Home / Browse projects / Pune, Maharashtra / Destination Mangalam Marvel
Destination Mangalam Marvel
RG-MH-99934 · RERA P52100055285 · Last updated on MahaRERA portal: 30 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Destination Mangalam Marvel is a Residential / Group Housing project by D R GAVHANE LEGACY in Pune, Maharashtra, registered with MahaRERA as P52100055285 on 14 Mar 2024. Possession is promised by 31 Dec 2027. 369 of the 561 units on this registration are recorded sold or booked, and 17 of 55 construction stages are filed complete.
At a glance
Project
- NameDestination Mangalam Marvel
- TypeResidential / Group Housing
- Location
- Charholi Wadmukhwadi road
- Charholi
- Haveli
- Pune
- 412105
- Pincode412105
- RERA no.P52100055285
- ReraGenie IDRG-MH-99934
Builder
- NameD R GAVHANE LEGACY
- Entity typePartnership
- PartnersAjit Damodar Gavhane designated partner of D R Gavhane Landmarks LLP, Dhananjay Vitthal Kalbhor designated partners of Kalbhor Realtors and Services LLP, Ramdas Damodar Phuge designated partner of Mangalam Landmarks LLP, Sagar Suresh Sakore, Vinod Chhotelal Dhusia
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on14 Mar 2024
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings5 building records
- Documents filed259 files
Current status
Figures as on 30 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A | NA | 16 | 14 | 110 | 0 | 110 |
| Building B | NA | 16 | 14 | 152 | 0 | 152 |
| Building C | NA | 16 | 14 | 152 | 0 | 152 |
| Building D | NA | 3 | 3 | 110 | 0 | 110 |
| Building E | NA | 9 | 7 | 37 | 0 | 37 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 30 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
17 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Slabs of Super Structure, at 85%.
Building A59%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 76% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building B55%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 85% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 55% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 66% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building C43%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 55% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 22% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building D42%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 60% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building E0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 30 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 55% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed259
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Building A | 21 | 6 | 27 |
| Building B | 35 | 0 | 35 |
| Building C | 152 | 0 | 152 |
| Building D | 21 | 0 | 21 |
| Building E | 24 | 0 | 24 |
Land and ownership26
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Ganesh Janardan Kalaje | CHARHOLI | Pune |
| Vimal Arjun Kalaje | CHARHOLI | Pune |
| Indumati Ramesh Kalaje | CHARHOLI | Pune |
| Umakant Ramesh Kalaje | CHARHOLI | Pune |
| Jayashree Umakant Kalaje | CHARHOLI | Pune |
| Shrikant Ramesh Kalaje | CHARHOLI | Pune |
| Pooja Sachin Parage | CHARHOLI | Pune |
| Dinkar Arjun Kalaje | CHARHOLI | Pune |
| Manisha Dinkar Kalaje | CHARHOLI | Pune |
| Tejas Dinkar Kalaje | CHARHOLI | Pune |
| Tripti Dinkar Kalaje | CHARHOLI | Pune |
| Nikhil Shankar Kalaje | CHARHOLI | Pune |
| Sunita Ram Jagtap | CHARHOLI | Pune |
| Subhash Bapu Kalaje | CHARHOLI | Pune |
| Ashwini Subhash Kalaje | CHARHOLI | Pune |
| Yogita Subhash Kalaje | CHARHOLI | Pune |
| Saurabh Subhash Kalaje | CHARHOLI | Pune |
| Neerabai Urf Meerabai Manik Kalaje | CHARHOLI | Pune |
| Santosh Manik Kalaje | CHARHOLI | Pune |
| Chitra Santosh Kalaje | CHARHOLI | Pune |
| Pooja Santosh Kalaje | CHARHOLI | Pune |
| Sakshi Santosh Kalaje | CHARHOLI | Pune |
| Rudra Santosh Kalaje | CHARHOLI | Pune |
| Jayashree Subhash Bahirat | CHARHOLI | Pune |
| Ramesh Arjun Kalaje | CHARHOLI | Pune |
| Sarthak Subhash Kalaje | CHARHOLI | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building C | NA | Rs 35.54 cr | Rs 8.19 cr |
| Building B | NA | Rs 34.64 cr | Rs 17.49 cr |
| Building A | NA | Rs 26.55 cr | Rs 18.69 cr |
| Building D | NA | Rs 26.55 cr | Rs 5.64 cr |
| - | NA | Rs 11.72 cr | Rs 2.64 cr |
| Building E | NA | Rs 5.08 cr | - |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Arise Architects & Interior Designers |
| Architect | Vilas J Yele |
| Engineer | Vaibhav Gaikwad |
| Chartered Accountant | Parag S Savale & Associates |
| Partner | Role in project |
|---|---|
| D R GAVHANE LEGACY | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 Mar 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Jan 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Jan 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Jan 2026Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed259
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 259 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Marvel upto march 2026.pdf | 30 May 2026 |
| Withdrawal Update Form 1File: Form 1 Marvel upto march 2025.pdf | 30 May 2026 |
| Withdrawal Update Form 1File: Form 1 Marvel upto march 2025.pdf | 30 May 2026 |
| Withdrawal Update Form 2File: Form 2 Marvel upto March 2026.pdf | 30 May 2026 |
| Withdrawal Update Form 2File: Form 2 Marvel upto March 2026.pdf | 30 May 2026 |
| Withdrawal Update Form 2File: Form 2 Marvel upto March 2026.pdf | 30 May 2026 |
| Withdrawal Update Form 3File: Form 3 Marvel upto March 2026.pdf | 30 May 2026 |
| Withdrawal Update Form 3File: Form 3 Marvel upto March 2026.pdf | 30 May 2026 |
| Withdrawal Update Form 3File: Form 3 Marvel upto March 2026.pdf | 30 May 2026 |
| Withdrawal Update Form 1File: Form 1 Marvel upto march 2026.pdf | 21 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 Marvel upto March 2026.pdf | 21 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 Marvel upto March 2026.pdf | 21 Apr 2026 |
| Layout approvalFile: LAYOUT 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 2 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 3 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 4 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 5 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 6 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 7 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 8 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 9 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 10 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 11 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 12 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 13 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 14 30925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 15 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 16 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 17 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 18 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 19 30925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 20 30925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 21 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 22 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 23 030925.pdf | 24 Jan 2026 |
| Building plan approvalFile: 24 030925.pdf | 24 Jan 2026 |
| Commencement certificateFile: CC 030925.pdf | 24 Jan 2026 |
| Withdrawal Update Form 1File: Marvel Form 1 upto 31122025.pdf | 24 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Marvel upto Dec 2025.pdf | 24 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 Marvel upto dec 2025.pdf | 24 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5 2024to25 DR Gavhane Legacy.pdf | 19 Jan 2026 |
| Form 5 (FY 2023-2024)File: Form 5 2023 - 2024 d r gavhane 200924001.pdf | 17 Jan 2026 |
| Withdrawal Update Form 1File: Marvel Arch Cert Sep 2025_0001.pdf | 14 Nov 2025 |
| Withdrawal Update Form 2File: Destination Marvel Form 2 Sep 2025 -download (1) (1).pdf | 14 Nov 2025 |
| Withdrawal Update Form 3File: Destination Sept From 3.pdf | 14 Nov 2025 |
| Layout approvalFile: LAYOUT.pdf | 11 Oct 2025 |
| Building plan approvalFile: 2.pdf | 11 Oct 2025 |
| Building plan approvalFile: 3.pdf | 11 Oct 2025 |
| Building plan approvalFile: 4.pdf | 11 Oct 2025 |
| Building plan approvalFile: 5.pdf | 11 Oct 2025 |
| Building plan approvalFile: 6.pdf | 11 Oct 2025 |
| Building plan approvalFile: 7.pdf | 11 Oct 2025 |
| Building plan approvalFile: 8.pdf | 11 Oct 2025 |
| Building plan approvalFile: 9.pdf | 11 Oct 2025 |
| Building plan approvalFile: 10.pdf | 11 Oct 2025 |
| Building plan approvalFile: 11.pdf | 11 Oct 2025 |
| Building plan approvalFile: 12.pdf | 11 Oct 2025 |
| Building plan approvalFile: 13.pdf | 11 Oct 2025 |
| Building plan approvalFile: 14.pdf | 11 Oct 2025 |
| Building plan approvalFile: 15.pdf | 11 Oct 2025 |
| Building plan approvalFile: 16.pdf | 11 Oct 2025 |
| Building plan approvalFile: 17.pdf | 11 Oct 2025 |
| Building plan approvalFile: 18.pdf | 11 Oct 2025 |
| Building plan approvalFile: 19.pdf | 11 Oct 2025 |
| Building plan approvalFile: 20.pdf | 11 Oct 2025 |
| Building plan approvalFile: 21.pdf | 11 Oct 2025 |
| Building plan approvalFile: 22.pdf | 11 Oct 2025 |
| Building plan approvalFile: 23.pdf | 11 Oct 2025 |
| Building plan approvalFile: 24.pdf | 11 Oct 2025 |
| Form 1File: Form 1 Arc cert june 25.pdf | 19 Jul 2025 |
| Form 2File: Form 2 Engineer cert.pdf | 19 Jul 2025 |
| Form 3File: Form 3 CA cert June 25.pdf | 19 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold unsold Inventory June 25.pdf | 19 Jul 2025 |
| Form 1File: Destination Arch Certificate upto Dec 2024.pdf | 26 Jun 2025 |
| Form 2File: Form 2 Dec 24 Engineers certificate Marvel.pdf | 26 Jun 2025 |
| Form 3File: DRG RERA form 3 Q3compressed.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Destination Disclosure of sold unsold inventory Upto 31Dec24_compressed.pdf | 26 Jun 2025 |
| Form 1File: Marvel Form1 Sept 2024.pdf | 26 Jun 2025 |
| Form 3File: Sept 2024 Form 3 CA Certificate.pdf | 26 Jun 2025 |
| Form 2File: scan Sept 24 Form 2 Engineers certificate Mangalam Destination.pdf | 26 Jun 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- All 259 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Destination Mangalam Marvel on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Charholi13,700+ in Pune
TANISH PARK
TANISH DEVELOPERS
Ajinkya Towers
APAK Bussiness Innovation Pvt Ltd
SILVER GARDENIA
SILVER PROMOTERS AND DEVELOPERS
Mangalam Life Park
Mangalam Buildcorp
SingaPune Ph 3
Xrbia Mirth Properties LLP
SingaPune Ph 2
Xrbia Mirth Properties LLP
Builder: D R GAVHANE LEGACY
D R GAVHANE LEGACY has 1 registration on MahaRERA, including Destination Mangalam Marvel. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Destination Mangalam Marvel is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Destination Mangalam Marvel?
The registered promoter entity is D R GAVHANE LEGACY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Destination Mangalam Marvel?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Destination Mangalam Marvel?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Destination Mangalam Marvel?
The professionals named in the filing: Architect: Arise Architects & Interior Designers; Architect: Vilas J Yele; Engineer: Vaibhav Gaikwad; Chartered Accountant: Parag S Savale & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Destination Mangalam Marvel?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback