Home / Browse projects / Mumbai Suburban, Maharashtra / EKTA TRIPOLIS PHASE II

Registered Litigation declared Residential / Group Housing project

EKTA TRIPOLIS PHASE II

By EKTA EVERGLADE HOMES PRIVATE LIMITED

RG-MH-10465 · RERA P51800000731 · Last updated on MahaRERA portal: 11 Dec 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 5 cases
  • 18 complaints at MahaRERA
  • Completion date moved by 54 months
  • 4 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 54 months from the original
9 of 11Construction stages donefurthest along: Internal walls, 90%
45 of 227Units unsoldnot recorded sold or booked
18Complaints at MahaRERAon this registration
Jump to the 90 documents Report an error

EKTA TRIPOLIS PHASE II is a Residential / Group Housing project by EKTA EVERGLADE HOMES PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000731 on 23 Jul 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 54 months from the original filing. 182 of the 227 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete. 18 complaints are on record with the regulator.

At a glance

Project

  • NameEKTA TRIPOLIS PHASE II
  • TypeResidential / Group Housing
  • Location
    • Road no 8 & 2
    • Siddharth Nagar
    • Goregaon (West)
    • Borivali
    • Mumbai Suburban
    • 400104
  • Pincode400104
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800000731
  • ReraGenie IDRG-MH-10465

Builder

  • NameEKTA EVERGLADE HOMES PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorASHOK GOBINDRAM MOHANANI
  • DirectorVivek Ashok Mohanani
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredJul 2017First promiseJun 2022Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Jul 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2022)
  • Buildings1 building record
  • Documents filed90 files

Current status

80%182 of 227 units booked
81.2%Work done, per cost certificate

Figures as on 11 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING CNA434320324227

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

WING C: 95% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 11 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed13

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots13
Closed/Covered1
Open Space12

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,730 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on11 Sep 2024

Approvals and building plan

Sanctioning authorityMunicipal Corporation of Greater Mumbai
Permissible FSI25777.25
Proposed, not sanctioned20,297 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchUNIT 2, GROUND FLOOR, HALLMARK PLAZA BANDRA E MUMBAI 400 051
Estimated costRs 166.94 cr
Cost incurredRs 135.48 cr
Work done81.15%
BuildingWingEstimatedIncurred
WING CNARs 142.86 crRs 114.28 cr
-NARs 24.09 crRs 21.20 cr

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSameer Desai
ArchitectSamir Desai
ArchitectSPACE MODULERS
EngineerSACHIN S KARAWADE
EngineerAmit Parshuram Kamble
EngineerJW CONSULTANTS LLP
Chartered AccountantShivanandan N Katdare
Chartered AccountantVIKAS MANGAL
Chartered AccountantLaddha & Laddha
PartnerRole in project
EKTA EVERGLADE HOMES PRIVATE LIMITED-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009106Jun 2022 → Jun 2023

Reason as filed by the promoterDUE TO SCARCITY OF THE RESOURCES & ALSO SOME TECHNICAL REASONS

EXT51800017708Jun 2022 → Dec 2024

Reason as filed by the promoterReply attached herewith.

EA11092401793Jun 2022 → Dec 2025

Reason as filed by the promoterDue to disputes between MHADA and Guru Ashish

EA11122518629Jun 2022 → Dec 2026

Reason as filed by the promoterReply attached herewith.

Litigation declared5

CaseCourtStatus
175/2018Bombay High CourtPending
815/2019Bombay High CourtOngoing
815/2019BOMBAY HIGH COURTOngoing
815/2019BOMBAY HIGH COURTOngoing
815/2019BOMBAY HIGH COURTOngoing

Complaints filed with MahaRERA18

Case no.ComplainantRespondentFiled
CC006000000044008VISHRAM D. KUYESKAREKTA EVERGLADE HOMES PVT LTD05/04/2018
CC006000000396548SURAJ GHOGAREEKTA EVERGLADE HOMES PRIVATE LIMITED04/07/2023
CC006000000110706RAJENDRA WALIAEKTA TRIPOLIS20/09/2019
CC006000000192203SUNIL VASHDEV KHERAJANI & MEENA SUNIL KHERAJANIM/S EVERGLADE HOMES PVT. LTD.17/01/2020
CC006000000199169Darius MoosEkta Everglade Homes Pvt. Ltd.27/11/2021
CC006000000210515Mrs Kareena Shahani, Mr Sanjay Shahani & Mrs Poonam ShahaniEkta Everglade Homes Pvt Ltd28/03/2022
CC006000000210554Mr Amey Sudhakar Joshi & Mrs Disha Amey JoshiEkta Everglade Homes Pvt Ltd26/03/2022
CC006000000292324Vishal JaiswalEkta Everglade Homes Pvt. Ltd.17/08/2022
CC006000000292884Mr. Vidyut Chandrakant ChattyEkta Everglade Homes Pvt. Ltd.04/11/2022
CC006000000303233Devang Kishore ShahEkta Everglade Homes Private Limited04/11/2022
CC006000000580903Ekta Everglade Homes Private LimitedAmey Sudhakar Joshi and Anr26/06/2024
CC006000000590954Ekta Everglade Homes Private LimitedVishal Jaiswal and Anr30/06/2024
CC006000000591285RAJESH NARAINDAS PUNJABIEKTA EVERGLADE HOMES PRIVATE LIMITED24/07/2024
CC006000000591587Rajat HandaEkta Everglade Homes Private Limited20/08/2024
CC12500346Sachin Dilipkumar shahEKTA EVERGLADE HOMES PRIVATE LIMITED31/01/2025
CC12500744Surendra N KothariEKTA EVERGLADE HOMES PRIVATE LIMITED05/03/2025
CC12501301DEEPAK SURESHKUMAR GOYALEKTA EVERGLADE HOMES PRIVATE LIMITED19/04/2025
CC12503091KAMLESH SINGHEKTA EVERGLADE HOMES PRIVATE LIMITED03/09/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 26 May 2025

Documents filed90

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 90 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: signed TRIPOLIS PHASE II FORM 1 Sep 2025.pdf11 Dec 2025
Withdrawal Update Form 2File: Signed tripolis phase 2 form 2 Sep 2025.pdf11 Dec 2025
Withdrawal Update Form 3File: Signed_FORM 3_compressed Sep 2025.pdf11 Dec 2025
Form 2A (FY 2024-2025)File: FOMR 2A.pdf11 Dec 2025
Withdrawal Update Form 1File: signed TRIPOLIS PHASE II FORM 1 Sep 2025.pdf21 Oct 2025
Withdrawal Update Form 2File: Signed tripolis phase 2 form 2 Sep 2025.pdf21 Oct 2025
Withdrawal Update Form 3File: Signed_FORM 3_compressed Sep 2025.pdf21 Oct 2025
Form 5 (FY 2024-2025)File: FORM 5 EKTA TRIPOLIS PHASE II 31_03_25.pdf19 Sep 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: TRIPOLIS PHASE II ARCH CERT FORM 1 30-06-2025.pdf28 Jul 2025
Certificates of CA (Form 3)File: Signed Form 3 TP P II 30_06_25.pdf28 Jul 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 EKTA TRIPOLIS PHASE 2.pdf28 Jul 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD Tripolis Phase 2 30_06_25.pdf28 Jul 2025
Form 1File: TRIPOLIS PHASE II ARCH CERT FORM 1 30-06-2025.pdf19 Jul 2025
Form 2File: FORM 2 EKTA TRIPOLIS PHASE 2.pdf19 Jul 2025
Form 3File: Signed Form 3 TP P II 30_06_25.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD & UNSOLD Tripolis Phase 2 30_06_25.pdf19 Jul 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 13297_OCC_Signed TRIPOLIS PHASE II.pdf26 May 2025
Disclosure of sold/ booked inventoryFile: Ekta Tripolis Phase II Shop Sold Unsold Details as on 07_04_2025.pdf18 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW TRIPOLIS PHASE II ARCH CERT FORM 1 31_12_2024.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Ekta Tripolis Phase II Shop Sold Unsold Details as on 06_01_2025.pdf20 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FOORM 2 TRIPOLIS (1).pdf18 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW TRIPOLIS PHASE II ARCH CERT FORM 1 30-09-2024.pdf19 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW TRIPOLIS PHASE II Form 2 ENG CERT 30_09_24.pdf19 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ekta tripolis phase II.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: TP P II Sold Unsold Details as on 07_10_2024.pdf14 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW TRIPOLIS PHASE II ARCH CERT FORM 1 30-06-2024.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW TRIPOLIS PHASE II Form 2 ENG CERT 30_06_20244.pdf26 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: EW TRIPOLIS PHASE II Form 2 ENG CERT 30_06_20244.pdf26 Jul 2024
Certificates of CA (Form 3)File: JUNE 2024 FORM3 EKTA EVERGLADE TRIPOLIS PHASE II.pdf26 Jul 2024
Disclosure of sold/ booked inventoryFile: Ekta Tripolis Tower C Sold Unsold Details July 2024.pdf20 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW TRIPOLIS PHASE II ARCH CERT FORM 1 31-03-2024.pdf6 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW TRIPOLIS PHASE II Form 2 ENG CERT 31 march 2024.pdf6 May 2024
Certificates of CA (Form 3)File: SIGNED Form 3 EW TRIPOLIS P II 31-03-2024.pdf6 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: EW TRIPOLIS PHASE II FORM 2A QUALITY ASSURANCE CERT 31-3-2024.pdf3 May 2024
Disclosure of sold/ booked inventoryFile: Ekta Tripolis Phase II Sold Unsold Details April 2024.pdf16 Apr 2024
Disclosure of sold/ booked inventoryFile: Ekta Tripolis Phase II Sold Unsold Details April 2024 SHOP.pdf16 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW TRIPOLIS PHASE II ARCH CERT FORM 1 31-12-2023.pdf26 Feb 2024
Disclosure of sold/ booked inventoryFile: TRIPOLIS PHASE II.pdf19 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: tripolis phase ii.pdf15 Dec 2023
Certificates of CA (Form 3)File: SIGNED Form 3 TP P II 30092023.pdf7 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW TRIPOLIS PHASE II ARCH CERT FORM 1 30092023.pdf6 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW TRIPOLIS PHASE II FORM 2 ENGG CERT 06102023.pdf6 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Ekta Tripolis 29092023.pdf6 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Tripolis Phase II.pdf6 Sep 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Data Tower C.pdf16 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Tripolis Phase II.pdf6 Jul 2023
Certificates of CA (Form 3)File: Form 3 Tripolis Phase II SIGNED BY DIGITAL.pdf6 Jun 2023
Disclosure of sold/ booked inventoryFile: TP P II.pdf6 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Everglade.pdf15 Mar 2023
Details of encumbrances concerned to FinanceFile: Ekta Tripolis Phase II.pdf27 Feb 2023
Details of encumbrances concerned to LegalFile: Ekta Tripolis Phase II.pdf27 Feb 2023
Declaration about Commencement CertificateFile: EKTA TRIPOLIS PHASE II CC DECLARATION 20-02-2023.pdf27 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW TRIPOLIS PHASE II ARCH CERT FORM 1 20-2-2023.pdf27 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: EW TRIPOLIS PHASE II FORM 2A QUALITY ASSURANCE CERT 31-12-2020.pdf27 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: EW TRIPOLIS PHASE II FORM 2A QUALITY ASSURANCE CERT 31-12-2022.pdf27 Feb 2023
CERSAI detailsFile: Everglade.pdf20 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Everglade.pdf20 Feb 2023
Proforma of Agreement for saleFile: Ekta Tripolis Phase II - Wing C.pdf15 Feb 2023
Disclosure of sold/ booked inventoryFile: tripolis Phase II.pdf6 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Ekta Everglde_Tripolis_Phase-2_Form-5.pdf26 Oct 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold Data Tower C.pdf9 Oct 2022
Disclosure of sold/ booked inventoryFile: TRIPOLIS PHASE II.pdf6 Jul 2022
Disclosure of sold/ booked inventoryFile: TRIPOLIS PHASE II.pdf5 Apr 2022
Disclosure of sold/ booked inventoryFile: TRIPOLIS PHASE II.pdf6 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: TRIPOOLIS PHASE II.pdf30 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QA 20-21 Ekta Tripolis Phase 2.pdf7 Oct 2021
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Tower C Ekta Tripolis.pdf6 Oct 2021
Disclosure of sold/ booked inventoryFile: Sold-Unsold Data Tower C with Registration date.pdf25 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Ekta Tripolis Phase II.pdf10 Feb 2021
OtherFile: PHASE II TRIPOLIS.pdf29 Jan 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Tripolis Phase II.pdf16 Nov 2019
Certificates of CA (Form 5)File: Tripolis Phase II.pdf11 Oct 2019
Certificates of CA (Form 5)File: Tripolis Phase II 04102018132142.pdf9 Oct 2018
Declaration in FORM BFile: Form B Declaration Phase II.pdf20 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH-CERT-TRIPOLIS-PHASE II-20-7-17.pdf20 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate Triopolis Phase 2.pdf20 Jul 2017
Certificates of CA (Form 3)File: CA Certificate 19-07-2017.pdf20 Jul 2017
Proforma of Allotment letterFile: Allottment Letter and Agreement 20-07-2017.pdf20 Jul 2017
Copy of the legal title reportFile: Title Certificate Part I.pdf18 Jul 2017
OtherFile: Title Certificate Part I.pdf18 Jul 2017

How this compares with Mumbai Suburban

80%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 54 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep EKTA TRIPOLIS PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Siddharth Nagar, Goregaon (West)6,700+ in Mumbai Suburban

Builder: EKTA EVERGLADE HOMES PRIVATE LIMITED

EKTA EVERGLADE HOMES PRIVATE LIMITED has 2 registrations on MahaRERA, including EKTA TRIPOLIS PHASE I and EKTA TRIPOLIS PHASE II. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if EKTA TRIPOLIS PHASE II is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of EKTA TRIPOLIS PHASE II?

The registered promoter entity is EKTA EVERGLADE HOMES PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in EKTA TRIPOLIS PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against EKTA TRIPOLIS PHASE II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for EKTA TRIPOLIS PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at EKTA TRIPOLIS PHASE II?

The professionals named in the filing: Architect: Sameer Desai; Architect: Samir Desai; Architect: SPACE MODULERS; Engineer: SACHIN S KARAWADE; Engineer: Amit Parshuram Kamble; Engineer: JW CONSULTANTS LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EKTA TRIPOLIS PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EKTA TRIPOLIS PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EKTA TRIPOLIS PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.