Home / Browse projects / Thane, Maharashtra / DAISY GARDENS SURVEY NO 11
DAISY GARDENS SURVEY NO 11
RG-MH-27237 · RERA P51700005390 · Last updated on MahaRERA portal: 23 Feb 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Completion date moved by 66 months
- 4 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DAISY GARDENS SURVEY NO 11 is a Residential / Group Housing project by ANKITA BUILDERS in Thane, Maharashtra, registered with MahaRERA as P51700005390 on 11 Aug 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 66 months from the original filing. 81 of the 85 units on this registration are recorded sold or booked, and 30 of 33 construction stages are filed complete.
At a glance
Project
- NameDAISY GARDENS SURVEY NO 11
- TypeResidential / Group Housing
- Location
- KAMLAKAR NAGAR
- KHOJGAON
- Ambarnath(M Cl)
- Ambarnath
- Thane
- 421505
- Pincode421505
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700005390
- ReraGenie IDRG-MH-27237
Builder
- NameANKITA BUILDERS
- Entity typePartnership
- GSTIN27AARFA2290D1ZH
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnerJAYA PRAKASH WADHWA
- Other registrations3 more →
- Completed1 of 4
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects4 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on11 Aug 2017
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 30 Dec 2020)
- Buildings3 building records
- Documents filed69 files
Current status
Figures as on 23 Feb 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING NO 1 | NA | 9 | 7 | 28 | 0 | 28 |
| BUILDING NO 2 | NA | 9 | 7 | 28 | 0 | 28 |
| BUILDING NO 3 | NA | 8 | 7 | 29 | 0 | 29 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 23 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
30 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.
BUILDING NO 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING NO 291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING NO 391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 23 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 100% |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VITAN CONSULTANTS |
| Engineer | PRAMOD KAMBLE |
| Engineer | MR C N DUSEJA |
| Chartered Accountant | Mukesh Gurnani |
| Partner | Role in project |
|---|---|
| ANKITA BUILDERS | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project is under construction. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID - 19 it is getting delayed. Hence we request you to grant us the revised date of completion as 30/12/2021 for our Project - “Daisy Gardens Survey No. 11 ” bearing Registration No. P51700005390.
Reason as filed by the promoterThe project is under construction. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID - 19 it is getting delayed. Hence we request you to grant us the revised date of completion as 30/06/2023 for our Project - “Daisy Gardens Survey No. 11 ” bearing Registration No. P51700005390.
Reason as filed by the promoterThe project is under construction & we have almost completed work on the project. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID - 19 it is getting delayed.
Reason as filed by the promoterThe project is completed in all aspects and also we had applied for Occupancy Certificate. However due to Change in Process of getting Occupancy Certificate i.e. Online Process has been started due to which delay in getting Occupancy Certificate. For the Purpose of RERA Compliances we are apply for Extension of Project due to Expiry of Project Validity on MahaRERA Portal.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 23 Feb 2025
Documents filed69
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 4 FORM.pdf | 23 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5.pdf | 21 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 11.pdf | 19 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1.pdf | 19 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 form.pdf | 19 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 form.pdf | 19 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 form.pdf | 19 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 form.pdf | 19 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 form.pdf | 19 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf | 19 Feb 2025 |
| Declaration in FORM BFile: Form B.pdf | 25 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 25 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure.pdf | 25 Jun 2024 |
| Certificates of CA (Form 3)File: Form 3 S No 11 03052024.pdf | 9 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31032023_11zon.pdf | 25 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 30062023_11zon.pdf | 25 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 30092023_11zon.pdf | 25 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31122023_11zon.pdf | 25 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31032024_11zon.pdf | 25 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31032023.pdf | 25 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 30062023_11zon.pdf | 25 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 30092023_11zon.pdf | 25 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31122023.pdf | 25 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 S No 11 31032023_11zon.pdf | 25 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 S No 11 30062023_11zon.pdf | 25 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 S No 11 30092023_11zon.pdf | 25 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 S No 11 31122023_11zon.pdf | 25 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 S No 11 31032024_11zon.pdf | 25 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Rera 5390.pdf | 26 Mar 2024 |
| Declaration in FORM BFile: Form B S NO 11_11zon.pdf | 14 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A S NO 11.pdf | 14 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: Sol Unsold Disclosure_11zon.pdf | 13 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1 2018_compressed.pdf | 25 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 2019_compressed.pdf | 25 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 2020_compressed.pdf | 25 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 2021_compressed.pdf | 25 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5 31032022_compressed.pdf | 25 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6 30062022_compressed.pdf | 25 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 7 30092022_compressed.pdf | 25 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 8 31122022_compressed.pdf | 25 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2022 S NO 11.pdf | 5 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 2018.pdf | 16 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 2019.pdf | 16 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 2020.pdf | 16 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 2021.pdf | 16 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 31122022.pdf | 16 Mar 2023 |
| Declaration about Commencement CertificateFile: Format D S No 11.pdf | 15 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 31 03 2020 S No 11.pdf | 15 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 31 03 2021 S No 11_compressed.pdf | 15 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: S NO 11 - Disclosure.pdf | 15 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - S No 11.pdf | 15 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: RERA NO 5390 18-19 S NO 11.pdf | 14 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA NO 5390 19-20 S NO 11.pdf | 14 Jun 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement Certificate compressed.pdf | 28 Jul 2021 |
| Certificates of CA (Form 5)File: ankita survey no 11.pdf | 17 Oct 2018 |
| Certificates of CA (Form 3)File: SURVEY NO 11.pdf | 31 Jul 2017 |
| Building plan approvalFile: Commencement Certificate S No 11.pdf | 30 Jul 2017 |
| Layout approvalFile: Layout Daisy Gardens Survey No 11.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: Legal Title.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Layout Daisy Gardens Survey No 11.pdf | 30 Jul 2017 |
| Building Plan Approval (IOD)File: Commencement Certificate S No 11.pdf | 30 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate S No 11.pdf | 30 Jul 2017 |
| Declaration in FORM BFile: Form B Survey No 11.pdf | 30 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Daisy Gardens Survey No 11 Compressed.pdf | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Daisy Garden Survey No 11 Building 1 2 3 Compressed.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Sale Agreement As per RERA.pdf | 30 Jul 2017 |
| PAN CardFile: PAN Card of Firm Ankita Builders.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: Daisy Gardens S No 11.pdf | 29 Jul 2017 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Daisy Gardens Building No.13P51700052891 | Khoj-Khuntavli, Ambernath, Thane | 8 | Oct 2023 | Certificate Signed | Jun 2026 | Not delivered |
| DAISY GARDENS SURVEY NO 12 PHASE IP51700009528 | KHOJ GAON, Thane | 113 | Aug 2017 | Certificate Signed | Jun 2026Registered original: Dec 2020 | Not delivered |
| DAISY GARDENS | SURVEY NO 12 BY 12 15 BY 7 12 BY 3 CTS 33 BY 10 | 58 | - | Completed | Dec 2015 | Jan 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 69 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep DAISY GARDENS SURVEY NO 11 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KHOJGAON7,600+ in Thane
Filed coordinates, straight-line distance. 78 registered projects within 2 km.
MATOSHREE NAGAR EXCELLENCY BLDG SAPPHIRE A AND
MATOSHREE SHELTERS (INDIA) PRIVATE LIMITED
NIDHI RESIDENCY
ADITYA YASH BUILDERS
MIDTOWN B AND C WING
SIDDHIVINAYAK GROUP NX
PATELS LEGACY
RAPID CORPORATION
PATELS ETERNITY
OMKAR INFRASTRUCTURE
Harishree Celestial-1
HARISHREE CREATIONS
See every Thane project, with the district possession charts
Builder: ANKITA BUILDERS
ANKITA BUILDERS has 4 registrations on MahaRERA, including DAISY GARDENS SURVEY NO 11 and DAISY GARDENS SURVEY NO 12 PHASE I. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that DAISY GARDENS SURVEY NO 11 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if DAISY GARDENS SURVEY NO 11 is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DAISY GARDENS SURVEY NO 11?
The registered promoter entity is ANKITA BUILDERS, a partnership as per the filing. Its GSTIN 27AARFA2290D1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DAISY GARDENS SURVEY NO 11?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for DAISY GARDENS SURVEY NO 11?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DAISY GARDENS SURVEY NO 11?
The professionals named in the filing: Architect: VITAN CONSULTANTS; Engineer: PRAMOD KAMBLE; Engineer: MR C N DUSEJA; Chartered Accountant: Mukesh Gurnani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DAISY GARDENS SURVEY NO 11?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.