Home / Browse projects / Pune, Maharashtra / DB Commercial Phase II
DB Commercial Phase II
By Pune Buildtech Private Limited
RG-MH-12032 · RERA P52100003455 · Last updated on MahaRERA portal: 17 Oct 2023
Source: official MahaRERA filing
Red flags
- De-registered
- Possession 58 months past the filed date
- 2 complaints at MahaRERA
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DB Commercial Phase II is a Commercial project by Pune Buildtech Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100003455 on 5 Aug 2017. Possession was promised by 30 Dec 2021 and is now 58 months past that date. The completion date has moved by 24 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- NameDB Commercial Phase II
- TypeCommercial
- Location
- Plot 3B C
- Yerawada
- Pune (M Corp.)
- Pune City
- Pune
- 411006
- Pincode411006
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100003455
- ReraGenie IDRG-MH-12032
Builder
- NamePune Buildtech Private Limited
- Entity typeCompany
- CINU45201MH2006PTC164356
- GSTIN27AACCD4372R1Z3
- Other registrations1 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusDe-registered
- Registered on5 Aug 2017
- Promised completion30 Dec 2021
- Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
- Buildings1 building record
- Documents filed68 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| DB Commercial | NA | 23 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 17 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 50%.
DB Commercial: 61% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 10% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 10% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities16
As on 17 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 10% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 10% |
| Storm Water Drains | Yes | 10% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 10% |
| Solid Waste Management And Disposal | Yes | 10% |
| Water conservation /Rain water harvesting | Yes | 15% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 10% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
| Other Facilities | Yes | 0% |
Parking filed311
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Prakash Kulkarni |
| Architect | Ankur Associates |
| Engineer | Jagdish Kadu |
| Chartered Accountant | B B Jain & Associates |
| Chartered Accountant | HIMANK DESAI |
| Partner | Role in project |
|---|---|
| Pune Buildtech Private Limited | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter(a) NBFC Crisis: The NBFC crisis has been a tip of the iceberg of the ongoing headwinds faced by the real estate industry with the slower receivable cycles and further stretched unreasonably causing developers to face the escalated heat of liquidity crisis on one side and managing delivery pressure under RERA on another side. However, the Developer with a sincere intent to deliver the project as committed, kept trying to arrange funds and tackle all the other hurdles. Looking at the recent market situation and NBFC crisis the Developer has time and again failed to arrange funds from the financ
Litigation declared1
| Case | Court | Status |
|---|---|---|
| L 949 of 2016/2016 | Debt Recovery Tribunal | Matter Pending |
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000023069 | Prixhusp Contractor | Pune Buildtech Private Limited | 24/05/2019 |
| CC005000000177890 | Anjana Bansilal Thakkar | classic promoter and builders pvt. ltd | 04/12/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed68
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Mar 2022 Phase II form 2.pdf | 17 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Jun 2022 Phase II form 2.pdf | 17 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sep 2022 Phase II form 2.pdf | 17 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Dec 2022 Phase II form 2.pdf | 17 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Mar 2023 Phase II form 2.pdf | 17 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Jun 2023 Phase II form 2.pdf | 17 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: DB Comm - Form 2 Phase 2 - Sept 20.pdf | 13 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: DB Comm - Form 2 Phase 2 Dec 20.pdf | 13 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: DB Comm - Form 2 Phase 2 Mar 21.pdf | 13 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: DB Comm - Form 2 Phase 2 Jun 21.pdf | 13 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: DB Comm - Form 2 Phase 2 - Sept 21.pdf | 13 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: DB Comm - Form 2 Phase 2 Dec 21.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Form-3 DB Commercial Ph II 30062020.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Sept 2020 Phase II form 3.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Dec 2020 Phase II From 3.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Mar 2021 Phase II form 3.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Jun 2021 Phase II Form 3.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Sept 2021 Phase II Form 3.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Dec 2021 Phase II Form 3.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Mar 2022 Phase II form 3.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Jun 2022 Phase II form 3.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Sept 2022 Phase II form 3.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Dec 2022 Phase II form 3.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Mar 2023 Phase II form 3.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Jun 2023 Phase II form 3.pdf | 13 Oct 2023 |
| Certificates of CA (Form 5)File: PBPL_FORM 5 DB COMMERCIAL PHASE II.pdf | 30 Sep 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ankur Associates_20210121153606.pdf | 28 Jan 2021 |
| Certificates of CA (Form 3)File: DB Commercial-Ph II revised.pdf | 6 Oct 2020 |
| Certificates of CA (Form 5)File: DB Commercial Form 5 phase 2.pdf | 30 Sep 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 DB Commercial Phase II March Qtr.pdf | 4 Sep 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 DB Commercial Phase II June Qtr.pdf | 4 Sep 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: DB Commercial Form 2 Phase 2.pdf | 31 Dec 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 DB Commercial phase II.pdf | 31 Dec 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: DB Commercial Form 2 Phase 2.pdf | 31 Dec 2019 |
| Certificates of CA (Form 3)File: Pune Project DB Commerical Form 3 Phase II.pdf | 31 Dec 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate - DB Commercial Ph -2.pdf | 6 Nov 2019 |
| Certificates of CA (Form 3)File: Form-3_DB Commercial_Ph II.pdf | 29 Oct 2019 |
| Certificates of CA (Form 5)File: DB Commercial_Phase II.pdf | 30 Sep 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert P2 March 19.pdf | 29 Jul 2019 |
| Form 2AFile: Form 2A P2 March 19.pdf | 29 Jul 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q6 (Dec18) Form1 - DB Commercial Ph 2.pdf | 15 Apr 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q6 (Dec18) Form2 - DB Commercial Ph 2.pdf | 15 Apr 2019 |
| Certificates of CA (Form 3)File: Q6 (Dec18) Form3 - DB Commercial Ph 2.pdf | 15 Apr 2019 |
| Certificates of CA (Form 5)File: Form 5 (Aug17 - Mar18) DB Comm Ph2.pdf | 30 Sep 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q1 (Sep17) Form 2 - DB Comm Ph-2.pdf | 23 Feb 2018 |
| Layout approvalFile: Layout Approval.pdf | 29 Jul 2017 |
| Building plan approvalFile: Building Plan Approval pt1.pdf | 29 Jul 2017 |
| Building plan approvalFile: Building Plan Approval pt3.pdf | 29 Jul 2017 |
| Building plan approvalFile: Building Plan Approval pt4.pdf | 29 Jul 2017 |
| Building plan approvalFile: Building Plan Approval pt2.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Layout Approval.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: Building Plan Approval pt1.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: Building Plan Approval pt2.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: Building Plan Approval pt3.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: Building Plan Approval pt4.pdf | 29 Jul 2017 |
| Declaration in FORM BFile: DB Commercial phase 2 form B.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architects Certificate PHASE 2.pdf | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: DB Commercial Pune Form-2 Engineers Certificate 2nd Phase.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: DB Commercial Form-3 CAs Certificate Phase 2-Pt(1).pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: DB Commercial Form-3 CAs Certificate Phase 2-Pt(2).pdf | 29 Jul 2017 |
| Proforma of Allotment letterFile: Proforma of the Allotment Letter and AFS.pdf | 29 Jul 2017 |
| PAN CardFile: PAN Card IB.pdf | 28 Jul 2017 |
| PAN CardFile: PAN Card JK.pdf | 28 Jul 2017 |
| PAN CardFile: PAN Pune Buildtech.pdf | 28 Jul 2017 |
| Copy of the legal title reportFile: Legal Title Report.pdf | 28 Jul 2017 |
| Details of encumbrancesFile: Details of Encumbrances.pdf | 28 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate pt1.pdf | 28 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate pt2.pdf | 28 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 68 filed documents as one ZIP, foldered, with a manifest
Keep DB Commercial Phase II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Yerawada13,700+ in Pune
Filed coordinates, straight-line distance. 12 registered projects within 2 km.
VAISHNAVI OURANOS
VAISHNAVI & OM CONSTRUCTION
Nandanvan
NG Rathi Construction Private Limited
KALPANA CO OP HSG SOC LTD - PHASE 1
Bramhacorp Limited
UTTAM TOWNSCAPE LIFE HUB A,A1,B
FORTUNE DEVELOPERS AND INFRASTRUCTURES
VRUNDAVAN A WING
NG Rathi Promoters
White House A
CITY ETHERNAL LLP
Builder: Pune Buildtech Private Limited
Pune Buildtech Private Limited has 2 registrations on MahaRERA, including DB Commercial Phase I and DB Commercial Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that DB Commercial Phase II shows as de-registered on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if DB Commercial Phase II is delayed beyond 30 Dec 2021?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DB Commercial Phase II?
The registered promoter entity is Pune Buildtech Private Limited, a company as per the filing. Its CIN U45201MH2006PTC164356 and GSTIN 27AACCD4372R1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DB Commercial Phase II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against DB Commercial Phase II?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for DB Commercial Phase II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DB Commercial Phase II?
The professionals named in the filing: Architect: Prakash Kulkarni; Architect: Ankur Associates; Engineer: Jagdish Kadu; Chartered Accountant: B B Jain & Associates; Chartered Accountant: HIMANK DESAI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DB Commercial Phase II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback