Home / Browse projects / Mumbai Suburban, Maharashtra / Dolphin Tower

Registration lapsed No litigation declared Residential / Group Housing project

Dolphin Tower

By Rajendra Builders Private Limited

RG-MH-55746 · RERA P51800020320 · Last updated on MahaRERA portal: 10 Jan 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 29 months past the filed date
  • Completion date moved by 59 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
May 2024Possession promised29 months past this date
1 of 11Construction stages donefurthest along: Basement (if any), 50%
10 of 78Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

Dolphin Tower is a Residential / Group Housing project by Rajendra Builders Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800020320 on 5 Apr 2019. Possession was promised by 6 May 2024 and is now 29 months past that date. The completion date has moved by 59 months from the original filing. 68 of the 78 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameDolphin Tower
  • TypeResidential / Group Housing
  • Location
    • Off Marve Road
    • Jankalyan Nagar Behind Fire Brigade Station
    • Borivali
    • Mumbai Suburban
    • 400095
  • Pincode400095
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800020320
  • ReraGenie IDRG-MH-55746

Builder

  • NameRajendra Builders Private Limited
  • Entity typeCompany
  • Managing DirectorAmit Rajendra Singh

Key dates

29 months past promisethis monthRegisteredApr 2019First promiseJun 2019Revised toMay 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Apr 2019
  • Promised completion6 May 2024
  • Revised completionRevised to 6 May 2024 (originally 30 Jun 2019)
  • Buildings1 building record
  • Documents filed42 files

Current status

87%68 of 78 units booked

Figures as on 10 Jan 2024, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Dolphin TowerNA181678078

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 50%.

Dolphin Tower: 55% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)50%
Podiums (if any)50%
Plinth50%
Stilt Floor50%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 10 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed39

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots39
Closed/Covered39

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,148 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityBRIHANMUMBAI MUNICIPAL CORPORATION
Permissible FSI5714.68
Proposed, not sanctioned5,715 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSingh Sadan S V Road Santacruz West Mumbai 400054

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNeocon Infrastrucuture
Chartered AccountantViral Mehta & Co
PartnerRole in project
Rajendra Builders Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800016550Jun 2019 → Oct 2023

Reason as filed by the promoterWe have completed the proposed building comprising of Stilt + 1st to 16th upper floor on said plot. Now, we are Applying for Occupation Certificate/Building Completion Certificate for Completed building under reference, As per Proforma 'A' of Approved Amended plan dt. 09.01.2014, there is deduction for Road Set back area and Reservation of Municipal School (RE 1.1) and Playground which admeasures 2.58 Sq.mt. for Road Setback area, 4.90 Sq.mt. Municipal School Re(1. 1) and Playground 19.50 Sq.mt. which we have already Handed over to MCGM as per the Possession Receipt u.no. CHE/ DP/ 19047/TDR dt

EXT51800017967Jun 2019 → May 2024

Reason as filed by the promoterProject is completed only OC is pending due to plot handover to BMC

Litigation declared4

CaseCourtStatus
CC/13/280/2013Consumer CourtPending
3510/2012Bombay City Civil CourtNot to sold
1671/2014Bombay City Civil Court DindoshiNot to create third part right
1801-1808/2014Bombay City Civil CourtNot to create third part right

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Apr 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Apr 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Apr 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RBPL Rera Form 5.pdf10 Jan 2024
Certificates of CA (Form 3)File: Form 3 rajendra Builder 30 Dec 2023_compressed.pdf4 Jan 2024
Declaration in FORM BFile: Form B extn.pdf16 Nov 2023
Declaration about Commencement CertificateFile: CC Declaration corrected.pdf20 Jun 2023
Declaration in FORM BFile: Form B Corrected.pdf20 Jun 2023
Declaration in FORM BFile: Form B 6 month extension.pdf17 Jun 2023
Declaration about Commencement CertificateFile: CC declaration.pdf15 Jun 2023
Declaration in FORM BFile: Form B affidavit.pdf15 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 neocon.pdf15 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 annual report_compressed.pdf15 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 annual report_compressed.pdf15 Jun 2023
OtherFile: Soc Reg Certificate.pdf15 Jun 2023
OtherFile: rajendra builders 1.pdf15 Jun 2023
OtherFile: rajendra builders 2.pdf15 Jun 2023
OtherFile: dolphin tower letter.pdf15 Jun 2023
Disclosure of sold/ booked inventoryFile: Unsold Inventory List.pdf31 May 2023
Disclosure of sold/ booked inventoryFile: Unsold List.pdf31 May 2023
Certificates of CA (Form 3)File: April-June_22_compressed.pdf26 May 2023
Certificates of CA (Form 3)File: July - Sept_22_compressed.pdf26 May 2023
Certificates of CA (Form 3)File: Oct - Dec_22_compressed.pdf26 May 2023
Certificates of CA (Form 3)File: Jan-March_23_compressed.pdf26 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5.pdf26 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf26 May 2023
Layout approvalFile: Plan - 1 (1).pdf3 Apr 2019
Layout approvalFile: Plan - 2 (1).pdf3 Apr 2019
Layout approvalFile: Plan - 3 (1).pdf3 Apr 2019
Layout approvalFile: Plan - 4 (1).pdf3 Apr 2019
Layout approvalFile: Plan - 5 (1).pdf3 Apr 2019
Copy of Layout Approval (in case of layout)File: Plan - 1 (1).pdf3 Apr 2019
Copy of Layout Approval (in case of layout)File: Plan - 2 (1).pdf3 Apr 2019
Copy of Layout Approval (in case of layout)File: Plan - 3 (1).pdf3 Apr 2019
Copy of Layout Approval (in case of layout)File: Plan - 4 (1).pdf3 Apr 2019
Copy of Layout Approval (in case of layout)File: Plan - 5 (1).pdf3 Apr 2019
Declaration in FORM BFile: Form B.pdf3 Apr 2019
OtherFile: Declaration .pdf3 Apr 2019
Building plan approvalFile: IOD - Rajendra builders RESIZE_compressed.pdf1 Apr 2019
Copy of the legal title reportFile: Title Certificate.pdf1 Apr 2019
Details of encumbrancesFile: Encumbrance Certificate.pdf1 Apr 2019
Building Plan Approval (IOD)File: IOD - Rajendra builders RESIZE_compressed.pdf1 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf1 Apr 2019
Certificates of CA (Form 3)File: Form 3.pdf1 Apr 2019
Proforma of Allotment letterFile: AGREEMENT RBPL (1).pdf1 Apr 2019

How this compares with Mumbai Suburban

87%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 59 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Dolphin Tower on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Jankalyan Nagar Behind Fire Brigade Station6,700+ in Mumbai Suburban

2 kmDolphin TowerCompleted 51Lapsed / revoked 39Other 67Dot size: filed unitsN

Filed coordinates, straight-line distance. 157 registered projects within 2 km.

Builder: Rajendra Builders Private Limited

Rajendra Builders Private Limited has 1 registration on MahaRERA, including Dolphin Tower. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Dolphin Tower shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Dolphin Tower is delayed beyond 6 May 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Dolphin Tower?

The registered promoter entity is Rajendra Builders Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Dolphin Tower?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Dolphin Tower?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Dolphin Tower?

The professionals named in the filing: Architect: Neocon Infrastrucuture; Chartered Accountant: Viral Mehta & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Dolphin Tower?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Dolphin Tower. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Dolphin Tower to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.