EKA VALLY
RG-MH-35383 · RERA P52100017628 · Last updated on MahaRERA portal: 17 Dec 2024
Source: official MahaRERA filing
Red flags
- Completion date moved by 28 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
EKA VALLY is a Residential / Group Housing project by SAI NANDAN BUILDCON in Pune, Maharashtra, registered with MahaRERA as P52100017628 on 29 Aug 2018. The registration is recorded completed; possession was promised by 10 Dec 2024. The completion date has moved by 28 months from the original filing.
At a glance
Project
- NameEKA VALLY
- TypeResidential / Group Housing
- Location
- KARLA
- Mawal
- Pune
- 410405
- Pincode410405
- RERA no.P52100017628
- ReraGenie IDRG-MH-35383
Builder
- NameSAI NANDAN BUILDCON
- Entity typePartnership
- PartnerHERALD FRANCISIS ALBUKARK
- Other registrations1 more →
- Completed2 of 2
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on29 Aug 2018
- Promised completion10 Dec 2024
- Revised completionRevised to 10 Dec 2024 (originally 28 Aug 2022)
- Buildings1 building record
- Documents filed41 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| EKA VALLY - A BUILDING | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 17 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
EKA VALLY - A BUILDING: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities16
As on 17 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| COMPOUND WALL | Yes | 100% |
Parking filed4
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MR BABASAHEB DHAVALE |
| Partner | Role in project |
|---|---|
| SAI NANDAN BUILDCON | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterdue to covid 19 we were not able to construct anymore because of labour contractors and poor market conditions we were unable to complete the project within the due time.
Reason as filed by the promoter1. Our project EKA VALLY bearing Reg. No. P52100017628 is getting delayed due to an non availability of electricity and COVID-19 disruptions. 2. We are currently in the position of applying for completion certificate subject to pending completion work, from our respective authority (PMRDA), but we were facing COVID-19 disruptions and hurdles for 2 years, also there was non availability of electricity from PMRDA in our sector (which has been currently restored), moreover there was administrative delay in getting the NOC from the respective authorities. 3. Due to all these factors we are facing
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Aug 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Aug 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Aug 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Aug 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 6 Nov 2024
Documents filed41
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf | 17 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Sainandan Builcon.pdf | 17 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 3 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf | 3 Dec 2024 |
| Certificates of CA (Form 3)File: FORM 3 Chartered Accountant Certificate eka vally with UDIN.pdf | 3 Dec 2024 |
| Declaration in FORM BFile: Form B_compressed.pdf | 2 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 2 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf | 2 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 2 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf | 27 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: A Wing Completion certificate .pdf | 6 Nov 2024 |
| PAN CardFile: PAN Sai Nandan Buildcon.pdf | 13 May 2024 |
| Details of encumbrances concerned to FinanceFile: Encumburancr legal.pdf | 13 May 2024 |
| Details of encumbrances concerned to LegalFile: Encumburancr legal.pdf | 13 May 2024 |
| CERSAI detailsFile: CERSAI.pdf | 13 May 2024 |
| Disclosure of sold/ booked inventoryFile: Sold unsold Ekka Vally.pdf | 13 May 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration.pdf | 13 May 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation Allotment.pdf | 13 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q1 Eka Vally.pdf | 10 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q2 Eka Vally.pdf | 10 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q3 Eka Vally.pdf | 10 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Ekka Vally FY 2022-23.pdf | 10 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2021.pdf | 16 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 2022.pdf | 16 Feb 2023 |
| Declaration about Commencement CertificateFile: declaration.pdf | 6 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: engineer pratik.pdf | 6 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: sold unsold.pdf | 6 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Rera Certificate- Sai Nandan Buildcom _compressed.pdf | 4 Dec 2020 |
| Layout approvalFile: Plan 1.pdf | 21 Aug 2018 |
| Details of encumbrancesFile: No Encumbrance letter final.pdf | 21 Aug 2018 |
| Copy of Layout Approval (in case of layout)File: Plan 1.pdf | 21 Aug 2018 |
| Declaration in FORM BFile: Form B.pdf | 21 Aug 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 21 Aug 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Site Engineer Cert.pdf | 21 Aug 2018 |
| Certificates of CA (Form 3)File: CA certificate.pdf | 21 Aug 2018 |
| Proforma of Allotment letterFile: Draft Agreement_RERA.pdf | 21 Aug 2018 |
| Proforma of Allotment letterFile: allotment letter Final1.pdf | 21 Aug 2018 |
| Building plan approvalFile: Plan 2.pdf | 16 Aug 2018 |
| Copy of the legal title reportFile: Legal Title Search Report.pdf | 16 Aug 2018 |
| Building Plan Approval (IOD)File: Plan 2.pdf | 16 Aug 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Commen Cement.pdf | 16 Aug 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 41 filed documents as one ZIP, foldered, with a manifest
Keep EKA VALLY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KARLA13,700+ in Pune
AQUAGEM
NAMRATA REALTY
VIGHNESH VIKAS
MADANLAL HANSRAJ GUPTA
Monte Karla
GOODBRICK REALTY PRIVATE LIMITED
GAGAN NULIFE PHASE 2
GAGAN LIFESPACE
Misty Winds 2
Planet I Developers
WEEKENDER COUNTRY SONGS
NAMRATA REALTY
Builder: SAI NANDAN BUILDCON
SAI NANDAN BUILDCON has 2 registrations on MahaRERA, including EKA VALLY and RAMANA EKA VALLEY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if EKA VALLY is delayed beyond 10 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of EKA VALLY?
The registered promoter entity is SAI NANDAN BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in EKA VALLY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for EKA VALLY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at EKA VALLY?
The professionals named in the filing: Architect: MR BABASAHEB DHAVALE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in EKA VALLY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback