Home / Browse projects / Mumbai Suburban, Maharashtra / DOTOM ISLE-SHAKTI

Registration lapsed No litigation declared Residential / Group Housing project

DOTOM ISLE-SHAKTI

By M/S. DOTOM REAL ESTATE

RG-MH-79687 · RERA P51800031765 · Last updated on MahaRERA portal: 2 Jul 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • 4 complaints at MahaRERA
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
5 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 90%
4Complaints at MahaRERAon this registration
Jump to the 125 documents Report an error

DOTOM ISLE-SHAKTI is a Residential / Group Housing project by M/S. DOTOM REAL ESTATE in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800031765 on 9 Nov 2021. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 6 months from the original filing. 4 complaints are on record with the regulator.

At a glance

Project

  • NameDOTOM ISLE-SHAKTI
  • TypeResidential / Group Housing
  • Location
    • BHOOMI PARK ROAD
    • MALAD WEST
    • Borivali
    • Mumbai Suburban
    • 400095
  • Pincode400095
  • RERA no.P51800031765
  • ReraGenie IDRG-MH-79687

Builder

  • NameM/S. DOTOM REAL ESTATE
  • Entity typePartnership
  • GSTIN27AASFD4226D1ZH
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersDOTOM REALTY PVT LTD, MOHINI SKYLINE PVT LTD
  • Other registrations2 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

16 months past promisethis monthRegisteredNov 2021First promiseDec 2024Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Nov 2021
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed125 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CORALNA290000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

CORAL: 92% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)70%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 2 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes60%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes80%
Water conservation /Rain water harvestingYes60%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes10%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area23,122 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SHAKTI PROPERTY DEVELOPERS PRIVATE LIMITEDBorivaliMumbai Suburban

Approvals and building plan

Permissible FSI150783.33
Proposed, not sanctioned64,163 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFORT

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
M/S. DOTOM REAL ESTATE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800025426Dec 2024 → Jun 2025

Reason as filed by the promoterWE HAVE APPLIED FOR EXT U/S. 6 OF RERA ACT 2016 FOR 6 MONTHS, THAT IS, UPTO 30 TH JUNE 2025 WE HAVE COMPLETED THE BUILDING CONSTRUCTION WORK AS PER THE APPROVED PLAN AND APPLIED FOR THE FULL OC ON 7.01.2025 ANDARE AWAITING THE SANCTION OF THE SRA. THE PART OC UPTO THE 22ND FLOOR FOR FLATS NO 1 TO 4 ON EACH FLOOR IS ALREADY ISSUED BY SRA AND THE SAME UPLOADED IN THE ORIGINAL APPLICATION. WE HAVE UPDATED ALL THE QPR UPTO DECEMBER 2025 THAT IS FORM 1, 2, 3, 2A AND 5, SOLD BOOKED INVENTORY ETC. THE DECLARATION REGARDING THE EXPLANATION, REASON FOR DELAY, NEED FOR EXTENSION ETC AT SERIAL NO. 1 ALON

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC006000000292609DR.ROHITKUMAR VIJAYSHANKAR PANDEYM/s Dotom Real Estate13/09/2022
CC006000000354337Dotom Real EstateSameer Sarjerao Kharat15/02/2023
CC006000000439649M/s DOTOM Real Estate (Through its Authorized Representative)Mrs. Meena Uttam Chauhan20/03/2024
CC12600725manoj joshiM/S. DOTOM REAL ESTATE08/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Nov 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Nov 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jan 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 Jul 2025

Documents filed125

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 125 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FULLOC_1 (3).PDF2 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 of qpr 2 2023.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch CERT July - Sep 2023.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 of qpr 4 2023.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 of qpr 1 2024.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 wing S April - june 2024.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 of qpr 3 2024.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 of qpr 4 2024.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Dotom Isle Signed (Jan-Mar24).pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Annexure D Form 3 - S Wing (Oct-Dec24).pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Annexure D Form 3 - S Wing Final (Jul-Sept24).pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Dotom Annexure D Form 3 - S Wing (Apr-Jun24).pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Annexure D Form 3 - S Wing Final (Oct-Dec23).pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Annexure D Form 3 - S Wing Final (Jul-Sept23).pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Annexure D Form 3 - S Wing Final (Apr-Jun23) (1).pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Annexure D Form 3 - S Wing Final signed (1).pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 wing S jan - March 2023.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 of qpr 2 2023.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 wing S July - Sep 2023.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 wing S Oct - Dec 2023.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 of qpr 1 2024.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 wing S April - june 2024.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 of qpr 3 2024.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 of qpr 4 2024.pdf2 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC COPY S WING.pdf1 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf8 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2 A 2021-22.pdf8 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: S wing_signed.pdf8 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ilovepdf_merged (96).pdf7 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ilovepdf_merged (97).pdf7 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: P51800031765_FileName_0.pdf7 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2 a 2022.pdf7 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2 updated.pdf7 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 20250227175533.pdf28 Feb 2025
Declaration in FORM BFile: ilovepdf_merged (92) - converted.pdf25 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf18 Feb 2025
Declaration in FORM BFile: form b (6).pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 S WING.pdf17 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Annexure D Form 3 - S Wing New.pdf17 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 s.pdf17 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 S WING.pdf17 Feb 2025
Disclosure of sold/ booked inventoryFile: sold (3).pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DocScanner Feb 3, 2025 3-23 PM.pdf3 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ilovepdf_merged (85).pdf3 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DocScanner Feb 3, 2025 2-14 PM.pdf3 Feb 2025
Disclosure of sold/ booked inventoryFile: DocScanner Feb 3, 2025 3-03 PM.pdf3 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23) (4)_signed.pdf31 Jan 2025
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about RERA.pdf11 Jan 2025
Declaration in FORM BFile: FORM B PAGE 1_merged (1)_compressed.pdf9 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Coral ( S Wing).pdf9 Jan 2025
CERSAI detailsFile: CERSAI_Search_Report_200334847161_For_Debtor_Based_Search_09_01_2025_13_27_32_781.pdf9 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations (5).pdf9 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2022-23.pdf9 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2023-24.pdf9 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate (1).pdf5 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FINAL FORM 3.pdf5 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Structural Engineer Certificate.pdf5 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA AR CERT- TOWER-S-5-4-2024.pdf6 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA CERT- TOWER-S-5-4-2024.pdf6 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Annexure D Form 3 - S Wing Final.pdf6 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Dotom Isle.pdf6 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DocScanner 24-Apr-2024 2-04 pm_compressed.pdf24 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 new.pdf16 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 UPDATED.pdf21 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Cert - S Wing.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Annexure D Form 3 - S Wing Final.pdf16 Jan 2024
Details of encumbrances concerned to FinanceFile: RERA encumberence letter S Wing.pdf9 Jan 2024
Details of encumbrances concerned to LegalFile: RERA encumberence letter S Wing.pdf9 Jan 2024
Proforma of Agreement for saleFile: UPDATE_2 (1).pdf1 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A - S.pdf23 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Crt WING S.pdf6 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA CERT- TOWER-S-5-07-2023.pdf6 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 s.pdf6 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 s.pdf6 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory- Coral.pdf10 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tower S - Ar Certificate - Jan March 23.pdf3 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: TOWER-S-Engineer CERT- Jan March 23.pdf3 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Annexure D Form 3 - S Wing Final signed_compressed.pdf24 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: S Wing Certificate ASA.pdf24 Jun 2023

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 6 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DOTOM ISLE-SHAKTI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MALAD WEST6,700+ in Mumbai Suburban

Builder: M/S. DOTOM REAL ESTATE

M/S. DOTOM REAL ESTATE has 3 registrations on MahaRERA, including DOTOM ISLE-SHAKTI and SAPPHIRE-DOTOM ISLE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that DOTOM ISLE-SHAKTI shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if DOTOM ISLE-SHAKTI is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DOTOM ISLE-SHAKTI?

The registered promoter entity is M/S. DOTOM REAL ESTATE, a partnership as per the filing. Its GSTIN 27AASFD4226D1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DOTOM ISLE-SHAKTI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against DOTOM ISLE-SHAKTI?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for DOTOM ISLE-SHAKTI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in DOTOM ISLE-SHAKTI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DOTOM ISLE-SHAKTI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DOTOM ISLE-SHAKTI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.