ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / DIVYA ELITE

Registered No litigation declared Others project

DIVYA ELITE

By RRS INFRACON LLP

RG-MH-66224 · RERA P52100047933 · Last updated on MahaRERA portal: 15 Apr 2026

Source: official MahaRERA filing

Red flags

  • Possession 2 months past the filed date
  • Completion date moved by 14 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Aug 2026Possession promised2 months past this date
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 90%
4 of 12Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 64 documents Report an error

DIVYA ELITE is a Others project by RRS INFRACON LLP in Pune, Maharashtra, registered with MahaRERA as P52100047933 on 1 Dec 2022. Possession was promised by 31 Aug 2026 and is now 2 months past that date. The completion date has moved by 14 months from the original filing. 8 of the 12 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameDIVYA ELITE
  • TypeOthers
  • Location
    • KATRAJ KONDHWA ROAD
    • KONDHWA
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411046
  • Pincode411046
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100047933
  • ReraGenie IDRG-MH-66224

Builder

  • NameRRS INFRACON LLP
  • Entity typePartnership
  • PartnersROHIT RAJIV SHETH, ROHAN RAJIV SHETH

Key dates

2 months past promisethis monthRegisteredDec 2022First promiseJun 2025Revised toAug 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Dec 2022
  • Promised completion31 Aug 2026
  • Revised completionRevised to 31 Aug 2026 (originally 30 Jun 2025)
  • Buildings1 building record
  • Documents filed64 files

Current status

67%8 of 12 units booked
52.9%Work done, per cost certificate

Figures as on 15 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DIVYA ELITENA668412

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.

DIVYA ELITE: 53% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 15 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed33

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots33
Open Space33

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area500 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
NITIN PRALHAD CHAVANPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPMC
Permissible FSI1202.13
Proposed, not sanctioned827 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKATRAJ, PUNE
Estimated costRs 2.27 cr
Cost incurredRs 1.20 cr
Work done52.92%
BuildingWingEstimatedIncurred
DIVYA ELITENARs 2.27 crRs 1.20 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAGAR SURESH MEHTA
EngineerROHIT RAJIV SHETH
Chartered AccountantROHIT R SHAH & CO
PartnerRole in project
RRS INFRACON LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA23042620711Jun 2025 → Aug 2026

Reason as filed by the promoterHEALTH ISSUES OF THE PROMOTER RESULTED IN THE DELAY. AS ON 31/03/2026, THE WORK IS 90 PERCENT COMPLETE AND THE COMPLETION IS EXPECTED TO BE RECEIVED BY THE END OF MAY 2026

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Oct 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed64

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1 30092024.pdf15 Apr 2026
Form 2File: FORM 2 engineer 300924-signed.pdf15 Apr 2026
Form 3File: FORM 3 30092024 SIGNED.pdf15 Apr 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF INVENTORY 30092024.pdf15 Apr 2026
Form 1File: FORM 1 31122024.pdf15 Apr 2026
Form 2File: FORM 2 engineer 311224-signed.pdf15 Apr 2026
Form 3File: FORM 3 31122024 SIGNED.pdf15 Apr 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF INVENTORY 31122024.pdf15 Apr 2026
Form 1File: FORM 1 31032025.pdf15 Apr 2026
Form 2File: FORM 2 engineer 310325-signed.pdf15 Apr 2026
Form 3File: FORM 3 31032025 SIGNED.pdf15 Apr 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF INVENTORY 31032025.pdf15 Apr 2026
Withdrawal Update Form 1File: FORM 1 30062025.pdf15 Apr 2026
Withdrawal Update Form 2File: FORM 2 engineer 300625.pdf15 Apr 2026
Withdrawal Update Form 3File: FORM 3 30062025 SIGNED.pdf15 Apr 2026
Form 1File: FORM 1 31122022.pdf8 Apr 2026
Form 2File: FORM 2 engineer 311222-signed.pdf8 Apr 2026
Form 3File: FORM 3 31122022 SIGNED.pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF INVENTORY 31122022.pdf8 Apr 2026
Form 1File: FORM 1 31032023.pdf8 Apr 2026
Form 2File: FORM 2 engineer 310323-signed.pdf8 Apr 2026
Form 3File: FORM 3 31032023 SIGNED.pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF INVENTORY 31032023.pdf8 Apr 2026
Form 1File: FORM 1 30062023.pdf8 Apr 2026
Form 2File: FORM 2 engineer 300623-signed.pdf8 Apr 2026
Form 3File: FORM 3 30062023 SIGNED.pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF INVENTORY 30062023 - for merge.pdf8 Apr 2026
Form 1File: FORM 1 31122023.pdf8 Apr 2026
Form 2File: FORM 2 engineer 311223-signed.pdf8 Apr 2026
Form 3File: FORM 3 31122023 SIGNED.pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF INVENTORY 31122023.pdf8 Apr 2026
Form 1File: FORM 1 31032024.pdf8 Apr 2026
Form 2File: FORM 2 engineer 310324-signed.pdf8 Apr 2026
Form 3File: FORM 3 31032024 SIGNED.pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF INVENTORY 31032024.pdf8 Apr 2026
Form 1File: FORM 1 30062024.pdf8 Apr 2026
Form 2File: FORM 2 engineer 300624.pdf8 Apr 2026
Form 3File: FORM 3 30062024 SIGNED.pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF INVENTORY 30062024.pdf8 Apr 2026
Proforma of Agreement for saleFile: _- REVISED MASTER DRAFT- DIVYA ELITE.pdf21 Nov 2022
Deviation Report with respect to model copy of AgreementFile: Deviation Certificate AFS_.pdf21 Nov 2022
Details of encumbrances concerned to FinanceFile: Legal Encumbrance _compressed.pdf16 Nov 2022
Details of encumbrances concerned to LegalFile: Legal Encumbrance _compressed.pdf16 Nov 2022
Deviation Report with respect to Allotment letterFile: Deviation Letter AL1_compressed.pdf16 Nov 2022
Proforma of Allotment letterFile: ALLOTMENT.pdf14 Nov 2022
Details of encumbrances concerned to FinanceFile: FINANCIAL ENCUMBRANCES SIGNED.pdf20 Oct 2022
Details of encumbrances concerned to LegalFile: LEGAL ENCUMBRANCES SIGNED.pdf20 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SCANNED AND SIGNED.pdf20 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SIGNED.pdf20 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED_compressed.pdf20 Oct 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORM A DECLARATION ABOUT BANK ACCOUNT SIGNED.pdf20 Oct 2022
Layout approvalFile: Plan1_compressed.pdf18 Oct 2022
Building plan approvalFile: plan 2.pdf18 Oct 2022
PAN CardFile: 882035188346410_signed_unlocked.pdf18 Oct 2022
Copy of the legal title reportFile: Scan format A legal title report.pdf18 Oct 2022
Copy of Layout Approval (in case of layout)File: Plan1_compressed.pdf18 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: plan 2.pdf18 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: NA Order -1.pdf18 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement 040820200.pdf18 Oct 2022
Declaration about Commencement CertificateFile: FORM D DECLARATION ABOUT COMMENCEMENT CERTIFICATE SIGNED.pdf18 Oct 2022
Declaration in FORM BFile: Form B (2).pdf18 Oct 2022
CERSAI detailsFile: CERSAI_Search_Report_200250106793_For_Asset_Based_Search_18_10_2022_19_13_28_328.pdf18 Oct 2022
CERSAI detailsFile: CERSAI_Search_Report_200250106773_For_Asset_Based_Search_18_10_2022_19_13_09_242.pdf18 Oct 2022
CERSAI detailsFile: CERSAI_Search_Report_200250106664_For_Asset_Based_Search_18_10_2022_19_11_32_273.pdf18 Oct 2022

How this compares with Pune

67%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 14 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DIVYA ELITE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KONDHWA13,700+ in Pune

2 kmDIVYA ELITECompleted 68Lapsed / revoked 41Other 54Dot size: filed unitsN

Filed coordinates, straight-line distance. 163 registered projects within 2 km.

Builder: RRS INFRACON LLP

RRS INFRACON LLP has 1 registration on MahaRERA, including DIVYA ELITE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if DIVYA ELITE is delayed beyond 31 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DIVYA ELITE?

The registered promoter entity is RRS INFRACON LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DIVYA ELITE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DIVYA ELITE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DIVYA ELITE?

The professionals named in the filing: Architect: SAGAR SURESH MEHTA; Engineer: ROHIT RAJIV SHETH; Chartered Accountant: ROHIT R SHAH & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DIVYA ELITE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DIVYA ELITE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DIVYA ELITE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.