Home / Browse projects / Mumbai Suburban, Maharashtra / Const of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli east
Const of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli east
By MHADA
RG-MH-02242 · RERA P51800000058 · Last updated on MahaRERA portal: 7 Mar 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 7 months past the filed date
- Completion date moved by 39 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Const of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli east is a Residential / Group Housing project by MHADA in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000058 on 22 Jun 2017. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 39 months from the original filing.
At a glance
Project
- NameConst of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli east
- TypeResidential / Group Housing
- Location
- Kurla
- Mumbai Suburban
- 400083
- Pincode400083
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800000058
- ReraGenie IDRG-MH-02242
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Jun 2017
- Promised completion31 Mar 2026
- Revised completionRevised to 31 Mar 2026 (originally 30 Dec 2022)
- Buildings20 building records
- Documents filed110 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BLDG NO 12B PKT-I | NA | 23 | 0 | 0 | 0 | 0 |
| BLDG NO 12A PKT-I | NA | 23 | 0 | 0 | 0 | 0 |
| BLDG NO 04 PKT-II | NA | 23 | 0 | 0 | 0 | 0 |
| 9A PKT-I | NA | 9 | 0 | 0 | 0 | 0 |
| 9B PKT-I | NA | 9 | 0 | 0 | 0 | 0 |
| 10A PKT-I | NA | 9 | 0 | 0 | 0 | 0 |
| 10B PKT-I | NA | 9 | 0 | 0 | 0 | 0 |
| 10C PKT-I | NA | 9 | 0 | 0 | 0 | 0 |
| 10 D PKT-I | NA | 9 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 0 | NA | 0 | 0 | 0 | 0 | 0 |
| 1A PKT-III | NA | 26 | 0 | 0 | 0 | 0 |
| 1B PKT-III | NA | 26 | 0 | 0 | 0 | 0 |
| 1A PKT-IV | NA | 24 | 0 | 0 | 0 | 0 |
| 1B PKT-IV | NA | 24 | 0 | 0 | 0 | 0 |
| 1C PKT-IV | NA | 24 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 7 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
130 of 220 construction stages are filed complete across 20 buildings. The stage furthest along is Installation of Lifts, at 80%.
BLDG NO 12B PKT-I82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BLDG NO 12A PKT-I82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BLDG NO 04 PKT-II37%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 50% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 10% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
9A PKT-I91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
9B PKT-I89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
10A PKT-I91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
10B PKT-I91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
10C PKT-I91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
10 D PKT-I91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
00%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
00%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
00%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
00%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
00%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
00%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
1A PKT-III91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
1B PKT-III91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
1A PKT-IV91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
1B PKT-IV91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
1C PKT-IV91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 7 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 30% |
| Water Supply | Yes | 30% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 40% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 30% |
| Electrical meter room, sub-station, receiving station | Yes | 30% |
| Aggregate area of recreational Open Space | Yes | 30% |
| Open Parking | Yes | 0% |
Parking filed112
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| BLDG NO 12B PKT-I | 0 | 21 | 21 |
| BLDG NO 12A PKT-I | 0 | 43 | 43 |
| BLDG NO 04 PKT-II | 0 | 28 | 28 |
| 9A PKT-I | 1 | 0 | 1 |
| 9B PKT-I | 1 | 0 | 1 |
| 10A PKT-I | 1 | 0 | 1 |
| 10B PKT-I | 1 | 0 | 1 |
| 10C PKT-I | 1 | 0 | 1 |
| 10 D PKT-I | 1 | 10 | 11 |
| 1A PKT-III | 1 | 0 | 1 |
| 1A PKT-IV | 1 | 0 | 1 |
| 1B PKT-IV | 1 | 0 | 1 |
| 1C PKT-IV | 1 | 0 | 1 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | N G MORE |
| Engineer | Y P Kajale |
| Partner | Role in project |
|---|---|
| MHADA | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe said Work could not be completed during time as existing tenants in transit buildings and chawls ‚ were not evicted by MBRR Board. Also due to worldwide outbreak of Covid-19 countrywide lockdown was declared by GOI. During lockdown reverse migration of labours took place to their native places, supply chain of construction material is disturbed which had adversely affected the construction activities in result the work could not completed in time. So 6th extension for the work is granted up to 31/03/2026 is granted by CE-II/MHADA on dt. 05.01.2022 for completing the total project. Accordin
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Jun 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Jun 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Dec 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 20 May 2025
Documents filed110
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 110 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Architect KN.pdf | 7 Mar 2026 |
| Form 2File: doc06220520260305113128.pdf | 7 Mar 2026 |
| Form 3File: doc06220320260305112859-compressed.pdf | 7 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: doc06220320260305112859-compressed.pdf | 7 Mar 2026 |
| Form 1File: Kannamwar Architect Certficate.pdf | 1 Dec 2025 |
| Form 2File: Kannamwar Engineer Certificate.pdf | 1 Dec 2025 |
| Form 3File: Kannamwar CA Form_compressed.pdf | 1 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Kannamwar CA Form_compressed.pdf | 1 Dec 2025 |
| OtherFile: OC bldg no 12AB.pdf | 20 May 2025 |
| OtherFile: Bldg no 4 OC.pdf | 20 May 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Bldg no 4 OC.pdf | 20 May 2025 |
| Building plan approvalFile: 12AB IOD_compressed.pdf | 31 Jul 2024 |
| Building plan approvalFile: 12AB Layout_compressed.pdf | 31 Jul 2024 |
| Building plan approvalFile: Typical bldg plan 12AB_compressed.pdf | 31 Jul 2024 |
| Building plan approvalFile: BLDG NO 4 TYPICAL PLAN.pdf | 31 Jul 2024 |
| Building plan approvalFile: 4 LIG PKT-II.pdf | 31 Jul 2024 |
| Building Plan Approval (IOD)File: 12AB IOD_compressed.pdf | 31 Jul 2024 |
| Building Plan Approval (IOD)File: 12AB Layout_compressed.pdf | 31 Jul 2024 |
| Building Plan Approval (IOD)File: Typical bldg plan 12AB_compressed.pdf | 31 Jul 2024 |
| Building Plan Approval (IOD)File: BLDG NO 4 TYPICAL PLAN.pdf | 31 Jul 2024 |
| Building Plan Approval (IOD)File: 4 LIG PKT-II.pdf | 31 Jul 2024 |
| Deviation Report with respect to Allotment letterFile: 1 Proforma of Allotment letter.pdf | 29 Jul 2024 |
| Deviation Report with respect to model copy of AgreementFile: 1 Proforma of Allotment letter.pdf | 29 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: march 2024 expenditure.pdf | 18 Jun 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Letter Pkt-III_compressed.pdf | 17 Oct 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Letter Pkt-IV_compressed.pdf | 17 Oct 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC drawings Pkt-III-1_compressed.pdf | 17 Oct 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Drawings Pkt-IV-1_compressed.pdf | 17 Oct 2023 |
| Declaration about Commencement CertificateFile: Certificate rera.pdf | 9 Aug 2023 |
| Declaration in FORM BFile: FORM B.pdf | 9 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 -7ABCD.pdf | 9 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 -8ABC.pdf | 9 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A 2019-20.pdf | 9 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 2020-21.pdf | 9 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 2021-2022.pdf | 9 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 2022-2023.pdf | 9 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: compliance of point 1(A).pdf | 9 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: March 2023 expenditure.pdf | 9 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: MARCH 2022.pdf | 9 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: Ts.pdf | 17 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Expenditure 2017-78.pdf | 9 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Expenditure 2018-19.pdf | 9 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Expenditure 2019-20.pdf | 9 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Expenditure 2020-21.pdf | 9 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate form-1.pdf | 9 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold-booked inventory.pdf | 9 Nov 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: MIG- 9AB,10ABC OC.pdf | 9 Nov 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 10-D OC.pdf | 9 Nov 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Kannamwar nagar CC.pdf | 6 Dec 2018 |
| OtherFile: 2ABC PART OC.pdf | 14 Aug 2018 |
| Layout approvalFile: PKT-I letter.pdf | 7 Jun 2017 |
| Layout approvalFile: layout pocket-1.pdf | 7 Jun 2017 |
| Layout approvalFile: Pkt-II layout plan letter.pdf | 7 Jun 2017 |
| Layout approvalFile: Layou PKT-2.pdf | 7 Jun 2017 |
| Layout approvalFile: IOD LETTER PKT 3.pdf | 7 Jun 2017 |
| Layout approvalFile: LAYOUT PLAN PKT-3.pdf | 7 Jun 2017 |
| Layout approvalFile: IOD LETTER PKT 4.pdf | 7 Jun 2017 |
| Layout approvalFile: LAYOUT PLAN PKT-4.pdf | 7 Jun 2017 |
| Building plan approvalFile: BLDG-2 IOD CC.pdf | 7 Jun 2017 |
| Building plan approvalFile: Gr floor plan bldg 2 pkt I.pdf | 7 Jun 2017 |
| Building plan approvalFile: BLDG-9 IOD CC.pdf | 7 Jun 2017 |
| Building plan approvalFile: Bldg 9 stilt plan.pdf | 7 Jun 2017 |
| Building plan approvalFile: BLDG-10 IOD CC.pdf | 7 Jun 2017 |
| Building plan approvalFile: bldg 10 stilt plan.pdf | 7 Jun 2017 |
| Building plan approvalFile: Bldg no 2 pkt-II letter.pdf | 7 Jun 2017 |
| Building plan approvalFile: Stilt floor bldg 2 PKT-2.pdf | 7 Jun 2017 |
| Building plan approvalFile: bldg no 3 PKT 2.pdf | 7 Jun 2017 |
| Building plan approvalFile: Stilt floor bldg 3 PKT-2.pdf | 7 Jun 2017 |
| Building plan approvalFile: bldg no 4 Pkt 2.pdf | 7 Jun 2017 |
| Building plan approvalFile: Stilt bldg 4 PKT-2.pdf | 7 Jun 2017 |
| Building plan approvalFile: Bldg 1 IOD LETTER PKT-3.pdf | 7 Jun 2017 |
| Building plan approvalFile: BLDG PLAN 1 PKT-3.pdf | 7 Jun 2017 |
| Building plan approvalFile: BLDG 2 IOD LETTER PKT-3.pdf | 7 Jun 2017 |
| Building plan approvalFile: BLDG 2 STILT PKT-3.pdf | 7 Jun 2017 |
| Building plan approvalFile: bldg no 1 IOD letter PKT-IV.pdf | 7 Jun 2017 |
| Building plan approvalFile: Stilt plan PKT-IV.pdf | 7 Jun 2017 |
| PAN CardFile: pan card.pdf | 7 Jun 2017 |
| Copy of the legal title reportFile: Legal title with property card.pdf | 7 Jun 2017 |
| Details of encumbrancesFile: non cumbrance certificate.pdf | 7 Jun 2017 |
| Copy of Layout Approval (in case of layout)File: PKT-I letter.pdf | 7 Jun 2017 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| TUNGWA POWAI | POWAI MUMBAI 400076 | 1,191 | Completed | Mar 2018 | Late, Mar 2019 |
| R-10 MANKHURD EWS AND LIG | S.NO. 138 CTS NO. 1 PMGP COLONY MANKHURD | 325 | Completed | Feb 2012 | Late, Jun 2016 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 17 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 110 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Const of 1041 TR Ts 69 shops 1950 EWS 224 MI on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kurla6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 151 registered projects within 2 km.
Cons 1221 MIG T/S and 100 Shops S. No. 113 (pt
Mumbai Housing And Area Development Board
Om Siddhivinayak CHS and Gurukrupa CHS
Shreeji Developers
AKASSH AMAZONIA TOWER 1
HEER MEHTA LANDMARK DEVELOPERS PRIVATE LIM
Ajmera Solis
Shree Yogi Realcon Private Limited
CENTRAL PARK
V LAXMI NURSES DEVELOPERS LLP
Swastik Platinum
SUVASYA BUILDERS AND DEVELOPERS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: MHADA
MHADA has 18 registrations on MahaRERA, including Ruby Mill and Bharat Mill. Its filings disclose 10 earlier MahaRERA projects: declares 2 of 10 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Const of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli east shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Const of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli east is delayed beyond 31 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Const of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli east?
The registered promoter entity is MHADA, a public authority as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Const of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli east?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Const of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli east?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Const of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli east?
The professionals named in the filing: Architect: N G MORE; Engineer: Y P Kajale. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Const of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli east?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.