Home / Browse projects / Pune, Maharashtra / DWARKA SQUARE PHASE I

Registered No litigation declared Residential / Group Housing project

DWARKA SQUARE PHASE I

By ASHA PROPERTIES

RG-MH-25127 · RERA P52100010743 · Last updated on MahaRERA portal: 17 Dec 2025

Source: official MahaRERA filing

Red flags

  • 3 complaints at MahaRERA
  • Completion date moved by 78 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 78 months from the original
24 of 55Construction stages doneacross 5 buildings; furthest along: Sanitary Fittings within the flats /..., 90%
123 of 262Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 33 documents Report an error

DWARKA SQUARE PHASE I is a Residential / Group Housing project by ASHA PROPERTIES in Pune, Maharashtra, registered with MahaRERA as P52100010743 on 31 Aug 2017. Possession is promised by 30 Jun 2027. The completion date has moved by 78 months from the original filing. 139 of the 262 units on this registration are recorded sold or booked, and 24 of 55 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameDWARKA SQUARE PHASE I
  • TypeResidential / Group Housing
  • Location
    • 4 CHOVISAWADI
    • CHARHOLI
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100010743
  • ReraGenie IDRG-MH-25127

Builder

  • NameASHA PROPERTIES
  • Entity typePartnership
  • PartnersSHAILESH SHANTILAL PATEL, YUVRAJ RAMESH LANDE, MAHESH KONDAJI GHAWATE

Key dates

this monthRegisteredAug 2017First promiseDec 2020Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Aug 2017
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Dec 2020)
  • Buildings5 building records
  • Documents filed33 files

Current status

53%139 of 262 units booked
77.8%Work done, per cost certificate

Figures as on 17 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA21000
BNA15844044
CNA151294094
DNA151268068
MHADANA10756056

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 17 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B84%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
C90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
D90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
MHADA0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 17 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed5

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5
Closed/Covered5
BuildingClosed/CoveredTotal
A11
B11
C11
D11
MHADA11

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area19,400 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
DEVIDAS BABAN TAPKIRCHARHOLIPune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI12304.49
Proposed, not sanctioned11,493 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNIGDI PRADHIKARAN
Estimated costRs 35.16 cr
Cost incurredRs 27.36 cr
Work done77.81%
BuildingWingEstimatedIncurred
CNARs 12.78 crRs 12.49 cr
DNARs 9.24 crRs 9.03 cr
BNARs 5.98 crRs 5.84 cr
MHADANARs 3.65 cr-
-NARs 3.52 cr-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMAHENDRA THAKUR
EngineerR K RANDHAVE CONSUTANT
Chartered AccountantAkshay Lad
PartnerRole in project
ASHA PROPERTIES-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100011172Dec 2020 → Dec 2023

Reason as filed by the promoterDue to Covid-19, work was affected and hence completion is delayed by one year.

EA16122518701Dec 2020 → Jun 2027

Reason as filed by the promoterWe are writing to request an extension for the completion timeline of our project, which includes Wing A, Wing B, Wing C, Wing D & Wing Mhada, registered under RERA in 2017. The COVID-19 pandemic severely impacted the project, causing several disruptions: • Customer Payment Deferrals: Many buyers in Wing B, Wing C, Wing D deferred their payments due to financial uncertainty, which affected our cash flow and resulted in a shortage of working capital. • Construction Slowdown: Lockdowns and restrictions from 2020 to 2021 caused labour shortages, supply chain disruptions, and site closures, forcin

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC005000000117014VISHAL SHANKARRAO DHOTEAsha Properties through its partner Arvind Kapurchand Solanki04/05/2022
CC005000000116972Devendrasingh Yogarajsingh RajputAsha Properties25/04/2022
CC005000000471175DwarkaSquare FlatOwnersShailesh Kantilal Patel25/06/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed33

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2020-2021)File: Form 2A Quality Assurances Certificate March 2021.pdf17 Dec 2025
Form 2A (FY 2021-2022)File: Form 2A Quality Assurances Certificate March 2022.pdf17 Dec 2025
Form 2A (FY 2022-2023)File: Form 2A Quality Assurances Certificate March 2023.pdf17 Dec 2025
Form 2A (FY 2023-2024)File: Form 2A Quality Assurances Certificate March 2024.pdf17 Dec 2025
Form 2A (FY 2024-2025)File: Form 2A Quality Assurances Certificate March 2025.pdf17 Dec 2025
Withdrawal Update Form 1File: Form 1 Architect Certificate September 2025.pdf16 Dec 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate Sept 2025.pdf16 Dec 2025
Withdrawal Update Form 3File: Form 2 Engineer Certificate Sept 2025.pdf16 Dec 2025
CERSAI detailsFile: CERSAI_Search_Report.pdf21 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5.pdf21 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5.pdf21 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5.pdf21 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5.pdf21 Feb 2022
Copy of the legal title reportFile: Title Report_compressed.pdf23 Dec 2021
Declaration about Commencement CertificateFile: circular 32.pdf23 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 310321.pdf23 Dec 2021
Disclosure of sold/ booked inventoryFile: sold circuler 29.pdf23 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: Download File (2) (1).pdf5 Mar 2018
OtherFile: Dwarka Square Declaration (1)-ilovepdf-compressed.pdf28 Jan 2018
Certificates of CA (Form 3)File: FORM 3 CA Certificate DAWARKA.pdf12 Aug 2017
OtherFile: Dwarka Undertaking.pdf12 Aug 2017
Layout approvalFile: scan00354 ASHA PROPERTIES LAY OUT.pdf11 Aug 2017
Building plan approvalFile: asha pro IOD Plan 2 Final.pdf11 Aug 2017
PAN CardFile: asha properties pan card1.pdf11 Aug 2017
Copy of the legal title reportFile: Dwarka Search report.pdf11 Aug 2017
Details of encumbrancesFile: DHFL SAnction Letter.pdf11 Aug 2017
Copy of Layout Approval (in case of layout)File: scan00354 ASHA PROPERTIES LAY OUT.pdf11 Aug 2017
Building Plan Approval (IOD)File: asha pro IOD Plan 2 Final.pdf11 Aug 2017
Declaration in FORM BFile: Asha Properties Form B.pdf11 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Asha Propety Architect Data.pdf11 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Download File (1).pdf11 Aug 2017
Proforma of Allotment letterFile: Allotment letter.pdf11 Aug 2017
Proforma of Allotment letterFile: asha properties draft 1.pdf11 Aug 2017

How this compares with Pune

53%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 78 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DWARKA SQUARE PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHARHOLI13,700+ in Pune

2 kmDWARKA SQUARE PHASE ICompleted 65Lapsed / revoked 32Other 87Dot size: filed unitsN

Filed coordinates, straight-line distance. 184 registered projects within 2 km.

Builder: ASHA PROPERTIES

ASHA PROPERTIES has 1 registration on MahaRERA, including DWARKA SQUARE PHASE I. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if DWARKA SQUARE PHASE I is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DWARKA SQUARE PHASE I?

The registered promoter entity is ASHA PROPERTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DWARKA SQUARE PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against DWARKA SQUARE PHASE I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for DWARKA SQUARE PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DWARKA SQUARE PHASE I?

The professionals named in the filing: Architect: MAHENDRA THAKUR; Engineer: R K RANDHAVE CONSUTANT; Chartered Accountant: Akshay Lad. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DWARKA SQUARE PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DWARKA SQUARE PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DWARKA SQUARE PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.