ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / EKTA VICTORIA

Registered No litigation declared Residential / Group Housing project

EKTA VICTORIA

By EKTA HOUSING PRIVATE LIMITED

RG-MH-85609 · RERA PR1180002502359 · Last updated on MahaRERA portal: 19 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 8 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 30%
16 of 17Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 6 documents Report an error

EKTA VICTORIA is a Residential / Group Housing project by EKTA HOUSING PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as PR1180002502359 on 13 Feb 2026. Possession is promised by 31 Dec 2028. 1 of the 17 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameEKTA VICTORIA
  • TypeResidential / Group Housing
  • Location
    • St. Alexlous Road
    • Near Mac Craig
    • Pali Hill
    • Bandra
    • Andheri
    • Mumbai Suburban
    • 400050
  • Pincode400050
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR1180002502359
  • ReraGenie IDRG-MH-85609

Builder

  • NameEKTA HOUSING PRIVATE LIMITED
  • Entity typeCompany
  • CINU45200MH1990PTC058279
  • GSTIN27AAACE2460K1ZP
  • DirectorsVIVEK ASHOK MOHANANI, ASHOK GOBINDRAM MOHANANI
  • Other registrations8 more →
  • Completed5 of 9
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

this monthRegisteredFeb 2026PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on13 Feb 2026
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed6 files

Current status

6%1 of 17 units booked
10.3%Work done, per cost certificate

Figures as on 19 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
EKTA VICTORIANA141017017

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 30%.

EKTA VICTORIA: 3% average across the applicable activities

ActivityProgress
Excavation30%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNo0%
Landscaping & Tree PlantingNo0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNo0%
Energy managemcntNo0%
Fire protection and fire safety requirementsNo0%
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed33

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots33
Stilt / Ground18
Basement10
Podiums / Upper Parking Floor5

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area664 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on6 Feb 2026
LandownerVillageDistrict
VICTORIA CO OPERATIVE HOUSING SOCIETY LIMITEDBandraMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI1792.38
Proposed, not sanctioned1,792 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGRD FLR HALLMARK BUSINESS PLAZA SHOP NO 001 B SANT DYANESHWAR MARG KALANAGAR BANDRA E MUM 51 MAH
Estimated costRs 18.01 cr
Cost incurredRs 1.85 cr
Work done10.28%
BuildingWingEstimatedIncurred
EKTA VICTORIANARs 16.99 crRs 1.85 cr
-NARs 1.02 cr-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSameer Desai
EngineerSACHIN S KARAWADE
Chartered AccountantVIKAS MANGAL
PartnerRole in project
EKTA HOUSING PRIVATE LIMITED-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportNot on the file

    A lawyer's report on who owns the land and what is registered against it.

  2. Layout approvalNot on the file

    The planning authority's approval of how the plots and buildings sit on the land.

  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Feb 2026
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed6

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: SIGNED FORM 1 VICTORIA MARCH 2026 - Copy.pdf19 Apr 2026
Withdrawal Update Form 2File: SIGNED FORM 2 VICTORIA MARCH 2026.pdf19 Apr 2026
Withdrawal Update Form 3File: SIGNED FORM 3 VICTORIA 31_03_2026.pdf19 Apr 2026
Building plan approvalFile: Victoria Full IOD Plans 8_10_25 PDF.pdf2 Feb 2026
Declaration and undertaking (Annexure A)File: ANNEXURE A Declaration Cum Undertaking.pdf2 Feb 2026
Building plan approvalFile: Victoria Full IOD Cert 8-10-2025.pdf4 Jan 2026

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise4 delivered late
ProjectLocationFlatsStatusPromisedDelivered
EKTA GREENVILLE WING F,G,H,L,M,NSURVEY NO 231 AT PATHARDI NASHIK - 422 010192CompletedMar 2017Late, Jul 2017
EKTA CALIFORNIA WING A,B,C,D,ESurvey No 9 Hissa No 1 Part Undri Pune120CompletedMar 2015Late, Jul 2015
EKTA GREENVILLE ROW HOUSES AND VILLASSURVEY NO 231 AT PATHARDI NASHIK - 422 01020CompletedMay 2014Late, Jul 2017
EKTA GREENVILLE ROW HOUSE NO 29 AND 30SURVEY NO 231 AT PATHARDI NASHIK - 422 0102CompletedJul 2012Jul 2012
EKTA GREENVILLE WING A, B, C, D, E, KSURVEY NO 231 AT PATHARDI NASHIK - 422 010192CompletedApr 2012Late, Jul 2012

How this compares with Mumbai Suburban

6%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep EKTA VICTORIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Mac Craig, Pali Hill6,700+ in Mumbai Suburban

2 kmEKTA VICTORIACompleted 95Lapsed / revoked 47Other 120Dot size: filed unitsN

Filed coordinates, straight-line distance. 262 registered projects within 2 km.

Builder: EKTA HOUSING PRIVATE LIMITED

EKTA HOUSING PRIVATE LIMITED has 9 registrations on MahaRERA, including EKTA GREENVILLE PHASE 1 WING I AND J and EKTA GREENVILLE PHASE 2 WING O , P , Q AND R. Its filings disclose 5 earlier MahaRERA projects: declares 1 of 5 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if EKTA VICTORIA is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of EKTA VICTORIA?

The registered promoter entity is EKTA HOUSING PRIVATE LIMITED, a company as per the filing. Its CIN U45200MH1990PTC058279 and GSTIN 27AAACE2460K1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in EKTA VICTORIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for EKTA VICTORIA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at EKTA VICTORIA?

The professionals named in the filing: Architect: Sameer Desai; Engineer: SACHIN S KARAWADE; Chartered Accountant: VIKAS MANGAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EKTA VICTORIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EKTA VICTORIA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EKTA VICTORIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.