 |
| Proforma of Allotment letterFile: RERA Agreement (2).pdf | 5 Mar 2021 |
| Proforma of Allotment letterFile: RERA AGREEMENT.pdf | 22 Sep 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Certificate 14-8-2020_compressed.pdf | 20 Aug 2020 |
| Form 2AFile: QUALITY ASSURANCE FORM 2A RERA 20-7-2020_compressed.pdf | 20 Aug 2020 |
| Building plan approvalFile: IOA (2).pdf | 29 Jul 2020 |
| Building Plan Approval (IOD)File: IOA (2).pdf | 29 Jul 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Sale Building.pdf | 29 Jul 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Paradigm Evolvers LLP.pdf | 6 Feb 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Sep.pdf | 29 Jan 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec.pdf | 29 Jan 2020 |
| Form 2AFile: Form 2A Sep.pdf | 29 Jan 2020 |
| Form 2AFile: Form 2A Dec.pdf | 29 Jan 2020 |
| Details of encumbrancesFile: Declration on Encumbrance on the Project_07_10_2019.pdf | 12 Oct 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Certificate_Shivsfurti_2019_compressed.pdf | 20 Aug 2019 |
| Form 2AFile: Form 2A June'19 Certi.pdf | 20 Aug 2019 |
| OtherFile: Revised LOI dated 16 May 2019.pdf | 3 Jun 2019 |
| Copy of the legal title reportFile: Title Certificate_07-12-2018_compressed.pdf | 31 May 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA FORM 1.pdf | 31 May 2019 |
| Form 2AFile: QUALITY ASSURANCE March'19 Certi.pdf | 31 May 2019 |
| Proforma of Allotment letterFile: AFS.pdf | 31 May 2019 |
| Details of encumbrancesFile: Decleration of Encumbrance_PELLP_26-04-2019.pdf | 6 May 2019 |
| Form 2AFile: Jamsandekar.PDF | 12 Mar 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - El-Signora-min.pdf | 10 Dec 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Form 2.pdf | 10 Dec 2018 |
| Certificates of CA (Form 3)File: CA Certificate_Form 3.pdf | 10 Dec 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf | 12 Nov 2018 |
| Details of encumbrancesFile: No Encumbrance Declaration.PDF | 29 Oct 2018 |
| Certificates of CA (Form 5)File: FORM 5 PARAS.pdf | 11 Oct 2018 |
| Building plan approvalFile: IOD Latter (1).pdf | 19 Sep 2018 |
| Building plan approvalFile: IOD Latter (1).pdf | 19 Sep 2018 |
| Building Plan Approval (IOD)File: IOD Latter (1).pdf | 19 Sep 2018 |
| Building Plan Approval (IOD)File: IOD Latter (1).pdf | 19 Sep 2018 |
| Layout approvalFile: LAYOUT PLAN 110518.pdf | 25 Jul 2018 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN 110518.pdf | 25 Jul 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC OF Rehab Bldg No 2 DTD 220618.pdf | 25 Jul 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 95 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep EL SIGNORA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near ADARSH NAGAR6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 257 registered projects within 2 km.
ROSWALT ZAIDEN
A S HIGHTECH LLP
Dream Signature
Prime Realtors
Sayba Noor
Star Raises
Gurukrupa Ekam
GURUKRUPA REALCON INFRABUILD LLP
The Westpark Phase-1
WESTPARK DEVELOPERS PRIVATE LIMITED
Kalpataru Hrushikesh
Kalpataru Townships Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: PARAS BUILDERS (1985)
PARAS BUILDERS (1985) has 1 registration on MahaRERA, including EL SIGNORA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that EL SIGNORA shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if EL SIGNORA is delayed beyond 28 Feb 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of EL SIGNORA?
The registered promoter entity is PARAS BUILDERS (1985), a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in EL SIGNORA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against EL SIGNORA?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for EL SIGNORA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at EL SIGNORA?
The professionals named in the filing: Architect: GRIHA RACHANA; Engineer: FAKHRI A HASAMWALA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in EL SIGNORA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback