MHADA has 18 registrations in this build, including Ruby Mill and Bharat Mill. Its filings disclose 10 earlier MahaRERA projects: 2 of 10 past projects completed on time.
Projects in this build
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Piramal Mill | 6 May 2010 | 24 May 2012 | +25 months |
| Shriram Mill | 6 May 2010 | 7 Apr 2012 | +23 months |
| Simplex Mill | 7 May 2010 | 30 Sep 2011 | +17 months |
| Standard Mill Sewree | 5 Jun 2010 | 17 Mar 2012 | +21 months |
| Standard Mill Prabhadevi | 5 Jun 2010 | 16 Dec 2011 | +18 months |
| Dwan Mill Swan Mill | 21 Sep 2010 | 21 Sep 2010 | On time |
| New Hind Mill | 9 Nov 2010 | 25 May 2012 | +19 months |
| R-10 MANKHURD EWS AND LIG | 24 Feb 2012 | 30 Jun 2016 | +52 months |
| Pratiksha Nagar Ph IV | 21 Aug 2015 | 21 Aug 2015 | On time |
| TUNGWA POWAI | 31 Mar 2018 | 31 Mar 2019 | +12 months |
Frequently asked questions
How do I verify MHADA as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with MHADA?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.