Home / Browse projects / Sangli, Maharashtra / Construction of 96 LIG tenements at S No 116, Gut No 127/1, Palus Dist-Sangli

Registration lapsed No litigation declared Residential / Group Housing project

Construction of 96 LIG tenements at S No 116, Gut No 127/1, Palus Dist-Sangli

By Pune Housing and Area Development Board Pune

RG-MH-14704 · RERA P53100024663 · Last updated on MahaRERA portal: 20 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
88 of 88Construction stages doneacross 8 buildings; every applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 14 documents Report an error

Construction of 96 LIG tenements at S No 116, Gut No 127/1, Palus Dist-Sangli is a Residential / Group Housing project by Pune Housing and Area Development Board Pune in Sangli, Maharashtra, registered with MahaRERA as P53100024663 on 28 Feb 2020. Possession was promised by 30 Dec 2025 and is now 10 months past that date.

At a glance

Project

  • NameConstruction of 96 LIG tenements at S No 116, Gut No 127/1, Palus Dist-Sangli
  • TypeResidential / Group Housing
  • Location
    • Kirloskar airport road
    • Palus Colony
    • Palus
    • Sangli
    • 416310
  • Pincode416310
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P53100024663
  • ReraGenie IDRG-MH-14704

Builder

  • NamePune Housing and Area Development Board Pune
  • Entity typePublic Authority
  • GSTIN27AAAJM0344H5ZA
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Executive Engineer II PHADBManisha Ananda More
  • Chief Account OfficerLalit Pomeshwar Khapre
  • Other registrations21 more →
  • Completed9 of 22
  • No longer live7 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

10 months past promisethis monthRegisteredFeb 2020PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on28 Feb 2020
  • Promised completion30 Dec 2025
  • Revised completionNone
  • Buildings8 building records
  • Documents filed14 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building 1NA54000
Building 2NA50000
Building 3NA50000
Building 4NA50000
Building 5NA50000
Building 6NA50000
Building 7NA50000
Building 8NA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building8

As on 20 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

88 of 88 construction stages are filed complete across 8 buildings.

Building 1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 2100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 3100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 4100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 5100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 6100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 7100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 8100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed8

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots8
Closed/Covered8
BuildingClosed/CoveredTotal
Building 111
Building 211
Building 311
Building 411
Building 511
Building 611
Building 711
Building 811

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,445 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4957.44
Proposed, not sanctioned4,957 sq m
Buildings approved8
Buildings sanctioned8

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKhuda Murad, Sarabatwala Chowq,sachpir street,pune camp

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPramod Chougule
Engineerdeputy engineer
Chartered AccountantChief Account Officer
PartnerRole in project
Pune Housing and Area Development Board Pune-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Dec 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Dec 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Dec 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Dec 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 20 Feb 2025

Documents filed14

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 116.pdf20 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 116.pdf20 Feb 2025
Layout approvalFile: layout _116_opt.pdf14 Dec 2019
Building plan approvalFile: BUilding plan _116_opt.pdf14 Dec 2019
Copy of the legal title reportFile: 7-12 Palus_opt.pdf14 Dec 2019
Details of encumbrancesFile: NON_encumbrance_116_opt.pdf14 Dec 2019
Copy of Layout Approval (in case of layout)File: layout _116_opt.pdf14 Dec 2019
Building Plan Approval / NA Order for plotted developmentFile: BUilding plan _116_opt.pdf14 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: building permission_opt.pdf14 Dec 2019
Declaration in FORM BFile: S No 116, Palus Form B_opt.pdf14 Dec 2019
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch certificate_116_opt.pdf14 Dec 2019
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate_116_opt.pdf14 Dec 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_form3_116_opt.pdf14 Dec 2019
Proforma of Allotment letterFile: Attotment Letter Upload.pdf14 Dec 2019

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise2 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Construction of 16 LIG tenements, 16 MIG tenements and 13 Shops at S No 252/1, SangliP53100024685Abhaynagar, Sangli45Feb 2020CompletedMar 2026Jun 2023
Composite Housing Scheme on Plot E2 at Sant Tukaram Nagar Pimpri PuneP52100049355Opposite Sant Tukaram Nagar Police Chowki, Pune64Feb 2023OngoingDec 2025Registered original: Dec 2024Not delivered
Composite Housing Scheme on Plot D1 at Sant Tukaram Nagar Pimpri PuneP52100049490Opposite Sant Tuakaram Nagar Police Chowki, Pune-Feb 2023OngoingDec 2024Not delivered
Const 72 MIG TenamentsAmboli Road Near Maruti Showroom Saswad72-CompletedMar 2017Mar 2017

How this compares with Sangli

11%of Sangli projects moved their completion datethis one has not
29%of Sangli registrations have lapsed or been cancelledthis one is among them

Computed across the 790+ Sangli projects on ReraGenie, from their own filings.

Keep Construction of 96 LIG tenements at S No 116 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Palus Colony790+ in Sangli

2 kmConstruction of 96 LIG tCompleted 1Lapsed / revoked 1Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: Pune Housing and Area Development Board Pune

Pune Housing and Area Development Board Pune has 22 registrations on MahaRERA, including Constructing 54 Tenements LIG and 36 Tenements MIG at Gat No 1712 part Dive Taluka Purander Dist Pun and Const.378 LIG,331MIG,154HIG T.. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Sangli district page.

Frequently asked questions

What does it mean that Construction of 96 LIG tenements at S No 116, Gut No 127/1, Palus Dist-Sangli shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Construction of 96 LIG tenements at S No 116, Gut No 127/1, Palus Dist-Sangli is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Construction of 96 LIG tenements at S No 116, Gut No 127/1, Palus Dist-Sangli?

The registered promoter entity is Pune Housing and Area Development Board Pune, a public authority as per the filing. Its GSTIN 27AAAJM0344H5ZA can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Construction of 96 LIG tenements at S No 116, Gut No 127/1, Palus Dist-Sangli?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Construction of 96 LIG tenements at S No 116, Gut No 127/1, Palus Dist-Sangli?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Construction of 96 LIG tenements at S No 116, Gut No 127/1, Palus Dist-Sangli?

The professionals named in the filing: Architect: Pramod Chougule; Engineer: deputy engineer; Chartered Accountant: Chief Account Officer. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Construction of 96 LIG tenements at S No 116, Gut No 127/1, Palus Dist-Sangli?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Construction of 96 LIG tenements at S No 116, Gut No 127/1, Palus Dist-Sangli. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Construction of 96 LIG tenements at S No 116 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.