Home / Browse projects / Pune, Maharashtra / Construction of 760 EWS tenaments on survey No 12 part at Talegaon Dabhade
Construction of 760 EWS tenaments on survey No 12 part at Talegaon Dabhade
By PUNE HOUSING AND AREA DEVELOPMENT BOARD
RG-MH-71655 · RERA P52100019009 · Last updated on MahaRERA portal: 26 Mar 2025
Source: official MahaRERA filing
Red flags
- Completion date moved by 26 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Construction of 760 EWS tenaments on survey No 12 part at Talegaon Dabhade is a Residential / Group Housing project by PUNE HOUSING AND AREA DEVELOPMENT BOARD in Pune, Maharashtra, registered with MahaRERA as P52100019009 on 28 Dec 2018. The registration is recorded completed; possession was promised by 31 Aug 2024. The completion date has moved by 26 months from the original filing.
At a glance
Project
- NameConstruction of 760 EWS tenaments on survey No 12 part at Talegaon Dabhade
- TypeResidential / Group Housing
- Location
- Chakan Road
- Joshiwada
- Talegaon Dabhade (M Cl)
- Mawal
- Pune
- 410507
- Pincode410507
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100019009
- ReraGenie IDRG-MH-71655
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on28 Dec 2018
- Promised completion31 Aug 2024
- Revised completionRevised to 31 Aug 2024 (originally 30 Jun 2022)
- Buildings4 building records
- Documents filed54 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A | NA | 13 | 0 | 0 | 0 | 0 |
| Building B | NA | 13 | 0 | 0 | 0 | 0 |
| Building C | NA | 13 | 0 | 0 | 0 | 0 |
| Building D | NA | 13 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 26 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
28 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is External plumbing and external plaster, at 90%.
Building A87%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Building B87%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Building C87%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Building D87%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Progress on shared amenities16
As on 26 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 75% |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 10% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 90% |
| Solid Waste Management And Disposal | Yes | 90% |
| Water conservation /Rain water harvesting | Yes | 80% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
| Others | Yes | 100% |
Parking filed838
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Building A | 168 | 64 | 232 |
| Building B | 47 | 140 | 187 |
| Building C | 47 | 140 | 187 |
| Building D | 168 | 64 | 232 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RIYAZ MULLA |
| Engineer | Aqueel M H structure vision |
| Chartered Accountant | Swati Parab Chief Accounts Officer MHADA Pune |
| Partner | Role in project |
|---|---|
| PUNE HOUSING AND AREA DEVELOPMENT BOARD | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterUnable to complete the constructions due to technical difficulties and natural calamities.
Reason as filed by the promoterNEED EXTENSION TILL DATE OF COMPLETION CERTIFICATE
Reason as filed by the promoterLockdown due to corona,Local issues
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Sep 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 Oct 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Oct 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Sep 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 13 Aug 2024
Documents filed54
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Other - LegalFile: MHADA FORM 4.pdf | 26 Mar 2025 |
| Other - TechnicalFile: MHADA FORM 4.pdf | 26 Mar 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: MHADA FORM 4.pdf | 17 Jan 2025 |
| Declaration in FORM BFile: Form B (6).pdf | 13 Aug 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: MAHADACert_PO_326089_1SwXO0Sign.pdf | 13 Aug 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: MAHADA_Cert_FO_386097_1RsZE2Sign.pdf | 13 Aug 2024 |
| Declaration in FORM BFile: Form B (2)_11zon.pdf | 2 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3 2023 MHADA.pdf | 2 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate 2019.pdf | 15 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate 2020.pdf | 15 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate 2021.pdf | 15 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate 2022.pdf | 15 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate 2023.pdf | 15 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer Certifivcate 2019.pdf | 15 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer Certifivcate 2020.pdf | 15 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer Certifivcate 2021.pdf | 15 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer Certifivcate 2022.pdf | 15 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer Certifivcate 2023.pdf | 15 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21) (1).pdf | 15 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A Quality Assurance 2022-23.pdf | 15 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: INVENTRY ABCD BUILDING.pdf | 15 Jul 2023 |
| Certificates of CA (Form 3)File: FORM 3 CA Certificate 2019.pdf | 15 Jul 2023 |
| Certificates of CA (Form 3)File: FORM 3 CA Certificate 2020.pdf | 15 Jul 2023 |
| Certificates of CA (Form 3)File: FORM 2 Engineer Certifivcate 2021.pdf | 15 Jul 2023 |
| Certificates of CA (Form 3)File: FORM 3 CA Certificate 2022.pdf | 15 Jul 2023 |
| Certificates of CA (Form 3)File: FORM 3 CA Certificate 2023.pdf | 15 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21) (1).pdf | 15 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 Annual Report 2022-23.pdf | 15 Jul 2023 |
| Declaration about Commencement CertificateFile: Format D.pdf | 6 Sep 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2A 2019_compressed.pdf | 6 Sep 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2A 2020_compressed.pdf | 6 Sep 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2021_compressed.pdf | 6 Sep 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2022_compressed.pdf | 6 Sep 2022 |
| CERSAI detailsFile: Declaration.pdf | 6 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Mhada.pdf | 6 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2019.pdf | 6 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: form 5 2020.pdf | 6 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5 2021.pdf | 6 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2022.pdf | 6 Sep 2022 |
| Form 2AFile: Form 2 A_compressed.pdf | 16 Apr 2019 |
| Certificates of CA (Form 5)File: form 5.pdf | 16 Apr 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate-ilovepdf-compressed.pdf | 12 Dec 2018 |
| Certificates of CA (Form 3)File: CA cerificate-ilovepdf-compressed.pdf | 12 Dec 2018 |
| Layout approvalFile: Layout plan.pdf | 2 Oct 2018 |
| Building plan approvalFile: Senction pdf-ilovepdf-compressed.pdf | 2 Oct 2018 |
| Copy of Layout Approval (in case of layout)File: Layout plan.pdf | 2 Oct 2018 |
| Building Plan Approval (IOD)File: Senction pdf-ilovepdf-compressed.pdf | 2 Oct 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archetect cerificate-ilovepdf-compressed.pdf | 2 Oct 2018 |
| Proforma of Allotment letterFile: Allotment letter(1)-ilovepdf-compressed.pdf | 2 Oct 2018 |
| Declaration in FORM BFile: FORM B.pdf | 1 Oct 2018 |
| PAN CardFile: PAN NO.pdf | 29 Sep 2018 |
| Copy of the legal title reportFile: Land title certificate.pdf | 29 Sep 2018 |
| Details of encumbrancesFile: ENCUMBERANCE CERTIFICATE.pdf | 29 Sep 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 29 Sep 2018 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Const 448 No EWS Ts 448 LIG Ts 517 No MIG Ts and 10 No Shop under ph-I at Mahalunge | Mahalunge Tal Khed Dist Pune | 1,413 | Completed | May 2017 | May 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 54 filed documents as one ZIP, foldered, with a manifest
Keep Construction of 760 EWS tenaments on survey on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Joshiwada13,700+ in Pune
Filed coordinates, straight-line distance. 121 registered projects within 2 km.
ANANDAM PHASE I
A V BHAT DEVELOPERS LLP
Ashiana Amodh Phase I
Ashiana Housing Limited
Ashiana Amodh Phase 3
Ashiana Housing Limited
HAPPYCITY VARALE
NAMRATA DEVELOPERS PRIVATE LIMITED
Namrata Sarvam
NAMRATA KHANDGE VENTURES
PLATINUM ELITE
Sugat Properties
Builder: PUNE HOUSING AND AREA DEVELOPMENT BOARD
PUNE HOUSING AND AREA DEVELOPMENT BOARD has 2 registrations on MahaRERA, including Construction of 760 EWS tenaments on survey No 12 part at Talegaon Dabhade and Construction of 400 EWS on land bearing no 818 p chakan Pune. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Construction of 760 EWS tenaments on survey No 12 part at Talegaon Dabhade is delayed beyond 31 Aug 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Construction of 760 EWS tenaments on survey No 12 part at Talegaon Dabhade?
The registered promoter entity is PUNE HOUSING AND AREA DEVELOPMENT BOARD, a public authority as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Construction of 760 EWS tenaments on survey No 12 part at Talegaon Dabhade?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Construction of 760 EWS tenaments on survey No 12 part at Talegaon Dabhade?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Construction of 760 EWS tenaments on survey No 12 part at Talegaon Dabhade?
The professionals named in the filing: Architect: RIYAZ MULLA; Engineer: Aqueel M H structure vision; Chartered Accountant: Swati Parab Chief Accounts Officer MHADA Pune. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Construction of 760 EWS tenaments on survey No 12 part at Talegaon Dabhade?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback