Completed No litigation declared Others project

CROWN PHASE 1

By SHREE SAMARTH REALITY

RG-MH-90221 · RERA P52000013990 · Last updated on MahaRERA portal: 20 Jan 2025

Source: official MahaRERA filing

Red flags

  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 2 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
19 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 86%
0Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

CROWN PHASE 1 is a Others project by SHREE SAMARTH REALITY in Raigarh, Maharashtra, registered with MahaRERA as P52000013990 on 7 Nov 2017. The registration is recorded completed; possession was promised by 30 Dec 2021.

At a glance

Project

  • NameCROWN PHASE 1
  • TypeOthers
  • Location
    • Karjat
    • Raigarh
    • 410201
  • Pincode410201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000013990
  • ReraGenie IDRG-MH-90221

Builder

  • NameSHREE SAMARTH REALITY
  • Entity typePartnership
  • PartnersRAHUL HANUMANT SATAV, CHHAYA RAHUL SATAV
  • Declared earlier projects2 →

Key dates

this monthRegisteredNov 2017PromisedDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on7 Nov 2017
  • Promised completion30 Dec 2021
  • Revised completionNone
  • Buildings2 building records
  • Documents filed59 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WingNA60000
B WingNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

19 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 86%.

A Wing91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B Wing90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.86%

Progress on shared amenities17

As on 20 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Fitness CenterYes0%
ClubYes0%

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
A Wing11
B Wing11

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,558 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
PRADEEP ARJUN RAMCHANDANIUlhasnagar (M Corp.)Thane

Approvals and building plan

Permissible FSI3559.06
Proposed, not sanctioned3,559 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVaidya Sankul, At post Karjat, Taluka Karjat, Dist Raigarh Pin 410 201

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVASTU RACHANA CONSULTANCY
EngineerSHIVMURTI MAHADEV MANDOLIKAR
PartnerRole in project
SHREE SAMARTH REALITY-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000015347Dec 2021 → Mar 2024

Reason as filed by the promoterThe project is completed on 16 March 2022 and completion certificate is also received from the authority which is uploaded in this application as well as in the Document upload tab. We have received mail from your side to take extension till completion date, as there is no requirement of consent from clients, though we have taken consents from our allottes. kindly grant us the extension till completion of the said project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Oct 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Oct 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Oct 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Oct 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Dec 2022

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: crown Phase 1 and from 3_compressed.pdf20 Jan 2025
Layout approvalFile: layout crown phase 1pdf 32.pdf24 Oct 2024
Copy of Layout Approval (in case of layout)File: layout crown phase 1pdf 32.pdf24 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Crown Phase 1 Form 5.pdf13 Feb 2024
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 A WING CROWN PHASE 1.pdf16 Jun 2023
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 B WING CROWN PHASE 1.pdf16 Jun 2023
Disclosure of sold/ booked inventoryFile: CROWN A AND B Phase I.pdf3 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architact Certificate Form 1, 31-03-2019 ,Crown Phase 1.pdf13 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architact Certificate Form 1, 31-03-2020 ,Crown Phase 1.pdf13 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architact Certificate Form 1, 31-03-2021 ,Crown Phase 1.pdf13 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architact Certificate Form 1, 31-12-2021 ,Crown Phase 1.pdf13 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2,Apr-22 to Dec 22 Crown Phase 1.pdf13 Mar 2023
Certificates of CA (Form 3)File: CA Certificate Form 3 2017-18 Crown Phase 1.pdf13 Mar 2023
Certificates of CA (Form 3)File: CA Certificate Form 3, 2018-19 Crown Phase 1.pdf13 Mar 2023
Certificates of CA (Form 3)File: CA Certificate Form 3, 2019-20 Crown Phase 1.pdf13 Mar 2023
Certificates of CA (Form 3)File: CA Certificate Form 3, 2020-21 Crown Phase 1.pdf13 Mar 2023
Certificates of CA (Form 3)File: CA Certificate Form 3, 2021-22 Crown Phase 1.pdf13 Mar 2023
Certificates of CA (Form 3)File: CA Certificate Form 3, upto Dec 2022 Crown Phase 1.pdf13 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Audit Report Form 5 (20-21) Crown Phase 1.pdf13 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Audit Report Form 5 (21-22) Crown Phase 1.pdf13 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate 2017-18 Crown Phase 1.pdf9 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate 2018-19 Crown Phase 1.pdf9 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate 2019-20 Crown Phase 1.pdf9 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate 2020-21 Crown Phase 1.pdf9 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate 2021-22 Crown Phase 1.pdf9 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2,Apr-22 to Dec 22 Crown Phase 1.pdf9 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineers Quality Assurance Form 2A 2020-21 Crown Phase 1.pdf9 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineers Quality Assurance Form 2A 2021-22 Crown Phase 1.pdf9 Mar 2023
Disclosure of sold/ booked inventoryFile: Sold and Unsold Inventory Crown Phase 1 31-12-2022.pdf9 Mar 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC A WING.pdf7 Dec 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society formation certificate Crown Phase 1.pdf3 Nov 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC B Wing.pdf1 Apr 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC B Wing.pdf1 Apr 2022
Declaration about Commencement CertificateFile: Commencement Certificate.pdf7 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2019-2020.pdf7 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020-2021.pdf7 Aug 2021
Disclosure of sold/ booked inventoryFile: Inventory Statment up to 31032021.pdf7 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5.pdf18 Feb 2021
Certificates of CA (Form 5)File: Form5CA_Certificate_31-03-2018.pdf30 Sep 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: DOC-20180517-WA0016.pdf17 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form 1 (Arch ceft) .pdf17 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form 1 (Arch ceft) .pdf17 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form 1 (Arch ceft) .pdf17 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form 1 (Arch ceft) .pdf17 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form 1 (Arch ceft) .pdf17 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Ceft Form 2 March Update .pdf17 Mar 2018
Building plan approvalFile: Building Plan Approval.pdf18 Oct 2017
Layout approvalFile: Building Plan Approval.pdf18 Oct 2017
PAN CardFile: PAN.pdf18 Oct 2017
Copy of the legal title reportFile: Legal Title Report.pdf18 Oct 2017
Details of encumbrancesFile: Declaration of Encumbrances.pdf18 Oct 2017
Copy of Layout Approval (in case of layout)File: Building Plan Approval.pdf18 Oct 2017
Building Plan Approval (IOD)File: Building Plan Approval.pdf18 Oct 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf18 Oct 2017
Declaration in FORM BFile: Form B.pdf18 Oct 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 RERA Architect Certificate.pdf18 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Certificate of Architect.pdf18 Oct 2017
Certificates of CA (Form 3)File: CA Certificate.pdf18 Oct 2017
Proforma of Allotment letterFile: Draft Agreement As per RERA Act Agreement for Sale .pdf18 Oct 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
COSMOS BSurvey Number 11 2 Near Good Shephered Convert School Village Gundge Taluka Karjat Dist Raigad Pin 41020122CompletedMar 2017Mar 2017
COSMOS ASurvey Number 11 2 Near Good Shephered Convert School Village Gundge Taluka Karjat Dist Raigad Pin 41020129CompletedMar 2017Feb 2017

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CROWN PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Karjat5,900+ in Raigarh

2 kmCROWN PHASE 1Completed 17Lapsed / revoked 19Other 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 75 registered projects within 2 km.

Builder: SHREE SAMARTH REALITY

SHREE SAMARTH REALITY has 1 registration on MahaRERA, including CROWN PHASE 1. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if CROWN PHASE 1 is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CROWN PHASE 1?

The registered promoter entity is SHREE SAMARTH REALITY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CROWN PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CROWN PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CROWN PHASE 1?

The professionals named in the filing: Architect: VASTU RACHANA CONSULTANCY; Engineer: SHIVMURTI MAHADEV MANDOLIKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CROWN PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CROWN PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CROWN PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.