Home / Browse projects / Mumbai Suburban, Maharashtra / EKTA SRA CHS

Registration lapsed Litigation declared Residential / Group Housing project

EKTA SRA CHS

By CLASSIC ENTERPRISES VAKOLA

RG-MH-25695 · RERA P51800004680 · Last updated on MahaRERA portal: 10 Sep 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 8 months past the filed date
  • Litigation declared, 4 cases
  • Completion date moved by 30 months
  • 3 extensions taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Feb 2026Possession promised8 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
47 of 70Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 224 documents Report an error

EKTA SRA CHS is a Residential / Group Housing project by CLASSIC ENTERPRISES VAKOLA in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800004680 on 9 Aug 2017. Possession was promised by 28 Feb 2026 and is now 8 months past that date. The completion date has moved by 30 months from the original filing. 23 of the 70 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameEKTA SRA CHS
  • TypeResidential / Group Housing
  • Location
    • MUMBAI
    • VAKOLA
    • Andheri
    • Mumbai Suburban
    • 400055
  • Pincode400055
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800004680
  • ReraGenie IDRG-MH-25695

Builder

  • NameCLASSIC ENTERPRISES VAKOLA
  • Entity typePartnership
  • PartnersCHANDRAKANT BHASKAR GORULE, KRISHNA BABAL KAUTHANKAR

Key dates

8 months past promisethis monthRegisteredAug 2017First promiseAug 2023Revised toFeb 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion28 Feb 2026
  • Revised completionRevised to 28 Feb 2026 (originally 1 Aug 2023)
  • Buildings1 building record
  • Documents filed224 files

Current status

33%23 of 70 units booked

Figures as on 10 Sep 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
EKTA CHSNA9961970

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

EKTA CHS: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 10 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
STACK PARKINGYes100%

Parking filed14

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots14
Closed/Covered11
Open Space3

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area605 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Jul 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI3834.36
Proposed, not sanctioned1,770 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch369, SUNRISE APARTMENT NEHRU ROAD VAKOLA, SANTACRUZ EAST MUMBAI 400055

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVISION ARCH
ArchitectMEENAL SACHIN GANDRE
EngineerSwapneel Consultants
EngineerPRASHANT MADHAV SANE
Chartered AccountantPRITAM NEVREKAR
Chartered AccountantS.D.Satam & Co.
Chartered AccountantSANTOSH DHONDU SATAM
PartnerRole in project
CLASSIC ENTERPRISES VAKOLA-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800017236Aug 2023 → Jul 2024

Reason as filed by the promoterCOURT CASE IN HIGH COURT MUMBAI regarding ownership of the property and existing commercial tenants (shops) in road setback are not ready to shift in the permanent rehab commercial premises (SHOPS) after obtaining part occupation of the Ground Floor of the building.

EXT51800024646Aug 2023 → Jun 2025

Reason as filed by the promoter1) Writ petition No. 10551 of 2018 verses Shri Dattaram Mahadev Mahadik (Petitioner) and Slum Rehabilitation Authority (Respondent) petitioner was instructed to withdraw the petition and file and appeal before AGR on 21st September 2018. 2) Before the Apex Grievance Redressal Committee Government of Maharashtra Application (L) No. 205 of 2018 and Application (L) No. 206 of 2018 Applicant. 3) Order of Dy. Collector SRA vide No. OW/2019/11427 जा. क्र. झोपुप्रा / अजि / मुद्रा / कार्या - 09/2019 dated 6th March 2018 4) Lock down period 1 year work effected 5) Now extension for project is being del

EA17092502618Aug 2023 → Feb 2026

Reason as filed by the promoter1) Writ petition No. 10551 of 2018 verses Shri Dattaram Mahadev Mahadik (Petitioner) and Slum Rehabilitation Authority (Respondent) petitioner was instructed to withdraw the petition and file and appeal before AGR on 21st September 2018. 2) Before the Apex Grievance Redressal Committee Government of Maharashtra Application (L) No. 205 of 2018 and Application (L) No. 206 of 2018 Applicant. 3) Order of Dy. Collector SRA vide No. OW/2019/11427 जा. क्र. झोपुप्रा / अजि / मुद्रा / कार्या - 09/2019 dated 6th March 2018 4) Lock down period 1 year work effected 5) Now extension for project is being del

Litigation declared4

CaseCourtStatus
2616/2450/ 04/J-3/2016REVENUE DEPARTMENTORDER ISSUED
1631 OF 2023/2023ADDITIONAL COLLECTOR ENC REM WESTER SUBURBAN MUMBAI COMPETENT AUTHORITY APPELLATE AUTHORITYPENDING
10532 OF 2018/2018HIGH COURT OF JUDICATURE AT BOMBAYClosed
10532 OF 2018/2018HIGH COURT OF JUDICATURE AT BOMBAYClosed

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 Jan 2023

Documents filed224

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 224 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1 for 2024-2025.pdf10 Sep 2025
Form 2File: FORM 2 FOR 2024-2025.pdf10 Sep 2025
Form 3File: Form 3 for 31 march 2025.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY ( BUILDING WING WISE) AS ON 31 MARCH 2025.pdf10 Sep 2025
Form 1File: FORM 1 for 2024-2025.pdf10 Sep 2025
Form 2File: FORM 2 FOR 2024-2025.pdf10 Sep 2025
Form 3File: Form 3 for 31 march 2025.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY ( BUILDING WING WISE) AS ON 31 MARCH 2025.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY ( BUILDING WING WISE) AS ON 31 MARCH 2025.pdf10 Sep 2025
Form 1File: FORM 1 for 2024-2025.pdf10 Sep 2025
Form 2File: FORM 2 FOR 2024-2025.pdf10 Sep 2025
Form 3File: Form 3 for 31 march 2025.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY ( BUILDING WING WISE) AS ON 31 MARCH 2025.pdf10 Sep 2025
Form 1File: FORM 1 for 2024-2025.pdf10 Sep 2025
Form 2File: FORM 2 FOR 2024-2025.pdf10 Sep 2025
Form 3File: Form 3 for 31 march 2025.pdf10 Sep 2025
Form 1File: 2017-2018.pdf10 Sep 2025
Form 2File: 2017-2018.pdf10 Sep 2025
Form 3File: 2017-2018.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: 2017-2018.pdf10 Sep 2025
Form 1File: 2017-2018.pdf10 Sep 2025
Form 2File: 2017-2018.pdf10 Sep 2025
Form 3File: 2017-2018.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: 2017-2018.pdf10 Sep 2025
Form 1File: 2017-2018.pdf10 Sep 2025
Form 2File: 2017-2018.pdf10 Sep 2025
Form 3File: 2017-2018.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: 2017-2018.pdf10 Sep 2025
Form 1File: FORM 1 for 2018-2019.pdf10 Sep 2025
Form 2File: FORM 2 FOR 2018-2019.pdf10 Sep 2025
Form 3File: Form 3 RERA by SD SATAM 2018-2019.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: 2017-2018.pdf10 Sep 2025
Form 3File: Form 3 RERA by SD SATAM 2018-2019.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: 2017-2018.pdf10 Sep 2025
Form 2File: FORM 2 FOR 2018-2019.pdf10 Sep 2025
Form 1File: FORM 1 for 2018-2019.pdf10 Sep 2025
Form 1File: FORM 1 for 2018-2019.pdf10 Sep 2025
Form 2File: FORM 2 FOR 2018-2019.pdf10 Sep 2025
Form 3File: Form 3 RERA by SD SATAM 2018-2019.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: 2017-2018.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: 2017-2018.pdf10 Sep 2025
Form 3File: Form 3 RERA by SD SATAM 2018-2019.pdf10 Sep 2025
Form 2File: FORM 2 FOR 2018-2019.pdf10 Sep 2025
Form 1File: FORM 1 for 2018-2019.pdf10 Sep 2025
Form 1File: FORM 1 for 2019-2020.pdf10 Sep 2025
Form 2File: FORM 2 FOR 2024-2025.pdf10 Sep 2025
Form 3File: Form 3 RERA by SD SATAM 2019-2020.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY ( BUILDING WING WISE) AS ON 16 JAN 2023.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY ( BUILDING WING WISE) AS ON 16 JAN 2023.pdf10 Sep 2025
Form 1File: FORM 1 for 2019-2020.pdf10 Sep 2025
Form 2File: FORM 2 FOR 2018-2019.pdf10 Sep 2025
Form 3File: Form 3 RERA by SD SATAM 2019-2020.pdf10 Sep 2025
Form 1File: FORM 1 for 2019-2020.pdf10 Sep 2025
Form 2File: FORM 2 FOR 2018-2019.pdf10 Sep 2025
Form 3File: Form 3 RERA by SD SATAM 2019-2020.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY ( BUILDING WING WISE) AS ON 16 JAN 2023.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY ( BUILDING WING WISE) AS ON 16 JAN 2023.pdf10 Sep 2025
Form 1File: FORM 1 for 2019-2020.pdf10 Sep 2025
Form 2File: FORM 2 FOR 2018-2019.pdf10 Sep 2025
Form 3File: Form 3 RERA by SD SATAM 2019-2020.pdf10 Sep 2025
Form 1File: FORM 1 for 2019-2020.pdf10 Sep 2025
Form 2File: FORM 2 FOR 2018-2019.pdf10 Sep 2025
Form 3File: Form 3 RERA by SD SATAM 2020-2021.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY ( BUILDING WING WISE) AS ON 16 JAN 2023.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY ( BUILDING WING WISE) AS ON 16 JAN 2023.pdf10 Sep 2025
Form 1File: FORM 1 for 2019-2020.pdf10 Sep 2025
Form 2File: FORM 2 FOR 2018-2019.pdf10 Sep 2025
Form 3File: Form 3 RERA by SD SATAM 2020-2021.pdf10 Sep 2025
Form 1File: FORM 1 for 2019-2020.pdf10 Sep 2025
Form 2File: FORM 2 FOR 2018-2019.pdf10 Sep 2025
Form 3File: Form 3 RERA by SD SATAM 2020-2021.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY ( BUILDING WING WISE) AS ON 16 JAN 2023.pdf10 Sep 2025
Form 1File: FORM 1 for 2019-2020.pdf10 Sep 2025
Form 2File: FORM 2 FOR 2018-2019.pdf10 Sep 2025
Form 3File: Form 3 RERA by SD SATAM 2019-2020.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY ( BUILDING WING WISE) AS ON 16 JAN 2023.pdf10 Sep 2025
Form 1File: FORM 1 for 2020-2021.pdf10 Sep 2025
Form 2File: FORM 2 FOR 2018-2019.pdf10 Sep 2025
Form 3File: Form 3 RERA by SD SATAM 2020-2021.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY ( BUILDING WING WISE) AS ON 16 JAN 2023.pdf10 Sep 2025

How this compares with Mumbai Suburban

33%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 30 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep EKTA SRA CHS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VAKOLA6,700+ in Mumbai Suburban

2 kmEKTA SRA CHSCompleted 63Lapsed / revoked 50Other 94Dot size: filed unitsN

Filed coordinates, straight-line distance. 207 registered projects within 2 km.

Builder: CLASSIC ENTERPRISES VAKOLA

CLASSIC ENTERPRISES VAKOLA has 1 registration on MahaRERA, including EKTA SRA CHS. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that EKTA SRA CHS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if EKTA SRA CHS is delayed beyond 28 Feb 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of EKTA SRA CHS?

The registered promoter entity is CLASSIC ENTERPRISES VAKOLA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in EKTA SRA CHS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for EKTA SRA CHS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at EKTA SRA CHS?

The professionals named in the filing: Architect: VISION ARCH; Architect: MEENAL SACHIN GANDRE; Engineer: Swapneel Consultants; Engineer: PRASHANT MADHAV SANE; Chartered Accountant: PRITAM NEVREKAR; Chartered Accountant: S.D.Satam & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EKTA SRA CHS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EKTA SRA CHS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EKTA SRA CHS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.