Home / Browse projects / Mumbai Suburban, Maharashtra / DAHISAR UDAYRAJ CHSL

Registration lapsed No litigation declared Residential / Group Housing project

DAHISAR UDAYRAJ CHSL

By MITESH B SHAH

RG-MH-08253 · RERA P51800007203 · Last updated on MahaRERA portal: 10 May 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 35 months past the filed date
  • Completion date moved by 59 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Nov 2023Possession promised35 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 95%
8 of 8Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 52 documents Report an error

DAHISAR UDAYRAJ CHSL is a Residential / Group Housing project by MITESH B SHAH in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007203 on 17 Aug 2017. Possession was promised by 30 Nov 2023 and is now 35 months past that date. The completion date has moved by 59 months from the original filing. 0 of the 8 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameDAHISAR UDAYRAJ CHSL
  • TypeResidential / Group Housing
  • Location
    • PARBAT NAGAR
    • DAHISAR EAST
    • Greater Mumbai (M Corp.) (Part) (802794)
    • Mumbai
    • Mumbai Suburban
    • 400068
  • Pincode400068
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800007203
  • ReraGenie IDRG-MH-08253

Builder

  • NameMITESH B SHAH
  • Entity typeIndividual
  • GSTIN27AXPPS8892N3ZY
  • PartnerKIRAN GAURU MAHADIK
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

35 months past promisethis monthRegisteredAug 2017First promiseDec 2018Revised toNov 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Aug 2017
  • Promised completion30 Nov 2023
  • Revised completionRevised to 30 Nov 2023 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed52 files

Current status

0%0 of 8 units booked

Figures as on 10 May 2023, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DAHISAR UDAYRAJ CHSLNA98808

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

DAHISAR UDAYRAJ CHSL: 80% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 10 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes30%
Landscaping & Tree PlantingYes30%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed14

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots14
Closed/Covered1
Open Space13

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area488 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityBRUHUN MUMBAI MAHANAGAR PALIKA
Permissible FSI1316.25
Proposed, not sanctioned527 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 1 DHARMAKHETRS CHSL NO 1 FACTORY LANE NEAR AMBAMATA TEMPLE BORIVALI WEST

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJEEGAR J TANNA
EngineerCHINTAN V PATEL
Chartered AccountantRAHUL SUKHWAL
PartnerRole in project
MITESH B SHAH-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800000747Dec 2018 → Dec 2020

Reason as filed by the promoterAS PER GOV POLICY THEY WERE NOT GIVING THE 2.7 FSI ON LESS THEN 9 MTR ROAD AFTER GIVING THE COMPLAINT TO URBAN DEVELOPMENT AND THEY GAVE THE CLEARANCE LAST WEEK OF JULY 2018 SO DUE TO THAT WE WERE NOT GETTING THE APPROVAL FOR FURTHER CONSTRUCTION AND AT THE SAME TIME SLUM TDR WAS NOT AVAILABLE IN MARKET DUE TO THAT WE WERE UNABLE TO LOAD THE TDR ON PROPERTY SO WE WANT EXTENSION OF TIME PERIOD TILL 31/12/2019.DO NEEDFUL FOR US SO WE CAN GO AHEAD POSITIVELY FOR REDEVELOPMENT OF OUR PROJECT. AND AS NEW DCR 2034 HAS BEEN COME ON 21ST SEP 2018 AND IT IS GOING TO IMPLEMENT ON 24TH OCT 2018 ,SO KINDL

EXT51800003670Dec 2018 → Dec 2020

Reason as filed by the promoterSIR AS PER THE NEW DCPR 2034 THERE IS NOT CLEARANCE FOR THE PROJECT WHICH IS LAID IN THE LAY OUT AND EVEN THERE WAS NO CLEARANCE FOR OPEN SPACE FOR FIRE FIGHTING 6MTR OR 9MTR FOR CFO , EVEN FOR TDR LOADING TO PLOT WHICH IS LYING BELOW 9MTR RAOD IS NOT CLEARED SO DUE TO THAT WE ARE NOT IN POSITION TO CARRY OUT THE WORK AND EVEN COMPLETE THE PROJECT AS PER REVISED COMPLETION OF DATE. SO NOW I AM REQUESTING YOU TO GIVE THE EXTENSION TILL 31/12/2020 SO WE CAN COMPLETE THE PROJECT AND GIVE THE POSSESSION TO THE MEMBERS OF SOCIETY. IN LAYOUT PLOTS THERE IS NOT CLEARANCE I THE RULES LIKE 14(b) AND 14

EXT51800011720Dec 2018 → May 2023

Reason as filed by the promoterWe had paid the amount for approval in the month of august 2021 but as per new rule they require Airport NOC for further CC so we received Airport NOC in the month of dec 2021 that i am attaching herewith and even after that further CC we got on 25Dec 2021 so to complete the work we require further extension and for that relevant paper we hereby attaching herewith

EXT51800009726Dec 2018 → Jun 2022

Reason as filed by the promoterAs you all aware that due to this Pandamic situation we are not able to get the approval as there is delay in the policy of the layout and even they require old papers of the members so they were not getting the papers due to the lockdown so just wants to extend the time line for completion of work

EXT51800015461Dec 2018 → Nov 2023

Reason as filed by the promoterAS HAVE TO TAKE AIRPORT NOC AND ALMOST ALL THE WORK HAS DONE HAVE TO TAKE THE OCCUPATION CERTIFICATE AS MATERIAL SHORTAGE WAS THERE AND WE GOT THE APPROVAL FOR BALANCE WORK IN LATER SATGE SO REQUESTING YOU TO GIVE THE EXTENTION OF 6 MORE MONTHS FOR COMPLETION OF THE PROJECT.

Litigation declared1

CaseCourtStatus
427 OF 2016/2016THE HIGH COURT OF JUDICATIVE AT BOMBAYSOLVED

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jun 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jun 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Dec 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed52

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 RERA Certificate FY 2021-2022.pdf10 May 2023
Disclosure of sold/ booked inventoryFile: Disclosure Of Sold,Booked Inventory.pdf9 May 2023
Deviation Report with respect to Allotment letterFile: DECLARATION.pdf26 Apr 2023
Deviation Report with respect to Allotment letterFile: DECLARATION (2).pdf26 Apr 2023
Deviation Report with respect to model copy of AgreementFile: DECLARATION.pdf26 Apr 2023
Details of encumbrances concerned to FinanceFile: Encumbrance.pdf24 Apr 2023
Details of encumbrances concerned to LegalFile: Encumbrance.pdf24 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: ENGINEER CERTIFICATE.pdf24 Apr 2023
CERSAI detailsFile: CERSAI_Search_Report_200266780414_For_Asset_Based_Search_23_04_2023_17_47_59_140.pdf24 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organization.pdf24 Apr 2023
Proforma of Agreement for saleFile: Agreement for sale draft.pdf24 Apr 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Details.pdf24 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 2017-18.pdf31 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2018-19.pdf31 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-20.pdf31 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-21.pdf31 Aug 2021
Disclosure of sold/ booked inventoryFile: UDAYRAJ CHSL.pdf3 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 .pdf3 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate 31032019.pdf30 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 Engineers Certificate.pdf30 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 Engineers Certificate 31032018.pdf30 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 FY 2018.pdf30 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 FY 2019.pdf30 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 2018.pdf30 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 2020.pdf30 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 2021.pdf30 Jul 2021
Declaration about Commencement CertificateFile: CamScanner 06142021 (1).pdf28 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 Engineers Certificate.pdf28 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 Engineers Certificate 31032019.pdf28 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 Engineers Certificate 31032019.pdf28 Jun 2021
Disclosure of sold/ booked inventoryFile: Extension time for construction rera.pdf28 Jun 2021
Disclosure of sold/ booked inventoryFile: Extension time for construction rera.pdf28 Jun 2021
Disclosure of sold/ booked inventoryFile: Annexure (3) rera.pdf28 Jun 2021
Disclosure of sold/ booked inventoryFile: Annexure (4) rera.pdf28 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 FY 2018.pdf28 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 FY 2019.pdf28 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 2020.pdf28 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 2021.pdf28 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: CC For Suryoday001.pdf7 Dec 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Gaurav bhai.pdf28 Jul 2017
Certificates of CA (Form 3)File: Chetanbhai.pdf28 Jul 2017
Declaration in FORM BFile: suraj1.pdf6 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: letter pad034.pdf5 Jul 2017
Layout approvalFile: Graphic1.pdf1 Jul 2017
Details of encumbrancesFile: PAPER032.pdf1 Jul 2017
Copy of Layout Approval (in case of layout)File: Graphic1.pdf1 Jul 2017
Proforma of Allotment letterFile: aadad.pdf1 Jul 2017
Building plan approvalFile: Iod plan pdf.pdf25 Jun 2017
PAN CardFile: Mitesh Bhai(Pan).pdf25 Jun 2017
Copy of the legal title reportFile: Title Certificat.pdf25 Jun 2017
Building Plan Approval (IOD)File: Iod plan pdf.pdf25 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Udayraj CC022.pdf25 Jun 2017

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
SAPANA CHSLKOTHARIWADI RAMCHANDRALANE MALAD W24CompletedJun 2017May 2017
MATRUPRIYACHIKUWADI BORIVALI WEST24CompletedNov 2007Late, Dec 2017
TRI HANSH CHSLTPS IIIFP NO 505 CHIKUWADI BORIVALI WEST16CompletedDec 2006Jul 2006

How this compares with Mumbai Suburban

0%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 59 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DAHISAR UDAYRAJ CHSL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DAHISAR EAST6,700+ in Mumbai Suburban

2 kmDAHISAR UDAYRAJ CHSLCompleted 15Lapsed / revoked 16Other 14Dot size: filed unitsN

Filed coordinates, straight-line distance. 45 registered projects within 2 km.

Builder: MITESH B SHAH

MITESH B SHAH has 2 registrations on MahaRERA, including DAHISAR UDAYRAJ CHSL and PROPOSED RED. ON PLOT BEARING FP NO.41H OF TPS III VILLAGE KANHERI AT BORIVALI EAST MUMBAI. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that DAHISAR UDAYRAJ CHSL shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if DAHISAR UDAYRAJ CHSL is delayed beyond 30 Nov 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DAHISAR UDAYRAJ CHSL?

The registered promoter entity is MITESH B SHAH, an individual as per the filing. Its GSTIN 27AXPPS8892N3ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DAHISAR UDAYRAJ CHSL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DAHISAR UDAYRAJ CHSL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DAHISAR UDAYRAJ CHSL?

The professionals named in the filing: Architect: JEEGAR J TANNA; Engineer: CHINTAN V PATEL; Chartered Accountant: RAHUL SUKHWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DAHISAR UDAYRAJ CHSL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DAHISAR UDAYRAJ CHSL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DAHISAR UDAYRAJ CHSL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.