Home / Browse projects / Thane, Maharashtra / DAISY GARDENS SURVEY NO 12 PHASE I

Registered No litigation declared Residential / Group Housing project

DAISY GARDENS SURVEY NO 12 PHASE I

By ANKITA BUILDERS

RG-MH-58283 · RERA P51700009528 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 78 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 78 months from the original
27 of 33Construction stages doneacross 3 buildings; furthest along: Sanitary Fittings within the flats /..., 96%
40 of 113Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 128 documents Report an error

DAISY GARDENS SURVEY NO 12 PHASE I is a Residential / Group Housing project by ANKITA BUILDERS in Thane, Maharashtra, registered with MahaRERA as P51700009528 on 22 Aug 2017. Possession is promised by 30 Jun 2027. The completion date has moved by 78 months from the original filing. 73 of the 113 units on this registration are recorded sold or booked, and 27 of 33 construction stages are filed complete.

At a glance

Project

  • NameDAISY GARDENS SURVEY NO 12 PHASE I
  • TypeResidential / Group Housing
  • Location
    • KAMLAKAR NAGAR
    • KHOJ GAON
    • Ambarnath(M Cl)
    • Ambarnath
    • Thane
    • 421505
  • Pincode421505
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700009528
  • ReraGenie IDRG-MH-58283

Builder

  • NameANKITA BUILDERS
  • Entity typePartnership
  • GSTIN27AARFA2290D1ZH
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnerJAYA PRAKASH WADHWA
  • Other registrations3 more →
  • Completed1 of 4
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredAug 2017First promiseDec 2020Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Aug 2017
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Dec 2020)
  • Buildings3 building records
  • Documents filed128 files

Current status

65%73 of 113 units booked
100.0%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 10NA9737037
BUILDING NO 11NA9738038
BUILDING NO 12NA9738038

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 96%.

BUILDING NO 1090%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises96%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.93%
BUILDING NO 1190%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.93%
BUILDING NO 1291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes85%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes92%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes92%
Solid Waste Management And DisposalYes95%
Water conservation /Rain water harvestingYes93%
Energy managemcntYes90%
Fire protection and fire safety requirementsYes88%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes85%
Open ParkingYes100%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,000 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityAMBERNATH MUNICIPAL CORPORATION
Permissible FSI4498.92
Proposed, not sanctioned4,499 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKESWANI COMPLEX,GROUND AND 1ST FLOOR,NEAR CHOPRA COURT, ULHASNAGAR -421003
Estimated costRs 60.03 cr
Cost incurredRs 60.03 cr
Work done100.0%
BuildingWingEstimatedIncurred
-NARs 50.00 crRs 50.00 cr
BUILDING NO 10NARs 4.30 crRs 4.30 cr
BUILDING NO 11NARs 4.30 crRs 4.30 cr
BUILDING NO 12NARs 1.43 crRs 1.43 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVitan Consultants
EngineerDipesh Bare
EngineerPromod Kambke
Chartered AccountantMukesh Gurnani
Chartered AccountantGAURAV VASANT WANI
Chartered AccountantSitaram Chandrakant Palav
PartnerRole in project
ANKITA BUILDERS-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700008726Dec 2020 → Dec 2021

Reason as filed by the promoterThe project is under construction. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID - 19 it is getting delayed. Hence we request you to grant us the revised date of completion as 30/12/2021 for our Project - “Daisy Gardens Survey No.12 Phase I” bearing Registration No. P51700009528.

EXT51700012029Dec 2020 → Jun 2023

Reason as filed by the promoterThe project is under construction. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID - 19 it is getting delayed. Hence we request you to grant us the revised date of completion as 30/06/2023 for our Project - “Daisy Gardens Survey No.12 Phase I” bearing Registration No. P51700009528.

EXT51700024091Dec 2020 → Jun 2026

Reason as filed by the promoterThe project is completed in all aspects and we had applied for Occupancy Certificate. However for the Purpose of RERA Compliances we have applied for extension of Project due to expiry of Project Validity under MahaRERA.

EXT51700016783Dec 2020 → Jun 2024

Reason as filed by the promoterThe project is under construction & we have completed almost work on the project. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID - 19 it is getting delayed.

EA24062621493Dec 2020 → Jun 2027

Reason as filed by the promoter1) Slow booking response from customer. 2) Because of slow down in booking response, we have work/act accordingly in above said building. But at present, we have completed our 95% Project & pending for necessary permission from various concern Authorities for obtaining Completion Certificate from Ambernath Muncipal Council, Ambernath.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Feb 2025

Documents filed128

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 128 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 31122023 10,11,12_11zon.pdf20 Jul 2026
Withdrawal Update Form 1File: Form 1 bldg 1011 300626.pdf20 Jul 2026
Withdrawal Update Form 1File: Form 1 bldg 1011 300626.pdf20 Jul 2026
Withdrawal Update Form 2File: Form 2 Bldg no1011 300626.pdf20 Jul 2026
Withdrawal Update Form 2File: Form 2 Bldg no1011 300626.pdf20 Jul 2026
Withdrawal Update Form 2File: Form 2 Bldg no1011 300626.pdf20 Jul 2026
Withdrawal Update Form 3File: Form 3 31032026.pdf20 Jul 2026
Withdrawal Update Form 3File: Form 3 Bldg 1011 300626.pdf20 Jul 2026
Withdrawal Update Form 3File: Form 3 Bldg 1011 300626.pdf20 Jul 2026
Form 2A (FY 2024-2025)File: Form 2A 2024-2025.pdf30 Jun 2026
Form 2A (FY 2025-2026)File: Form 2A 2025-2026.pdf30 Jun 2026
Form 5 (FY 2024-2025)File: Form 5 2024-25.pdf25 Jun 2026
Withdrawal Update Form 1File: Form 1 31122023 10,11,12_11zon.pdf23 Jun 2026
Withdrawal Update Form 2File: Form 2 31032026.pdf23 Jun 2026
Withdrawal Update Form 3File: Form 3 31032026.pdf23 Jun 2026
Form 1File: Form 1 30092025.pdf4 May 2026
Form 2File: Form 2 30092025.pdf4 May 2026
Form 3File: Form 3 Bldg No1011 Sep25.pdf4 May 2026
Disclosure of Sold and Booked InventoryFile: Sols unsold 300925.pdf4 May 2026
Form 1File: Form 1 311225.pdf4 May 2026
Form 2File: Form 2 31122025.pdf4 May 2026
Form 3File: Form 3 bldg no1011 Dec25.pdf4 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold 311225.pdf4 May 2026
Form 1File: Form 1 300624.pdf4 May 2026
Form 2File: Form 2 300624.pdf4 May 2026
Form 3File: Form 3 300624compressed.pdf4 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold 300624.pdf4 May 2026
Form 1File: Form 1 300924.pdf4 May 2026
Form 2File: Form 2 300924.pdf4 May 2026
Form 3File: Form 3 300924compressed.pdf4 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold 300924.pdf4 May 2026
Form 1File: Form 1 311224.pdf4 May 2026
Form 2File: Form 2 311224.pdf4 May 2026
Form 3File: Form 3 311224compressed.pdf4 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold 311224.pdf4 May 2026
Form 1File: Form 1 310325.pdf4 May 2026
Form 2File: Form 2 310325.pdf4 May 2026
Form 3File: Form 3 310325compressed.pdf4 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold 310325.pdf4 May 2026
Form 1File: Form 1 30062025.pdf2 May 2026
Form 2File: Form 1 30062025.pdf2 May 2026
Form 3File: Form 3 Bldg No1011 Jun25.pdf2 May 2026
Disclosure of Sold and Booked InventoryFile: SOld Unsold Stock 3006.pdf2 May 2026
Form 1File: Form 1 28072017.pdf10 Mar 2026
Form 2File: Form 2 19072017 (2).pdf10 Mar 2026
Form 3File: Form 3 31072017 (2).pdf10 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold unsold inventory 101112 31072017.pdf10 Mar 2026
Form 1File: Form 1 30062023.pdf10 Mar 2026
Form 2File: Form 2 30062023.pdf10 Mar 2026
Form 3File: Form 3 30062023.pdf10 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf10 Mar 2026
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 4 FORM.pdf23 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5.pdf21 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 form.pdf19 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 form.pdf19 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM.pdf19 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM.pdf19 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 FORM.pdf19 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 FORM.pdf19 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 FORM.pdf19 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf19 Feb 2025
Declaration in FORM BFile: Form B.pdf21 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf21 Jun 2024
Disclosure of sold/ booked inventoryFile: sold inventory bldg 10.pdf21 Jun 2024
Disclosure of sold/ booked inventoryFile: sold inventory bldg 11.pdf21 Jun 2024
Disclosure of sold/ booked inventoryFile: sold inventory bldg 12pdf.pdf21 Jun 2024
Certificates of CA (Form 3)File: Form 3 S No 11 03052024.pdf9 May 2024
Certificates of CA (Form 3)File: Form 3 S No 12 Phase I 03052024.pdf9 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31032023 10,11,12_11zon.pdf27 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 30062023 10,11,12_11zon.pdf27 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 30092023 10,11,12_11zon.pdf27 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31122023 10,11,12_11zon.pdf27 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31032023.pdf27 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 30062023.pdf27 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 30092023.pdf27 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31122023.pdf27 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31032024_11zon.pdf27 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 31032023.pdf27 Apr 2024
Certificates of CA (Form 3)File: Form 3 S No 12 Phase I 31032023_11zon.pdf27 Apr 2024
Certificates of CA (Form 3)File: Form 3 S No 12 Phase I 30062023_11zon.pdf27 Apr 2024

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Daisy Gardens Building No.13P51700052891Khoj-Khuntavli, Ambernath, Thane8Oct 2023Certificate SignedJun 2026Not delivered
DAISY GARDENS SURVEY NO 11P51700005390KHOJGAON, Thane85Aug 2017Certificate SignedJun 2026Registered original: Dec 2020Not delivered
DAISY GARDENSSURVEY NO 12 BY 12 15 BY 7 12 BY 3 CTS 33 BY 1058-CompletedDec 2015Jan 2015

How this compares with Thane

65%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 78 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DAISY GARDENS SURVEY NO 12 PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KHOJ GAON7,600+ in Thane

2 kmDAISY GARDENS SURVEY NO Completed 23Lapsed / revoked 5Other 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 38 registered projects within 2 km.

Builder: ANKITA BUILDERS

ANKITA BUILDERS has 4 registrations on MahaRERA, including DAISY GARDENS SURVEY NO 11 and DAISY GARDENS SURVEY NO 12 PHASE I. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if DAISY GARDENS SURVEY NO 12 PHASE I is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DAISY GARDENS SURVEY NO 12 PHASE I?

The registered promoter entity is ANKITA BUILDERS, a partnership as per the filing. Its GSTIN 27AARFA2290D1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DAISY GARDENS SURVEY NO 12 PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DAISY GARDENS SURVEY NO 12 PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DAISY GARDENS SURVEY NO 12 PHASE I?

The professionals named in the filing: Architect: Vitan Consultants; Engineer: Dipesh Bare; Engineer: Promod Kambke; Chartered Accountant: Mukesh Gurnani; Chartered Accountant: GAURAV VASANT WANI; Chartered Accountant: Sitaram Chandrakant Palav. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DAISY GARDENS SURVEY NO 12 PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DAISY GARDENS SURVEY NO 12 PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DAISY GARDENS SURVEY NO 12 PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.