Home / Browse projects / Mumbai Suburban, Maharashtra / EKTA TRIPOLIS PHASE I

Completed No litigation declared Residential / Group Housing project

EKTA TRIPOLIS PHASE I

By EKTA EVERGLADE HOMES PRIVATE LIMITED

RG-MH-10374 · RERA P51800000947 · Last updated on MahaRERA portal: 30 Jun 2025

Source: official MahaRERA filing

Red flags

  • 65 complaints at MahaRERA
  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
12 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 97%
65Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

EKTA TRIPOLIS PHASE I is a Residential / Group Housing project by EKTA EVERGLADE HOMES PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000947 on 25 Jul 2017. The registration is recorded completed; possession was promised by 30 Dec 2023. The completion date has moved by 30 months from the original filing. 65 complaints are on record with the regulator.

At a glance

Project

  • NameEKTA TRIPOLIS PHASE I
  • TypeResidential / Group Housing
  • Location
    • Road no 8 & 2
    • Siddharth Nagar
    • Borivali
    • Mumbai Suburban
    • 400104
  • Pincode400104
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800000947
  • ReraGenie IDRG-MH-10374

Builder

  • NameEKTA EVERGLADE HOMES PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorASHOK GOBINDRAM MOHANANI
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredJul 2017First promiseJun 2021Revised toDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on25 Jul 2017
  • Promised completion30 Dec 2023
  • Revised completionRevised to 30 Dec 2023 (originally 30 Jun 2021)
  • Buildings2 building records
  • Documents filed54 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA430000
WING BNA430000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 30 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 97%.

WING A89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%
Sanitary Fittings within the flats / premises12%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks97%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
WING B88%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises93%
Sanitary Fittings within the flats / premises12%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks96%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities38

As on 30 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes60%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes95%
Solid Waste Management And DisposalYes95%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes50%
Open ParkingNoNot applicable
MULTIPURPOSE COURTYes0%
OPEN JACUZZIYes75%
E Charging Car PointYes0%
SWINGING CORNERYes0%
Mini Open AmphitheatreYes0%
MEDITATION & TRANQUILITY GARDENYes75%
LAWNYes75%
JOGGING and WALKING TRACKYes0%
CLUB HOUSEYes0%
CHILDREN`S PLAY AREA WITH PLAYING EQUIPMENTYes50%
TRELLIS ON PERGOLAS ABOVE DECKYes100%
SWIMMING POOL of size 25m x 9mYes75%
SQUASH COURT of size 9m x 6m will be in Club HouseYes75%
SNOOKER TABLE PART OF THE CLUB HOUSEYes0%
SHADE SHELTERYes0%
SENIOR CITIZEN GARDENYes0%
OUTDOOR CHESS BOARDYes0%
SEATING AREAS FORMING PART OF THE LANDSCAPEYes100%
POOL DECK is provided along the swimming poolYes0%
GYMNASIUM WITH FITNESS EQUIPMENT TO BE PART OF THE CLUB HOUSEYes50%
INDOOR GAMES ZONE with games like table tennis,chess & it will be a part of CLUB HOUSE.Yes75%
WATER FEATURE PART OF LANDSCAPEYes0%
KIDS POOL of 20 feet x 12 feetYes75%

Parking filed36

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots36
Closed/Covered1
Open Space35
BuildingClosed/CoveredOpen SpaceTotal
WING A01212
WING B12324

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,822 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI40356.34
Proposed, not sanctioned40,356 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchUNIT 2, GROUND FLOOR, HALLMARK PLAZA BANDRA E MUMBAI 400 051

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectREZA KABUL ARCHITECTS
ArchitectSPACE MODULERS
EngineerJW CONSULTANTS LLP
PartnerRole in project
EKTA EVERGLADE HOMES PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009105Jun 2021 → Jun 2022

Reason as filed by the promoterDue to scarcity of the resources & also some technical reasons

EXT51800013078Jun 2021 → Dec 2023

Reason as filed by the promoterThe existing possession date as per RERA is going to expire on 29.12.2022, The Project comprising wing A and B is ready since two years and we are OC Compliant since long, It is only delayed on account of the ongoing legal issues in between MAHADA and HDIL.

Litigation declared4

CaseCourtStatus
536/2017City civil court DindoshiDisposed off
175/2018Bombay High CourtPending
513/2023Bombay High CourtPending
513/2023Bombay High CourtPending

Complaints filed with MahaRERA65

Case no.ComplainantRespondentFiled
CC006000000192977Wayne Jordan SaldanhaEkta Everglade Homes Pvt. Ltd.19/03/2020
CC006000000012703Suresh V TahilramaniEkta Everglade Pvt Ltd01/01/2018
CC006000000089941Suresh TahilramaniEkta Everglade Homes Pvt Ltd16/12/2020
CC006000000591364Suresh RamaniEkta Everglade Homes Pvt Ltd03/08/2024
CC006000000054656Vidur SarinEKTA EVERGLADE HOMES PVT.LTD28/05/2018
CC006000000057923VIDUR SARINEKTA EVERGLADE HOMES PVT LTD01/02/2019
CC006000000151216Chander Sen KhanchandaniEkta Everglade Homes Pvt. Ltd.10/10/2019
CC006000000056721Digant Nandlal ThakkarM/s Ekta Everglades Home Pvt Ltd18/12/2019
CC006000000194343BHASKAR AND ARPITA CHAKRABORTYEKTA EVERGLADE HOMES PVT LTD08/10/2020
CC006000000090164DEEPA JETHO BHATIAEKTA EVERGLADE HOMES Pvt Ltd16/07/2019
CC006000000193895TANU BHARTIASHOK MOHANANI02/09/2020
CC006000000161434Mohammad Naimur Rehman & Tarrannum Mohammad Naimur RehmanEkta Everglade Homes Pvt Ltd05/11/2019
CC0060000001614551 Anand H Dubey, 2 Manisha Dubey, 3 Harish D Dubey, 4 Shahsi H DubeyEkta Everglade Homes Pvt Ltd06/11/2019
CC006000000171529Bhavesh ShahEkta Everglade Homes Limited15/11/2019
CC006000000171797Ashwin GedamEkta Everglade Homes Private Limited16/12/2019
CC006000000192835Amit MisraEkta Everglade Homes Pvt Ltd04/03/2020
CC006000000194799Harkishan Mohanlal Malkan and Chetan Harkishan MalkanEkta Everglade Homes Private Limited05/11/2020
CC006000000195024Yogendrasinh Yashvantsinh Vansia HUFEkta Everglade Homes Pvt Ltd25/11/2020
CC006000000195507Anjan Kumar and Jaya KumarEkta Everglade Homes Pvt Ltd04/01/2021
CC006000000195508N D Krishnaprakash Iyer and Vidya IyerEkta Everglade Homes Pvt Ltd04/01/2021
CC006000000198875Mr Pawan Koyal and Mrs Sangita KoyalEkta Everglade Homes Pvt Ltd30/10/2021
CC006000000199156Mrs Kiran Agarwal and Mr Rajeev KumarEkta Everglade Homes Pvt Ltd26/11/2021
CC006000000209428EKTA EVERGLADE HOMES PRIVATE LIMITEDRenuka Satish Tripathi15/12/2021
CC006000000209554KAMLESH YADAVekta everglade homes pvt ltd26/12/2021
CC006000000209758Mr Sonik Nirmal Puri & Mrs Veronica Sonik PuriEkta Everglade Homes Private Limited20/01/2022
CC006000000209940Mr Pradeep Gopal Krishnan & Mrs Vilasini SubramaniamEkta Everglade Homes Private Limited09/02/2022
CC006000000210483Mr Pankaj Verma & Mrs Seema VermaEkta Everglade Homes Pvt Ltd22/03/2022
CC006000000210520Mrs Jyoti Sunil Chaudhari & Mr Sunil Anandrao ChaudhariEkta Everglade Homes Pvt Ltd25/03/2022
CC006000000220625Jaikishan Ganesh KacherlaEkta Everglade Homes Private Limited01/04/2022
CC006000000220673Reju Gopal NairEkta Everglade Homes Private Limited04/04/2022
CC006000000220741Sanket ShahEkta Everglade Home Private Limited09/04/2022
CC006000000220734Mr Sandeep Kaura And Mrs Beenu Malhotra KauraEkta Everglade Homes Private Limited08/04/2022
CC006000000220740Mrs Sarita Sudarshan Jain And Mr Sudarshan Vir JainEkta Everglade Homes Pvt Ltd12/04/2022
CC006000000220750Mr Rajan Chhabria And Mrs Sanya ChhabriaEkta Everglade Homes Pvt Ltd11/04/2022
CC006000000251372Sameer GargEKTA EVERGLADE HOMES PRIVATE LIMITED07/06/2022
CC006000000251435Haresh A. KhilnaniM/s Ekta Everglade Homes Pvt. Ltd.15/06/2022
CC006000000251552SS Joseph Subbu ReddiEkta Ebverglade Homes Pvt Ltd23/06/2022
CC006000000282207Chandravadan M MistryEkta Everglade Homes Private Limited05/08/2022
CC006000000292768Lucas RodriguesEkta Everglade Homes Pvt. Ltd.21/09/2022
CC006000000292769Lucas RodriguesEkta Everglade Homes Pvt. Ltd.21/09/2022
CC006000000303212Chandrakant Annaji PatilEkta Everglade Homes Pvt Ltd02/11/2022
CC006000000303214Sheetal Chandrakant PatilEkta Everglade Homes Pvt Ltd02/11/2022
CC006000000000113KARISHMA PATELEkta Everglade Homes Pvt. Ltd10/08/2017
CC006000000303420H Venkatachalam IyerEkta Everglade Homes Private Limited12/12/2022
CC006000000303547Ananthakrishnan VishwanathanEkta Everglade Homes Private Limited02/12/2022
CC006000000303728Nitu Sanjeev SethM/S Ekta Everglade Homes Pvt Ltd through its promoter29/12/2022
CC006000000303743Amit Kumar Ramesh Kumar JalanEkta Everglade Homes Pvt Ltd21/12/2022
CC006000000333947Nutan SinhaEkta Everglade Homes Pvt. Ltd14/01/2023
CC006000000374767Seema Narain ShroffEkta Everglade Homes Private Limited14/03/2023
CC006000000374786Abhishek ShawEkta Everglade Homes Pvt Ltd.15/03/2023
CC006000000375402VINIT PADIAEkta Everglade Homes Private Limited26/04/2023
CC006000000375259Prashant Dwarka SainaniEkta Everglade Homes Pvt Ltd14/04/2023
CC006000000395527Rajendra WaliaM/s Ekta Everglade Homes Pvt Ltd04/05/2023
CC006000000395738Jigna Bhavesh ShahEKTA EVERGLADE HOMES PRIVATE LIMITED16/05/2023
CC006000000397991Vivek Ashok AgarwalEkta Everglade Homes Private Limited24/01/2024
CC006000000408111Prakas D'cunhaEkta Everglade Homes Pvt. Ltd10/11/2023
CC006000000408241Prakas D'cunhaEkta Everglade Homes Pvt. Ltd.25/11/2023
CC006000000408237Vijai PratapEkta Everglade Homes Pvt. Ltd.07/12/2023
CC006000000408588RUKHSANA SHAMIM SHAIKHEkta Everglades Home Pvt Ltd21/12/2023
CC006000000408655Mukesh ChamdiaEkta Everglade Homes Private Limited24/01/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 10 Apr 2023

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate.pdf30 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: TP P I 22-23 FORM 2A.pdf30 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: TP P I 23-24 FORM 2A.pdf30 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ekta tripolis phase I.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: Tripolis Phase I.pdf19 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Tripolis Phase I.pdf6 Jul 2023
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 TRIPOLIS I.pdf18 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC TRIPOLIS PHASE I.pdf10 Apr 2023
Disclosure of sold/ booked inventoryFile: TP P I.pdf6 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW TRIPOLIS PHASE I Form 2 ENGINEER CERTIFICATE 31-12-22.pdf15 Feb 2023
Certificates of CA (Form 3)File: final FORM 3 TRIPOLIS PHASE I.pdf15 Feb 2023
OtherFile: Tripolis Phase I.pdf11 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCH TRIPOLIS PHASE I 31-01-2023.pdf8 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW TRIPOLIS PHASE I Form 2 ENGINEER CERTIFICATE 31-12-22.pdf8 Feb 2023
Proforma of Agreement for saleFile: Tripolis Ph I.pdf7 Feb 2023
Details of encumbrances concerned to FinanceFile: Tripolis Phase I.pdf4 Feb 2023
Details of encumbrances concerned to LegalFile: Tripolis Phase I.pdf4 Feb 2023
Declaration about Commencement CertificateFile: EKTA TRIPOLIS PHASE I CC DECLARATION 31-01-2023.pdf4 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A QUALITY ASSURANCE TRIPOLIS PHASE I 1-01-2022.pdf4 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A QUALITY ASSURANCE TRIPOLIS PHASE I 1-01-2022.pdf4 Feb 2023
CERSAI detailsFile: Everglade.pdf4 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Everglade.pdf4 Feb 2023
Disclosure of sold/ booked inventoryFile: tripolis phase I.pdf6 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Ekta Everglde_Tripolis_Phase-1_Form-5.pdf26 Oct 2022
Disclosure of sold/ booked inventoryFile: TRIPOLIS PHASE I.pdf9 Oct 2022
Disclosure of sold/ booked inventoryFile: TRIPOLIS PHASE I.pdf6 Jul 2022
Disclosure of sold/ booked inventoryFile: TRIPOLIS PHASE I.pdf5 Apr 2022
Disclosure of sold/ booked inventoryFile: tripolis Phase I.pdf5 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: TRIPOLIS PHASE I.pdf30 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QA 20-21 Ekta Tripolis Phase 1.pdf7 Oct 2021
Disclosure of sold/ booked inventoryFile: Sold-Unsold Data Tower A with Registration Date.pdf25 Aug 2021
Disclosure of sold/ booked inventoryFile: Sold-Unsold Data Tower B with Registration Date.pdf25 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Ekta Tripolis Phase I.pdf10 Feb 2021
OtherFile: PHASE I TRIPOLIS.pdf29 Jan 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Tripolis Phase I_1.pdf16 Nov 2019
Certificates of CA (Form 5)File: Tripolis Phase I_1.pdf11 Oct 2019
Certificates of CA (Form 5)File: Tripolis Phase I 04102018110901.pdf9 Oct 2018
Declaration in FORM BFile: Form B Declaration Phase I.pdf20 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH-CERT TRIPOLIS PHASE I A_B 20-7-17.pdf20 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate Triopolis Phase 1.pdf20 Jul 2017
Certificates of CA (Form 3)File: CA Certificate 19-07-2017.pdf20 Jul 2017
Proforma of Allotment letterFile: Allottment Letter and Agreement 20-07-2017.pdf20 Jul 2017
Copy of the legal title reportFile: Title Certificate Part I.pdf18 Jul 2017
OtherFile: Title Certificate Part I.pdf18 Jul 2017
OtherFile: Title Certificate Part II.pdf18 Jul 2017
OtherFile: Title Certificate Part III.pdf18 Jul 2017
OtherFile: Title Certificate Part IV.pdf18 Jul 2017
Layout approvalFile: LAYOUT.pdf15 Jul 2017
Building plan approvalFile: IOD.pdf15 Jul 2017
Details of encumbrancesFile: Letter for encumbrance and IOM Index II.pdf15 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf15 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf15 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC Wing A and B.pdf15 Jul 2017
PAN CardFile: Pan Card.pdf13 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 30 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep EKTA TRIPOLIS PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Siddharth Nagar6,700+ in Mumbai Suburban

2 kmEKTA TRIPOLIS PHASE ICompleted 142Lapsed / revoked 82Abeyance 1Other 149Dot size: filed unitsN

Filed coordinates, straight-line distance. 374 registered projects within 2 km.

Builder: EKTA EVERGLADE HOMES PRIVATE LIMITED

EKTA EVERGLADE HOMES PRIVATE LIMITED has 2 registrations on MahaRERA, including EKTA TRIPOLIS PHASE I and EKTA TRIPOLIS PHASE II. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if EKTA TRIPOLIS PHASE I is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of EKTA TRIPOLIS PHASE I?

The registered promoter entity is EKTA EVERGLADE HOMES PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in EKTA TRIPOLIS PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against EKTA TRIPOLIS PHASE I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for EKTA TRIPOLIS PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at EKTA TRIPOLIS PHASE I?

The professionals named in the filing: Architect: REZA KABUL ARCHITECTS; Architect: SPACE MODULERS; Engineer: JW CONSULTANTS LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EKTA TRIPOLIS PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EKTA TRIPOLIS PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EKTA TRIPOLIS PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.