Eastern River Residency Wing D
RG-MH-23119 · RERA P52100033276 · Last updated on MahaRERA portal: 22 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 5 cases
- 8 complaints at MahaRERA
- Completion date moved by 16 months
- 2 extensions taken
Clear
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Eastern River Residency Wing D is a Residential / Group Housing project by Kishor Shankar Garve in Pune, Maharashtra, registered with MahaRERA as P52100033276 on 15 Feb 2022. Possession is promised by 30 Apr 2027. The completion date has moved by 16 months from the original filing. 131 of the 140 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 8 complaints are on record with the regulator.
At a glance
Project
- NameEastern River Residency Wing D
- TypeResidential / Group Housing
- Location
- Kashid Park
- Pimpale Gurav
- Haveli
- Pune
- 411061
- Pincode411061
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100033276
- ReraGenie IDRG-MH-23119
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on15 Feb 2022
- Promised completion30 Apr 2027
- Revised completionRevised to 30 Apr 2027 (originally 31 Dec 2025)
- Buildings1 building record
- Documents filed112 files
Current status
Figures as on 22 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing D | NA | 27 | 24 | 140 | 0 | 140 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 22 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 99%.
Wing D: 68% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 87% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 92% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 99% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 18% |
Progress on shared amenities15
As on 22 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 30% |
| Water Supply | Yes | 30% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 30% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 30% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 30% |
| Electrical meter room, sub-station, receiving station | Yes | 30% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed140
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership14
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Uttam Laxman Kashid | Pimpale Gurav | Pune |
| Balu Laxman Kashid | Pimpale Gurav | Pune |
| Dinesh Uttam Kashid | Pimpale Gurav | Pune |
| Sudam Laxman Kashid | Pimpale Gurav | Pune |
| Nitin Balasaheb Kashid | Pimpale Gurav | Pune |
| Akshay Sudam Kashid | Pimpale Gurav | Pune |
| Deepak Balasaheb Kashid | Pimpale Gurav | Pune |
| Ganesh Popat Kashid | Pimpale Gurav | Pune |
| Manohar Popat Kashid | Pimpale Gurav | Pune |
| Rupesh Uttam Kashid | Pimpale Gurav | Pune |
| Popat Laxman Kashid | Pimpale Gurav | Pune |
| Ajit Bhaskar Kuber | Satara | Satara |
| Vineet Bhaskar Kuber | Pune (M Corp.) | Pune |
| Aakash Sudam Kashid | Pimpale Gurav | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Wing D | NA | Rs 65.00 cr | Rs 53.58 cr |
| - | NA | Rs 2.00 cr | - |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Milind Patil |
| Engineer | Prathamesh Sugate |
| Engineer | Venkangouda V Jadiyappagoudar |
| Engineer | VKG Associates |
| Chartered Accountant | Chaudhari Agarwal and Associates |
| Chartered Accountant | TEJAS SATHE & ASSOCIATES |
| Chartered Accountant | JSG & CO |
| Partner | Role in project |
|---|---|
| M/s Vinayak Enterprises | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterConstruction of the said project is 95% completed. We want to apply for extension u/s 6 of RERA Act. to complete remaining construction of the project till 31/12/2026.
Reason as filed by the promoterNA
Litigation declared5
| Case | Court | Status |
|---|---|---|
| 616/2020 | Civil Judge Senior Division Pune | Closed |
| 4880/2001 | Honble High Court of Bombay | Ongoing |
| 2655/2003 | High Court of Bombay | Ongoing |
| 2594/2004 | High Court of Bombay | Ongoing |
| 987/2008 | Civil Judge Senior Division | Ongoing |
Complaints filed with MahaRERA8
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12602293 | Atish Ambadas Bargaje | M/s Vinayak Enterprises | 18/04/2026 |
| CC12602294 | Tulshiram Kaluram Date | M/s Vinayak Enterprises | 18/04/2026 |
| CC12602310 | Jitendra Sandeep Joshi | M/s Vinayak Enterprises | 19/04/2026 |
| CC12602321 | Bhushan Kishor Harne | M/s Vinayak Enterprises | 20/04/2026 |
| CC12602383 | Tejashri Tanaji Bagwe | M/s Vinayak Enterprises | 22/04/2026 |
| CC12602636 | Sonali Jadhav | M/s Vinayak Enterprises | 07/05/2026 |
| CC12602726 | NIKHIL ARVIND CHORGI | M/s Vinayak Enterprises | 10/05/2026 |
| CC12602725 | VINAYAK KASHINATH SAKHARE | M/s Vinayak Enterprises | 10/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Feb 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Mar 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Mar 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 May 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Apr 2027
Documents filed112
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 112 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: FORM-2 ERR D 2025-2026.pdf | 22 Sep 2026 |
| Form 2A (FY 2026-2027)File: FORM-2 ERR D 2026-2027.pdf | 22 Sep 2026 |
| Form 5 (FY 2025-2026)File: ERR D FORM-5 2025 - 2026.pdf | 19 Sep 2026 |
| Withdrawal Update Form 1File: FORM 1 ERR WING D June 26.pdf | 3 Aug 2026 |
| Withdrawal Update Form 2File: FORM 2 ERR WING D Jun 26.pdf | 3 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 ERR Wing D June 26.pdf | 3 Aug 2026 |
| Withdrawal Update Form 1File: FORM 1 ERR WING D Mar 26.pdf | 27 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2 ERR WING D Mar 26.PDF | 27 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 ERR Wing D Mar 26.pdf | 27 Jul 2026 |
| Layout approvalFile: Layout.pdf | 17 Mar 2026 |
| Building plan approvalFile: Building Plan 17-48.pdf | 17 Mar 2026 |
| Building plan approvalFile: Building Plan 18-48.pdf | 17 Mar 2026 |
| Building plan approvalFile: Building Plan 25-48.pdf | 17 Mar 2026 |
| Building plan approvalFile: Building Plan 26-48.pdf | 17 Mar 2026 |
| Building plan approvalFile: Building Plan 27-48.pdf | 17 Mar 2026 |
| Building plan approvalFile: Building Plan 28-48.pdf | 17 Mar 2026 |
| Building plan approvalFile: Building Plan 29-48.pdf | 17 Mar 2026 |
| Building plan approvalFile: Building Plan 30-48.pdf | 17 Mar 2026 |
| Building plan approvalFile: Building Plan 31-48.pdf | 17 Mar 2026 |
| Building plan approvalFile: Building Plan 32-48.pdf | 17 Mar 2026 |
| Withdrawal Update Form 1File: FORM 1 ERR WING D Dec 25.pdf | 28 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2 ERR WING D Dec 25.pdf | 28 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 ERR Wing D Dec 25.pdf | 28 Feb 2026 |
| Form 2A (FY 2021-2022)File: Form 2 A ERR Wing D Feb 22.pdf | 8 Jan 2026 |
| Form 2A (FY 2022-2023)File: FORM 2A ( 2022-2023).pdf | 8 Jan 2026 |
| Form 2A (FY 2023-2024)File: FORM 2A (2023-2024).pdf | 8 Jan 2026 |
| Form 2A (FY 2024-2025)File: Form 2A ERR Wing D FY 24-25.pdf | 8 Jan 2026 |
| Form 5 (FY 2021-2022)File: Form 5 FY (2021-2022).pdf | 8 Jan 2026 |
| Form 5 (FY 2022-2023)File: FORM 5 FY (2022-2023).pdf | 8 Jan 2026 |
| Form 5 (FY 2023-2024)File: FORM 5 (2023-2024).pdf | 8 Jan 2026 |
| Withdrawal Update Form 1File: FORM 1 ERR WING D Sept 25.pdf | 25 Dec 2025 |
| Withdrawal Update Form 2File: FORM 2 ERR WING D Sept 25.pdf | 25 Dec 2025 |
| Withdrawal Update Form 3File: Form 3 ERR Wing D Sept 25.pdf | 25 Dec 2025 |
| Form 5 (FY 2024-2025)File: ERR Wing D Form 5.pdf | 25 Dec 2025 |
| Withdrawal Update Form 1File: FORM 1 ERR WING D June 25.pdf | 24 Dec 2025 |
| Withdrawal Update Form 2File: FORM 2 ERR WING D June 25.pdf | 24 Dec 2025 |
| Withdrawal Update Form 3File: Form 3 ERR Wing D June 25.pdf | 24 Dec 2025 |
| Form 1File: Form 1 Architect Cetificate Mar 2025.pdf | 23 Dec 2025 |
| Form 2File: Form 2 Engg Certificate Mar 25.pdf | 23 Dec 2025 |
| Form 3File: Form 3 CA Cetificate Mar 2025.pdf | 23 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD INVENTORY Mar 25.pdf | 23 Dec 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 24 Wing D.pdf | 1 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 24 Wing D.pdf | 1 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 24 Wing D.pdf | 1 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 ERR Wing D 23-24.pdf | 1 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ERR Wing D Jun 24.PDF | 9 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ERR Wing D Sept 24.PDF | 9 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 ERR Wing D Jun 24.PDF | 9 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 ERR Wing D Sept 24.PDF | 9 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ERR Wing D Jun 2024.PDF | 9 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ERR Wing D Sept 2024.PDF | 9 Nov 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrances Declaration Legal.PDF | 13 Aug 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrances Declaration Finance.PDF | 13 Aug 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrances Declaration Legal.PDF | 13 Aug 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrances Declaration Finance.PDF | 13 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Cetificate Mar 2023.PDF | 13 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Cetificate Jun 2023.PDF | 13 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Cetificate Sept 2023.PDF | 13 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Cetificate Dec 2023.PDF | 13 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Cetificate Mar 2024.PDF | 13 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Mar 2023.PDF | 13 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Jun 2023.PDF | 13 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Sept 2023.PDF | 13 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Dec 2023.PDF | 13 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Mar 2024.PDF | 13 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Quality Assurance 22-23.PDF | 13 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Quality Assurance 23-24.PDF | 13 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory ERR Wing D Mar 23.PDF | 13 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory ERR Wing D Jun 23.PDF | 13 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory ERR Wing D Sept 23.PDF | 13 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory ERR Wing D Dec 23.PDF | 13 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory ERR Wing D Mar 24.PDF | 13 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Mar 23 Wing D.pdf | 13 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 23 Wing D.pdf | 13 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sept 23 Wing D.pdf | 13 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 23 Wing D.pdf | 13 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Mar 24 Wing D.pdf | 13 Aug 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration of Other RERA.PDF | 13 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: D wing CA Certificate.pdf | 13 Mar 2024 |
| Declaration about Commencement CertificateFile: Declaration Commencement Certificate 2022.PDF | 16 Apr 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Treasure | Kashid Park Pimple Gurav Pune. | 265 | Completed | Mar 2012 | Mar 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 5 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 112 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Eastern River Residency Wing D on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kashid Park13,700+ in Pune
Filed coordinates, straight-line distance. 91 registered projects within 2 km.
Samrajya Wing GH
Garve Patil Construction Company
Eastern River Residency Wing C
Kishor Shankar Garve
KRISHNA PRABHA AANGAN
RATHOD AND SONS
Eastern River Residency Wing B
Kishor Shankar Garve
Samrajya C Wing
Garve Patil Construction Company
10 Elite Akasa
Kadam Jagtap Associates
Builder: Kishor Shankar Garve
Kishor Shankar Garve has 6 registrations on MahaRERA, including Eastern River Residency Wing F and Eastern River Residency Wing D. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 4 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Eastern River Residency Wing D is delayed beyond 30 Apr 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Eastern River Residency Wing D?
The registered promoter entity is Kishor Shankar Garve, an individual as per the filing. Its GSTIN 27AAVPG2791H1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Eastern River Residency Wing D?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Eastern River Residency Wing D?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Eastern River Residency Wing D?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Eastern River Residency Wing D?
The professionals named in the filing: Architect: Milind Patil; Engineer: Prathamesh Sugate; Engineer: Venkangouda V Jadiyappagoudar; Engineer: VKG Associates; Chartered Accountant: Chaudhari Agarwal and Associates; Chartered Accountant: TEJAS SATHE & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Eastern River Residency Wing D?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback