Home / Browse projects / Pune, Maharashtra / CRYSTAL SPRING
CRYSTAL SPRING
By KISHANKUMAR JUGALKISHOR KEDIA
RG-MH-11426 · RERA P52100004437 · Last updated on MahaRERA portal: 8 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 1 case
- 10 complaints at MahaRERA
- Completion date moved by 73 months
- 1 extension taken
Clear
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
CRYSTAL SPRING is a Mixed project by KISHANKUMAR JUGALKISHOR KEDIA in Pune, Maharashtra, registered with MahaRERA as P52100004437 on 9 Aug 2017. Possession is promised by 31 Dec 2029. The completion date has moved by 73 months from the original filing. 0 of the 1 unit on this registration is recorded sold or booked, and 1035 of 1265 construction stages are filed complete. 10 complaints are on record with the regulator.
At a glance
Project
- NameCRYSTAL SPRING
- TypeMixed
- Location
- Karla
- Mawal
- Pune
- 410405
- Pincode410405
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100004437
- ReraGenie IDRG-MH-11426
Builder
- NameKISHANKUMAR JUGALKISHOR KEDIA
- Entity typeIndividual
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on9 Aug 2017
- Promised completion31 Dec 2029
- Revised completionRevised to 31 Dec 2029 (originally 28 Nov 2023)
- Buildings115 building records
- Documents filed153 files
Current status
Figures as on 8 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Bungalow No 1 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow No 2 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 3 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 4 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 5 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 6 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow no 7 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 8 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 9 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 10 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 11 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 12 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 13 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 14 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 15 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No16 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow no 17 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow no 18 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow no 19 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 20 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 21 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 22 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 23 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 24 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 25 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 26 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 27 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 28 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 29 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 30 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 31 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 32 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No33 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 34 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 35 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 36 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 37 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 38 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 39 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 40 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 41 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 42 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 43 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 44 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 45 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 46 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 47 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 48 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 49 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 50 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 51 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 52 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 53 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 54 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 55 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 56 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 57 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 58 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 59 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 60 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 61 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 62 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 63 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 64 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 65 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 66 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 67 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 68 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 69 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 70 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 71 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 72 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 73 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 74 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 75 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 76 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 77 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 78 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 79 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 80 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 81 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 82 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 83 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 84 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 85 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 86 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 87 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 88 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 89 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 90 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 91 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 92 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 93 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 94 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 95 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 96 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 97 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 98 | NA | 2 | 2 | 0 | 0 | 0 |
| Bunaglow No 99 | NA | 2 | 2 | 0 | 0 | 0 |
| Bunglow No 100 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 101 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 102 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 103 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 104 | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow no 1A | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 2A | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 3A | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 4A and 4B | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 5A | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 6A | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 7A and 7B | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 8A | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 9A | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 10A and 10B | NA | 2 | 2 | 0 | 0 | 0 |
| Bungalow No 11A | NA | 2 | 2 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 8 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 116 buildings; the table lists the first 20.
1035 of 1265 construction stages are filed complete across 116 buildings. The stage furthest along is Installation of Lifts, at 90%.
Bungalow No 190%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow No 290%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow No 390%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow No 490%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow No 590%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow No 690%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow no 790%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow No 890%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow No 990%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow No 1090%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow No 1190%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow No 1290%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow No 1390%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow No 1490%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow No 1590%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow No1690%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow no 1790%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow no 1890%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow no 1990%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Bungalow No 2090%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 8 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 80% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 80% |
| Street Lighting | Yes | 70% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 80% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 90% |
Parking filed115
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| Bungalow No 1 | 1 | 1 |
| Bungalow No 2 | 1 | 1 |
| Bungalow No 3 | 1 | 1 |
| Bungalow No 4 | 1 | 1 |
| Bungalow No 5 | 1 | 1 |
| Bungalow No 6 | 1 | 1 |
| Bungalow no 7 | 1 | 1 |
| Bungalow No 8 | 1 | 1 |
| Bungalow No 9 | 1 | 1 |
| Bungalow No 10 | 1 | 1 |
| Bungalow No 11 | 1 | 1 |
| Bungalow No 12 | 1 | 1 |
| Bungalow No 13 | 1 | 1 |
| Bungalow No 14 | 1 | 1 |
| Bungalow No 15 | 1 | 1 |
| Bungalow No16 | 1 | 1 |
| Bungalow no 17 | 1 | 1 |
| Bungalow no 18 | 1 | 1 |
| Bungalow no 19 | 1 | 1 |
| Bungalow No 20 | 1 | 1 |
| Bungalow No 21 | 1 | 1 |
| Bungalow No 22 | 1 | 1 |
| Bungalow No 23 | 1 | 1 |
| Bungalow No 24 | 1 | 1 |
| Bungalow No 25 | 1 | 1 |
| Bungalow No 26 | 1 | 1 |
| Bungalow No 27 | 1 | 1 |
| Bungalow No 28 | 1 | 1 |
| Bungalow No 29 | 1 | 1 |
| Bungalow No 30 | 1 | 1 |
| Bungalow No 31 | 1 | 1 |
| Bungalow No 32 | 1 | 1 |
| Bungalow No33 | 1 | 1 |
| Bungalow No 34 | 1 | 1 |
| Bungalow No 35 | 1 | 1 |
| Bungalow No 36 | 1 | 1 |
| Bungalow No 37 | 1 | 1 |
| Bungalow No 38 | 1 | 1 |
| Bungalow No 39 | 1 | 1 |
| Bungalow No 40 | 1 | 1 |
| Bungalow No 41 | 1 | 1 |
| Bungalow No 42 | 1 | 1 |
| Bungalow No 43 | 1 | 1 |
| Bungalow No 44 | 1 | 1 |
| Bungalow No 45 | 1 | 1 |
| Bungalow No 46 | 1 | 1 |
| Bungalow No 47 | 1 | 1 |
| Bungalow No 48 | 1 | 1 |
| Bungalow No 49 | 1 | 1 |
| Bungalow No 50 | 1 | 1 |
| Bungalow No 51 | 1 | 1 |
| Bungalow No 52 | 1 | 1 |
| Bungalow No 53 | 1 | 1 |
| Bungalow No 54 | 1 | 1 |
| Bungalow No 55 | 1 | 1 |
| Bungalow No 56 | 1 | 1 |
| Bungalow No 57 | 1 | 1 |
| Bungalow No 58 | 1 | 1 |
| Bungalow No 59 | 1 | 1 |
| Bungalow No 60 | 1 | 1 |
| Bungalow No 61 | 1 | 1 |
| Bungalow No 62 | 1 | 1 |
| Bungalow No 63 | 1 | 1 |
| Bungalow No 64 | 1 | 1 |
| Bungalow No 65 | 1 | 1 |
| Bungalow No 66 | 1 | 1 |
| Bungalow No 67 | 1 | 1 |
| Bungalow No 68 | 1 | 1 |
| Bungalow No 69 | 1 | 1 |
| Bungalow No 70 | 1 | 1 |
| Bungalow No 71 | 1 | 1 |
| Bungalow No 72 | 1 | 1 |
| Bungalow No 73 | 1 | 1 |
| Bungalow No 74 | 1 | 1 |
| Bungalow No 75 | 1 | 1 |
| Bungalow No 76 | 1 | 1 |
| Bungalow No 77 | 1 | 1 |
| Bungalow No 78 | 1 | 1 |
| Bungalow No 79 | 1 | 1 |
| Bungalow No 80 | 1 | 1 |
| Bungalow No 81 | 1 | 1 |
| Bungalow No 82 | 1 | 1 |
| Bungalow No 83 | 1 | 1 |
| Bungalow No 84 | 1 | 1 |
| Bungalow No 85 | 1 | 1 |
| Bungalow No 86 | 1 | 1 |
| Bungalow No 87 | 1 | 1 |
| Bungalow No 88 | 1 | 1 |
| Bungalow No 89 | 1 | 1 |
| Bungalow No 90 | 1 | 1 |
| Bungalow No 91 | 1 | 1 |
| Bungalow No 92 | 1 | 1 |
| Bungalow No 93 | 1 | 1 |
| Bungalow No 94 | 1 | 1 |
| Bungalow No 95 | 1 | 1 |
| Bungalow No 96 | 1 | 1 |
| Bungalow No 97 | 1 | 1 |
| Bungalow No 98 | 1 | 1 |
| Bunaglow No 99 | 1 | 1 |
| Bunglow No 100 | 1 | 1 |
| Bungalow No 101 | 1 | 1 |
| Bungalow No 102 | 1 | 1 |
| Bungalow No 103 | 1 | 1 |
| Bungalow No 104 | 1 | 1 |
| Bungalow no 1A | 1 | 1 |
| Bungalow No 2A | 1 | 1 |
| Bungalow No 3A | 1 | 1 |
| Bungalow No 4A and 4B | 1 | 1 |
| Bungalow No 5A | 1 | 1 |
| Bungalow No 6A | 1 | 1 |
| Bungalow No 7A and 7B | 1 | 1 |
| Bungalow No 8A | 1 | 1 |
| Bungalow No 9A | 1 | 1 |
| Bungalow No 10A and 10B | 1 | 1 |
| Bungalow No 11A | 1 | 1 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Adinath Patkar |
| Engineer | Mahadeo Rahate |
| Chartered Accountant | Ashish Maheshwari & Associates Chartered Accountants |
| Chartered Accountant | ASHISH MAHESHWARI & ASSOCIATES |
| Chartered Accountant | PODDAR A. & ASSOCIATES |
| Partner | Role in project |
|---|---|
| KISHANKUMAR JUGALKISHOR KEDIA | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs we are unable to get 51% consents from allottees we would like to apply under order 40.
Litigation declared1
| Case | Court | Status |
|---|---|---|
| S 30/465-466/22/J-5/2016 | Revenue Minister Government Of Maharashtra | For order |
Complaints filed with MahaRERA10
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000023435 | Nitish Kumar Patel | M/s. Garnet Construction Private Limited | 21/09/2019 |
| CC005000000023438 | Arunbhai Patel | Garnet Construction Private Limited | 21/09/2019 |
| CC005000000023439 | Hiralal Lalji Patel | Garnet Constructions Private Limited | 21/09/2019 |
| CC005000000023440 | Ms. Ruth Emily Nimbargi | Garnet Constructions Private Limited | 14/10/2019 |
| CC005000000023441 | Mr Vasant Sanghani | Garnet Constructions Private Limited | 21/09/2019 |
| CC005000000198048 | Garnet Construction Limited | Vasant D. Sanghani | 05/01/2023 |
| CC005000000198049 | Garnet Construction Limited | Hiralal Lalji Patel | 05/01/2023 |
| CC005000000198050 | Garnet Construction Limited | Nitish Kumar Patel | 05/01/2023 |
| CC005000000198051 | Garnet Construction Limited | Ruth Emily Nimbargi | 05/01/2023 |
| CC005000000198052 | Garnet Construction Limited | Arunbhai M. Patel | 05/01/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Feb 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2029
Documents filed153
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 153 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2File: Signed Form 2.pdf | 8 Jun 2026 |
| Form 3File: signed form 3.pdf | 8 Jun 2026 |
| Form 1File: FORM 1.pdf | 8 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory.pdf | 8 Jun 2026 |
| Form 1File: Form 1 Q3 CS.pdf | 20 Feb 2026 |
| Form 2File: Form 2 Q3 Crystal Spring signed.pdf | 20 Feb 2026 |
| Form 3File: Form 3 Q3 Crystal Spring signed.pdf | 20 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory.pdf | 20 Feb 2026 |
| Form 1File: FORM 1 CS Q 2.pdf | 1 Dec 2025 |
| Form 2File: Form 2 Sept 2025 CS.pdf | 1 Dec 2025 |
| Form 3File: Form 3 Sept 2025 CS.pdf | 1 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory.pdf | 1 Dec 2025 |
| Form 1File: withdrawl Application form 1 CS.pdf | 8 Oct 2025 |
| Form 2File: Form 2 CS June 25.pdf | 8 Oct 2025 |
| Form 3File: Form 3 CS June 25.pdf | 8 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory.pdf | 8 Oct 2025 |
| Form 1File: FORM 1 31 03 2025 Compress.pdf | 20 Jun 2025 |
| Form 2File: Form 2 Mar 25 CE signed.pdf | 20 Jun 2025 |
| Form 3File: Form 3 Mar 25 CA signed.pdf | 20 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory.pdf | 20 Jun 2025 |
| Certificates of CA (Form 3)File: Form 3 Mar 25 CA signed.pdf | 13 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Mar 25 CE signed.pdf | 13 May 2025 |
| Disclosure of sold/ booked inventoryFile: 1 Disclosure of sold_ booked inventory.pdf | 13 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 September 2021_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 31 03 2025 Compress.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 December 2024_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 September 2024_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 June 2024_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 March 2024.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 December 2023_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 September 2023_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 June 2023_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 March 2023_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 December 2022_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 September 2022_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 June 2022_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 March 2022_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 December 2021_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 December 2017_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 June 2021_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 March 2021_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 December 2020_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 September 2020_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 June 2020_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 March 2020_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 December 2019_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 September 2019_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 June 2019_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 March 2019_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 December 2018_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 September 2018_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 June 2018_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 March 2018_11zon.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 31 03 2025 Compress.pdf | 24 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 June 2024_11zon.pdf | 23 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 September 2024_11zon.pdf | 23 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 December 2024_11zon.pdf | 23 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 June 24 CS signed.pdf | 18 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sept 24 CS signed.pdf | 18 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 24 CS signed.pdf | 18 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Crystal Spring 23-24.pdf | 18 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 June 24 CS signed.pdf | 15 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 Sept 24 CS signed.pdf | 15 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 Dec 24 CS signed.pdf | 15 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Crystal Spring 23-24.pdf | 15 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Circular 29.pdf | 10 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate 31 March 2024.pdf | 7 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate 7 june 2024.pdf | 7 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: June'17_Form 2_Engineer's Certificate Crystal Spring.pdf | 6 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Mar'18_Form 2_Engineer's Certificate Crystal Spring.pdf | 6 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Mar'19_Form 2_Engineer's Certificate Crystal Spring.pdf | 6 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Mar'20_Form 2_Engineer's Certificate Crystal Spring.pdf | 6 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Mar'21_Form 2_Engineer's Certificate Crystal Spring.pdf | 6 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Mar'22_Form 2_Engineer's Certificate Crystal Spring.pdf | 6 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Mar'23_Form 2_Engineer's Certificate Crystal Spring.pdf | 6 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: June'23_Form 2_Engineer's Certificate Crystal Spring.pdf | 6 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sept'23_Form 2_Engineer's Certificate Crystal Spring.pdf | 6 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Dec'23_Form 2_Engineer's Certificate Crystal Spring.pdf | 6 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Mar'24_Form 2_Engineer's Certificate Crystal Spring.pdf | 6 Jun 2024 |
| Certificates of CA (Form 3)File: 1 Certificates of CA (Form 3) (1)_2017.pdf | 6 Jun 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Magic Hill | Village Ambivali Taluka Khalapur District Raigad | 283 | Completed | Apr 2017 | Apr 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 153 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep CRYSTAL SPRING on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Karla13,700+ in Pune
Filed coordinates, straight-line distance. 86 registered projects within 2 km.
AQUAGEM
NAMRATA REALTY
VIGHNESH VIKAS
MADANLAL HANSRAJ GUPTA
Monte Karla
GOODBRICK REALTY PRIVATE LIMITED
GAGAN NULIFE PHASE 2
GAGAN LIFESPACE
Misty Winds 2
Planet I Developers
WEEKENDER COUNTRY SONGS
NAMRATA REALTY
Builder: KISHANKUMAR JUGALKISHOR KEDIA
KISHANKUMAR JUGALKISHOR KEDIA has 1 registration on MahaRERA, including CRYSTAL SPRING. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if CRYSTAL SPRING is delayed beyond 31 Dec 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of CRYSTAL SPRING?
The registered promoter entity is KISHANKUMAR JUGALKISHOR KEDIA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in CRYSTAL SPRING?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against CRYSTAL SPRING?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for CRYSTAL SPRING?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at CRYSTAL SPRING?
The professionals named in the filing: Architect: Adinath Patkar; Engineer: Mahadeo Rahate; Chartered Accountant: Ashish Maheshwari & Associates Chartered Accountants; Chartered Accountant: ASHISH MAHESHWARI & ASSOCIATES; Chartered Accountant: PODDAR A. & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CRYSTAL SPRING?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback