Home / Browse projects / Bengaluru Urban, Karnataka / DS MAX SKY BLOSSOM

Registration approved No litigation declared Residential/Group Housing project

DS MAX SKY BLOSSOM

By DS-MAX PROPERTIES PRIVATE LIMITED

RG-KA-88108 · RERA PRM/KA/RERA/1251/310/PR/210324/006724 · Last updated on RERA Karnataka portal: 9 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Feb 2029Possession promisedno revision filed
6 of 18Construction stages donefurthest along: Masonry Construction, 0%
118 of 255Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 127 documents Report an error

DS MAX SKY BLOSSOM is a Residential/Group Housing project by DS-MAX PROPERTIES PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/210324/006724 on 21 Mar 2024. Possession is promised by 28 Feb 2029. 137 of the 255 units on this registration are recorded sold or booked, and 6 of 18 construction stages are filed complete.

At a glance

Project

  • NameDS MAX SKY BLOSSOM
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560068
  • Pincode560068
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/210324/006724
  • ReraGenie IDRG-KA-88108

Builder

  • NameDS-MAX PROPERTIES PRIVATE LIMITED
  • Entity typeCompany
  • CINU70102KA2007PTC041508
  • GSTIN29AACCD6168M1Z3
  • Authorized SignatoryShiva Shankar Chikkeri
  • Managing DirectorK V SATISH
  • DirectorsK V SATISH, S P Dayanand, Asha Satish
  • Project HeadSANNAPUREDDY HIMAVANTHA REDDY
  • Other registrations38 more →
  • Declared earlier projects31 →

Key dates

this monthRegisteredMar 2024PromisedFeb 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 Mar 2024
  • Promised completion28 Feb 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed127 files

Current status

54%137 of 255 units booked
53.5%Of the estimated cost spent so far

Figures as on 9 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SKY BLOSSOM---2550255

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 9 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 18 construction stages are filed complete. The stage furthest along is Masonry Construction, at 0%.

Building: 33% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 9 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallYes0%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes50%
LiftsYes50%
Corridor/LobbiesYes50%
Fire escapesYes50%
Common entrance and exit for the building/common portico/foyer/verandahYes50%
BasementYes100%
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,171 sq m
Named landowners1
LandownerVillageDistrict
Savithramma--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 59.76 cr
Cost incurredRs 31.94 cr
Spent of the estimate53.45%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 59.76 crRs 23.62 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)-Rs 3.93 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMunendra Babu
EngineerSwarupananda Goud K S
Chartered AccountantK Somanatham

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed127

As listed on the registration, under the names the promoter filed them with; the newest 80 of 127 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/210324/006724 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Sky Blossom_0001.pdf9 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5, Q2,2026-27,DS Max Sky Blossom.pdf9 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Sky Blossom_0001.pdf9 Oct 2026
Q2 2026-27 Water supply and sewage board9 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)9 Oct 2026
Q2 2026-27 KPTCL- BESCOM9 Oct 2026
Q2 2026-27 Fire and Safety9 Oct 2026
Q2 2026-27 Airport Authority of India9 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department9 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: SKY BLOSSOM_0008.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form5, Q1,2025-26,DS Max Sky Blossom.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: SKY BLOSSOM_0007.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q1 2026-27 Fire and Safety14 Jul 2026
Q1 2026-27 Airport Authority of India14 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Sky Blossom_0006.pdf13 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form5,Q4,2025-26,DS Max Sky Blossom.pdf13 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Sky Blossom_CE Mar 26.pdf13 Apr 2026
Q4 2025-26 Water supply and sewage board13 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Apr 2026
Q4 2025-26 KPTCL- BESCOM13 Apr 2026
Q4 2025-26 Fire and Safety13 Apr 2026
Q4 2025-26 Airport Authority of India13 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department13 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Sky Blossom_0005.pdf12 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5, Q3,2025-26,DS Max Sky Blossom.pdf12 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Sky Blossom CE.pdf12 Jan 2026
Q3 2025-26 Water supply and sewage board12 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)12 Jan 2026
Q3 2025-26 KPTCL- BESCOM12 Jan 2026
Q3 2025-26 Fire and Safety12 Jan 2026
Q3 2025-26 Airport Authority of India12 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department12 Jan 2026
Annual Audit Filed StatusFile: 1 Annual Audit Filed Status.jpeg15 Mar 2024
Quarterly Filed StatusFile: 2 Quarterly Filed Status.png15 Mar 2024
Skyblossom bank AffidavitFile: 3 Skyblossom bank Affidavit.pdf15 Mar 2024
Zoning_Regulations_RMP2015 Vol III (2007)File: 4 Zoning_Regulations_RMP2015 Vol III (2007).pdf15 Mar 2024
CDP Master ExtractFile: 5 CDP Master Extract.jpeg15 Mar 2024
Village Map DemarcationFile: 6 Village Map Demarcation.jpeg15 Mar 2024
Location DemarcationFile: 7 Location Demarcation.jpeg15 Mar 2024
Clarification on Single Layout Plot and OrderFile: 8 Clarification on Single Layout Plot and Order.pdf15 Mar 2024
Clarification on Commencement CertificateFile: 9 Clarification on Commencement Certificate.pdf15 Mar 2024
Swarupanada_CE_LicenseFile: 10 Swarupanada_CE_License.pdf15 Mar 2024
SKY BLOSSOM PLAN WITH STP_PLAN & SECTION DETAILSFile: 11 SKY BLOSSOM PLAN WITH STP_PLAN & SECTION DETAILS.pdf15 Mar 2024
SKYBLOSSOM GUIDELINES VALUEFile: 12 SKYBLOSSOM GUIDELINES VALUE.pdf15 Mar 2024
Clarification on waterFile: 13 Clarification on water.pdf15 Mar 2024
Proforma AFS - SKY BLOSSOMFile: 14 Proforma AFS - SKY BLOSSOM.pdf15 Mar 2024
Common Areas and AmenitiesFile: 15 Common Areas and Amenities.pdf15 Mar 2024
RTC, survey 134/3-
Mutation, survey 134/3-
Encumbrance Certificate, survey 134/3-
Conversion/Alienation Order, survey 134/3-
Sale/Title/Gift Deed, survey 134/3-
JDA, survey 134/3-
Khatha, survey 134/3-
Registration CertificateFile: Certificate of Incorporation.pdf-
Organization StructureFile: DS-Max Properties Pvt Ltd - Organisation Chart.pdf-
Certificate issued by CA Form 1File: Form-1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form-2 Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Form-3 Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non-Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Form-1 CA Certificate.pdf-
Balance Sheet 2022 - 2023File: DS-Max Properties Financials 2022-23.pdf-
Balance Sheet 2021 - 2022File: Balance Sheet and P&L 2021-22.pdf-
Balance Sheet 2020 - 2021File: Balance Sheet 2020-21.pdf-
Audited Profit and Loss Statement 2022 - 2023File: DS-Max Properties Financials 2022-23.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Balance Sheet and P&L 2021-22.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Balance Sheet 2020-21.pdf-
Director's Report 2022 - 2023File: DS-Max Properties Financials 2022-23.pdf-
Director's Report 2021 - 2022File: Directors Report 2021-22.pdf-
Cash Flow Statement 2022 - 2023File: DS-Max Properties Financials 2022-23.pdf-
Cash Flow Statement 2021 - 2022File: Cashflow Statement 2021-22.pdf-
Auditor's Report 2022 - 2023File: DS-Max Properties Financials 2022-23.pdf-
Auditor's Report 2021 - 2022File: Auditors Report 2021-22.pdf-

How this compares with Bengaluru Urban

54%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep DS MAX SKY BLOSSOM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmDS MAX SKY BLOSSOMOther 26Dot size: filed unitsN

Filed coordinates, straight-line distance. 26 registered projects within 2 km.

Builder: DS-MAX PROPERTIES PRIVATE LIMITED

DS Max Properties Private Limited has 39 registrations on RERA Karnataka, including DS MAX SKY SISIRA and DS MAX SKY SAMURAI. Its filings declare 31 earlier projects, 18 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if DS MAX SKY BLOSSOM is delayed beyond 28 Feb 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of DS MAX SKY BLOSSOM?

The registered promoter entity is DS-MAX PROPERTIES PRIVATE LIMITED, a company as per the filing. Its CIN U70102KA2007PTC041508 and GSTIN 29AACCD6168M1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in DS MAX SKY BLOSSOM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at DS MAX SKY BLOSSOM?

The professionals named in the filing: Architect: Munendra Babu; Engineer: Swarupananda Goud K S; Chartered Accountant: K Somanatham. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DS MAX SKY BLOSSOM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DS MAX SKY BLOSSOM. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DS MAX SKY BLOSSOM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.