- Registration lapsed
- Possession 19 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Chandrapur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DSKPARK 2 is a Residential / Group Housing project by DSK INFRA PROJECT in Chandrapur, Maharashtra, registered with MahaRERA as P50900028197 on 10 Feb 2021. Possession was promised by 30 Mar 2025 and is now 19 months past that date.
At a glance
Project
- NameDSKPARK 2
- TypeResidential / Group Housing
- Location
- OPP ZEE MOUNT LITERA SCHOOL KOSARA
- CHANDRAPUR
- Kosara
- 442406
- Pincode442406
- RERA no.P50900028197
- ReraGenie IDRG-MH-03576
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on10 Feb 2021
- Promised completion30 Mar 2025
- Revised completionNone
- Buildings25 building records
- Documents filed59 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| DUPLEX ROWHOUSE | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 2 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 3 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 4 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 5 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 6 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 7 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 8 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 9 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 10 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 11 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 12 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 13 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 14 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 15 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX 16 A | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 16 B | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 17 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 18 A | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 18 B | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 19 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 20 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 21 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 22 | NA | 2 | 0 | 0 | 0 | 0 |
| DUPLEX ROWHOUSE 23 | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 3 Feb 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 25 buildings; the table lists the first 20.
0 of 275 construction stages are filed complete across 25 buildings. The stage furthest along is Excavation, at 0%.
DUPLEX ROWHOUSE0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 20%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 30%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 40%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 50%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 60%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 70%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 80%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 90%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 100%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 110%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 120%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 130%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 140%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 150%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX 16 A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 16 B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 170%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 18 A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DUPLEX ROWHOUSE 18 B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 3 Feb 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 10% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 10% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 10% |
| Open Parking | No | Not applicable |
Parking filed25
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| DUPLEX ROWHOUSE | 1 | 1 |
| DUPLEX ROWHOUSE 2 | 1 | 1 |
| DUPLEX ROWHOUSE 3 | 1 | 1 |
| DUPLEX ROWHOUSE 4 | 1 | 1 |
| DUPLEX ROWHOUSE 5 | 1 | 1 |
| DUPLEX ROWHOUSE 6 | 1 | 1 |
| DUPLEX ROWHOUSE 7 | 1 | 1 |
| DUPLEX ROWHOUSE 8 | 1 | 1 |
| DUPLEX ROWHOUSE 9 | 1 | 1 |
| DUPLEX ROWHOUSE 10 | 1 | 1 |
| DUPLEX ROWHOUSE 11 | 1 | 1 |
| DUPLEX ROWHOUSE 12 | 1 | 1 |
| DUPLEX ROWHOUSE 13 | 1 | 1 |
| DUPLEX ROWHOUSE 14 | 1 | 1 |
| DUPLEX ROWHOUSE 15 | 1 | 1 |
| DUPLEX 16 A | 1 | 1 |
| DUPLEX ROWHOUSE 16 B | 1 | 1 |
| DUPLEX ROWHOUSE 17 | 1 | 1 |
| DUPLEX ROWHOUSE 18 A | 1 | 1 |
| DUPLEX ROWHOUSE 18 B | 1 | 1 |
| DUPLEX ROWHOUSE 19 | 1 | 1 |
| DUPLEX ROWHOUSE 20 | 1 | 1 |
| DUPLEX ROWHOUSE 21 | 1 | 1 |
| DUPLEX ROWHOUSE 22 | 1 | 1 |
| DUPLEX ROWHOUSE 23 | 1 | 1 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DEVENDRA MOTWANI |
| Engineer | ANANT KAPSE |
| Chartered Accountant | SHUBHANGI CHIDDARWAR |
| Partner | Role in project |
|---|---|
| DSK INFRA PROJECT | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 1 Feb 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Feb 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Feb 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Feb 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed59
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Building plan approvalFile: pl 11.pdf | 3 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 11.pdf | 3 Feb 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERT.pdf | 3 Feb 2021 |
| Layout approvalFile: LAYOUT MAP.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 1.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 2.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 3.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 4.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 5.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 6.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 7.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 8.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 9.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 10.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 12.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 13.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 14.pdf | 1 Feb 2021 |
| Building plan approvalFile: PL NO 15.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 16 a.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 16 b.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 17.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 18 a.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 18 b.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 19.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 20.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 21.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 22.pdf | 1 Feb 2021 |
| Building plan approvalFile: pl 23.pdf | 1 Feb 2021 |
| PAN CardFile: DSK INFRA PAN.pdf | 1 Feb 2021 |
| Copy of the legal title reportFile: LEGAL REPORT PHASE 2 FINAL.pdf | 1 Feb 2021 |
| Details of encumbrancesFile: ENCUMBARANCE CERT.pdf | 1 Feb 2021 |
| Copy of Layout Approval (in case of layout)File: LAYOUT MAP.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 1.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 2.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 3.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 4.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 5.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 6.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 7.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 8.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 9.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 10.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 12.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 13.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 14.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: PL NO 15.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 16 a.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 16 b.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 17.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 18 a.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 18 b.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 19.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 20.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 21.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 22.pdf | 1 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: pl 23.pdf | 1 Feb 2021 |
| Declaration in FORM BFile: FORM B.pdf | 1 Feb 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf | 1 Feb 2021 |
| Proforma of Allotment letterFile: Agreement_to_sale n allotment.pdf | 1 Feb 2021 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| DSK GREEN | DSK GREEN 317 DATALA NEW CHANDRAPUR | 2 | Completed | Mar 2021 | Mar 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Chandrapur
Computed across the 220+ Chandrapur projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 59 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep DSKPARK 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near CHANDRAPUR220+ in Chandrapur
RIDDHI 55 VILLAS
VIBHA RAJESH THAKUR
RIDDHI LEGACY TOWERS
YUVRAJ RAJESH THAKUR
TULIP
ANAYA INFRASTRUCTURE
CARNATION
SYNERGY PLOTTERS AND STRUCTURES
DAISY
SYNERGY PLOTTERS AND STRUCTURES
DSK HOMES
DSKINFRAPROJECT
See every Chandrapur project, with the district possession charts
Builder: DSK INFRA PROJECT
DSK INFRA PROJECT has 3 registrations on MahaRERA, including DSK GREEN and DSK PARK. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Chandrapur district page.
Frequently asked questions
What does it mean that DSKPARK 2 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if DSKPARK 2 is delayed beyond 30 Mar 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DSKPARK 2?
The registered promoter entity is DSK INFRA PROJECT, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DSKPARK 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for DSKPARK 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DSKPARK 2?
The professionals named in the filing: Architect: DEVENDRA MOTWANI; Engineer: ANANT KAPSE; Chartered Accountant: SHUBHANGI CHIDDARWAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DSKPARK 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback