Home / Browse projects / Pune, Maharashtra / DHRUPI TOWERS

Registration lapsed No litigation declared Others project

DHRUPI TOWERS

By HRITIK NITIN JAIN

RG-MH-48404 · RERA P52100077117 · Last updated on MahaRERA portal: 20 Aug 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 3 months past the filed date
  • Completion date moved by 19 months
  • 2 extensions taken
  • Rs 1.00 crore secured on the land, in favour of HRITIK JAIN
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2026Possession promised3 months past this date
4 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 80%
11 of 18Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 28 documents Report an error

DHRUPI TOWERS is a Others project by HRITIK NITIN JAIN in Pune, Maharashtra, registered with MahaRERA as P52100077117 on 23 Jul 2024. Possession was promised by 31 Jul 2026 and is now 3 months past that date. The completion date has moved by 19 months from the original filing. 7 of the 18 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameDHRUPI TOWERS
  • TypeOthers
  • Location
    • LAXMI NARAYAN NAGAR Lane no 5
    • CHAROLI (BK)
    • Wadmukhwadi
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100077117
  • ReraGenie IDRG-MH-48404

Builder

  • NameHRITIK NITIN JAIN
  • Entity typeIndividual

Key dates

3 months past promisethis monthRegisteredJul 2024First promiseDec 2024Revised toJul 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 Jul 2024
  • Promised completion31 Jul 2026
  • Revised completionRevised to 31 Jul 2026 (originally 24 Dec 2024)
  • Buildings1 building record
  • Documents filed28 files

Current status

39%7 of 18 units booked

Figures as on 20 Aug 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DHRUPI TOWERSNA6516218

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 80%.

DHRUPI TOWERS: 66% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)70%
Podiums (if any)0%
Plinth70%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area449 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofHRITIK JAIN
Secured amountRs 1.00 crore
CERSAI search filedYes
Declared on11 Jul 2025

Approvals and building plan

Sanctioning authorityPIMPRI CHINCHWAD MUNCIPAL CORPORATION
Permissible FSI789.52
Proposed, not sanctioned790 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKHADKI

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAJENDRA LONDE
ArchitectVIRENDRA SANJAY OSWAL
Engineerinfinity consultant
Chartered AccountantOSWAL AND HEDA
PartnerRole in project
HRITIK NITIN JAIN-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100027313Dec 2024 → Jun 2025

Reason as filed by the promoterDUE TO PENDING LIFT NOC FROM THE CONSULTANT.AND WE CANNOT TAKE THE OC

EA11072502048Dec 2024 → Jul 2026

Reason as filed by the promoterDUE TO PENDING OCCUPANCY CERTIFICATE

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Apr 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed28

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: ARCHITECT CERTIFICATE.pdf20 Aug 2025
Form 2File: FORM 2.pdf20 Aug 2025
Form 3File: FORM 3- Final-Q4 V-4.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf20 Aug 2025
Declaration in FORM BFile: FORM B.pdf16 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf10 Jul 2024
Declaration about Commencement CertificateFile: Declaration Cum Undertaking.pdf23 May 2024
Other - LegalFile: sale deed compress.pdf4 May 2024
Other - FinanceFile: Untitled design_20240420_123846_0000.pdf24 Apr 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: declaration about separate bank account .pdf22 Apr 2024
Details of encumbrances concerned to FinanceFile: legal encumbrance .pdf16 Apr 2024
Details of encumbrances concerned to LegalFile: legal encumbrance .pdf16 Apr 2024
Declaration about Commencement CertificateFile: Declaration about commencement certificate .pdf11 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold -booked inventory.pdf11 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organizations .pdf11 Apr 2024
Copy of the legal title reportFile: Legal title search report (1).pdf5 Apr 2024
CERSAI detailsFile: DocScanner 5 Apr 2024 19-25.pdf5 Apr 2024
Proforma of Agreement for saleFile: PROFOMA AGREEMENT.pdf5 Apr 2024
Proforma of Allotment letterFile: PROFOMA OF ALLOTMENT.pdf5 Apr 2024
Layout approvalFile: HPSC0221_compressed.pdf29 Mar 2024
Building plan approvalFile: HPSC0221_compressed.pdf29 Mar 2024
Copy of Layout Approval (in case of layout)File: HPSC0221_compressed.pdf29 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC0221_compressed.pdf29 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: SKM_C250i24010313480_rotated_compressed.pdf29 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: annexure A.pdf29 Mar 2024
Deviation Report with respect to Allotment letterFile: Allotment letter.pdf29 Mar 2024
Deviation Report with respect to model copy of AgreementFile: agreement for sale.pdf29 Mar 2024
PAN CardFile: pan card hrk.pdf23 Feb 2024

How this compares with Pune

39%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 19 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DHRUPI TOWERS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHAROLI (BK)13,700+ in Pune

2 kmDHRUPI TOWERSCompleted 19Lapsed / revoked 13Other 54Dot size: filed unitsN

Filed coordinates, straight-line distance. 86 registered projects within 2 km.

Builder: HRITIK NITIN JAIN

HRITIK NITIN JAIN has 1 registration on MahaRERA, including DHRUPI TOWERS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that DHRUPI TOWERS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if DHRUPI TOWERS is delayed beyond 31 Jul 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DHRUPI TOWERS?

The registered promoter entity is HRITIK NITIN JAIN, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DHRUPI TOWERS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DHRUPI TOWERS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DHRUPI TOWERS?

The professionals named in the filing: Architect: RAJENDRA LONDE; Architect: VIRENDRA SANJAY OSWAL; Engineer: infinity consultant; Chartered Accountant: OSWAL AND HEDA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DHRUPI TOWERS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DHRUPI TOWERS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DHRUPI TOWERS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.