Home / Browse projects / Thane, Maharashtra / DAISY GARDENS SURVEY NO 12 PHASE I
DAISY GARDENS SURVEY NO 12 PHASE I
RG-MH-58283 · RERA P51700009528 · Last updated on MahaRERA portal: 20 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 78 months
- 5 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DAISY GARDENS SURVEY NO 12 PHASE I is a Residential / Group Housing project by ANKITA BUILDERS in Thane, Maharashtra, registered with MahaRERA as P51700009528 on 22 Aug 2017. Possession is promised by 30 Jun 2027. The completion date has moved by 78 months from the original filing. 73 of the 113 units on this registration are recorded sold or booked, and 27 of 33 construction stages are filed complete.
At a glance
Project
- NameDAISY GARDENS SURVEY NO 12 PHASE I
- TypeResidential / Group Housing
- Location
- KAMLAKAR NAGAR
- KHOJ GAON
- Ambarnath(M Cl)
- Ambarnath
- Thane
- 421505
- Pincode421505
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700009528
- ReraGenie IDRG-MH-58283
Builder
- NameANKITA BUILDERS
- Entity typePartnership
- GSTIN27AARFA2290D1ZH
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnerJAYA PRAKASH WADHWA
- Other registrations3 more →
- Completed1 of 4
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects4 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on22 Aug 2017
- Promised completion30 Jun 2027
- Revised completionRevised to 30 Jun 2027 (originally 30 Dec 2020)
- Buildings3 building records
- Documents filed128 files
Current status
Figures as on 20 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING NO 10 | NA | 9 | 7 | 37 | 0 | 37 |
| BUILDING NO 11 | NA | 9 | 7 | 38 | 0 | 38 |
| BUILDING NO 12 | NA | 9 | 7 | 38 | 0 | 38 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
27 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 96%.
BUILDING NO 1090%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 96% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 93% |
BUILDING NO 1190%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 93% |
BUILDING NO 1291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 85% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 92% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 92% |
| Solid Waste Management And Disposal | Yes | 95% |
| Water conservation /Rain water harvesting | Yes | 93% |
| Energy managemcnt | Yes | 90% |
| Fire protection and fire safety requirements | Yes | 88% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | Yes | 85% |
| Open Parking | Yes | 100% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 50.00 cr | Rs 50.00 cr |
| BUILDING NO 10 | NA | Rs 4.30 cr | Rs 4.30 cr |
| BUILDING NO 11 | NA | Rs 4.30 cr | Rs 4.30 cr |
| BUILDING NO 12 | NA | Rs 1.43 cr | Rs 1.43 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vitan Consultants |
| Engineer | Dipesh Bare |
| Engineer | Promod Kambke |
| Chartered Accountant | Mukesh Gurnani |
| Chartered Accountant | GAURAV VASANT WANI |
| Chartered Accountant | Sitaram Chandrakant Palav |
| Partner | Role in project |
|---|---|
| ANKITA BUILDERS | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project is under construction. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID - 19 it is getting delayed. Hence we request you to grant us the revised date of completion as 30/12/2021 for our Project - “Daisy Gardens Survey No.12 Phase I” bearing Registration No. P51700009528.
Reason as filed by the promoterThe project is under construction. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID - 19 it is getting delayed. Hence we request you to grant us the revised date of completion as 30/06/2023 for our Project - “Daisy Gardens Survey No.12 Phase I” bearing Registration No. P51700009528.
Reason as filed by the promoterThe project is completed in all aspects and we had applied for Occupancy Certificate. However for the Purpose of RERA Compliances we have applied for extension of Project due to expiry of Project Validity under MahaRERA.
Reason as filed by the promoterThe project is under construction & we have completed almost work on the project. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID - 19 it is getting delayed.
Reason as filed by the promoter1) Slow booking response from customer. 2) Because of slow down in booking response, we have work/act accordingly in above said building. But at present, we have completed our 95% Project & pending for necessary permission from various concern Authorities for obtaining Completion Certificate from Ambernath Muncipal Council, Ambernath.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 23 Feb 2025
Documents filed128
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 128 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 31122023 10,11,12_11zon.pdf | 20 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 bldg 1011 300626.pdf | 20 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 bldg 1011 300626.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Bldg no1011 300626.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Bldg no1011 300626.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Bldg no1011 300626.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 31032026.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 Bldg 1011 300626.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 Bldg 1011 300626.pdf | 20 Jul 2026 |
| Form 2A (FY 2024-2025)File: Form 2A 2024-2025.pdf | 30 Jun 2026 |
| Form 2A (FY 2025-2026)File: Form 2A 2025-2026.pdf | 30 Jun 2026 |
| Form 5 (FY 2024-2025)File: Form 5 2024-25.pdf | 25 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 31122023 10,11,12_11zon.pdf | 23 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 31032026.pdf | 23 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 31032026.pdf | 23 Jun 2026 |
| Form 1File: Form 1 30092025.pdf | 4 May 2026 |
| Form 2File: Form 2 30092025.pdf | 4 May 2026 |
| Form 3File: Form 3 Bldg No1011 Sep25.pdf | 4 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sols unsold 300925.pdf | 4 May 2026 |
| Form 1File: Form 1 311225.pdf | 4 May 2026 |
| Form 2File: Form 2 31122025.pdf | 4 May 2026 |
| Form 3File: Form 3 bldg no1011 Dec25.pdf | 4 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 311225.pdf | 4 May 2026 |
| Form 1File: Form 1 300624.pdf | 4 May 2026 |
| Form 2File: Form 2 300624.pdf | 4 May 2026 |
| Form 3File: Form 3 300624compressed.pdf | 4 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 300624.pdf | 4 May 2026 |
| Form 1File: Form 1 300924.pdf | 4 May 2026 |
| Form 2File: Form 2 300924.pdf | 4 May 2026 |
| Form 3File: Form 3 300924compressed.pdf | 4 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 300924.pdf | 4 May 2026 |
| Form 1File: Form 1 311224.pdf | 4 May 2026 |
| Form 2File: Form 2 311224.pdf | 4 May 2026 |
| Form 3File: Form 3 311224compressed.pdf | 4 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 311224.pdf | 4 May 2026 |
| Form 1File: Form 1 310325.pdf | 4 May 2026 |
| Form 2File: Form 2 310325.pdf | 4 May 2026 |
| Form 3File: Form 3 310325compressed.pdf | 4 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 310325.pdf | 4 May 2026 |
| Form 1File: Form 1 30062025.pdf | 2 May 2026 |
| Form 2File: Form 1 30062025.pdf | 2 May 2026 |
| Form 3File: Form 3 Bldg No1011 Jun25.pdf | 2 May 2026 |
| Disclosure of Sold and Booked InventoryFile: SOld Unsold Stock 3006.pdf | 2 May 2026 |
| Form 1File: Form 1 28072017.pdf | 10 Mar 2026 |
| Form 2File: Form 2 19072017 (2).pdf | 10 Mar 2026 |
| Form 3File: Form 3 31072017 (2).pdf | 10 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold inventory 101112 31072017.pdf | 10 Mar 2026 |
| Form 1File: Form 1 30062023.pdf | 10 Mar 2026 |
| Form 2File: Form 2 30062023.pdf | 10 Mar 2026 |
| Form 3File: Form 3 30062023.pdf | 10 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf | 10 Mar 2026 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 4 FORM.pdf | 23 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5.pdf | 21 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 form.pdf | 19 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 form.pdf | 19 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM.pdf | 19 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM.pdf | 19 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 FORM.pdf | 19 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 FORM.pdf | 19 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 FORM.pdf | 19 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf | 19 Feb 2025 |
| Declaration in FORM BFile: Form B.pdf | 21 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 21 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: sold inventory bldg 10.pdf | 21 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: sold inventory bldg 11.pdf | 21 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: sold inventory bldg 12pdf.pdf | 21 Jun 2024 |
| Certificates of CA (Form 3)File: Form 3 S No 11 03052024.pdf | 9 May 2024 |
| Certificates of CA (Form 3)File: Form 3 S No 12 Phase I 03052024.pdf | 9 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31032023 10,11,12_11zon.pdf | 27 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 30062023 10,11,12_11zon.pdf | 27 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 30092023 10,11,12_11zon.pdf | 27 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31122023 10,11,12_11zon.pdf | 27 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31032023.pdf | 27 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 30062023.pdf | 27 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 30092023.pdf | 27 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31122023.pdf | 27 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31032024_11zon.pdf | 27 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 31032023.pdf | 27 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 S No 12 Phase I 31032023_11zon.pdf | 27 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 S No 12 Phase I 30062023_11zon.pdf | 27 Apr 2024 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Daisy Gardens Building No.13P51700052891 | Khoj-Khuntavli, Ambernath, Thane | 8 | Oct 2023 | Certificate Signed | Jun 2026 | Not delivered |
| DAISY GARDENS SURVEY NO 11P51700005390 | KHOJGAON, Thane | 85 | Aug 2017 | Certificate Signed | Jun 2026Registered original: Dec 2020 | Not delivered |
| DAISY GARDENS | SURVEY NO 12 BY 12 15 BY 7 12 BY 3 CTS 33 BY 10 | 58 | - | Completed | Dec 2015 | Jan 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 128 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep DAISY GARDENS SURVEY NO 12 PHASE I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KHOJ GAON7,600+ in Thane
Filed coordinates, straight-line distance. 38 registered projects within 2 km.
MATOSHREE NAGAR EXCELLENCY BLDG SAPPHIRE A AND
MATOSHREE SHELTERS (INDIA) PRIVATE LIMITED
NIDHI RESIDENCY
ADITYA YASH BUILDERS
MIDTOWN B AND C WING
SIDDHIVINAYAK GROUP NX
PATELS LEGACY
RAPID CORPORATION
PATELS ETERNITY
OMKAR INFRASTRUCTURE
Harishree Celestial-1
HARISHREE CREATIONS
See every Thane project, with the district possession charts
Builder: ANKITA BUILDERS
ANKITA BUILDERS has 4 registrations on MahaRERA, including DAISY GARDENS SURVEY NO 11 and DAISY GARDENS SURVEY NO 12 PHASE I. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if DAISY GARDENS SURVEY NO 12 PHASE I is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DAISY GARDENS SURVEY NO 12 PHASE I?
The registered promoter entity is ANKITA BUILDERS, a partnership as per the filing. Its GSTIN 27AARFA2290D1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DAISY GARDENS SURVEY NO 12 PHASE I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for DAISY GARDENS SURVEY NO 12 PHASE I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DAISY GARDENS SURVEY NO 12 PHASE I?
The professionals named in the filing: Architect: Vitan Consultants; Engineer: Dipesh Bare; Engineer: Promod Kambke; Chartered Accountant: Mukesh Gurnani; Chartered Accountant: GAURAV VASANT WANI; Chartered Accountant: Sitaram Chandrakant Palav. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DAISY GARDENS SURVEY NO 12 PHASE I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback