MHADA: RERA track record

Public Authority ยท attribution by exact filing name, entity resolution in progress

MHADA has 18 registrations in this build, including Ruby Mill and Bharat Mill. Its filings disclose 10 earlier MahaRERA projects: 2 of 10 past projects completed on time.

18Registrations in this build
10Past projects disclosed
+18 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Ruby MillMumbai City, Maharashtra--Completed
Bharat MillMaharashtra--Completed
Jubilee MillMaharashtra--Completed
Prakash Cotton MillMaharashtra--Completed
Bombay Dyeing MillMaharashtra--Registration lapsed
Century MillMaharashtra--Completed
Pratiksha Nagar Sion Phase VMaharashtra--Completed
Pratiksha Nagar Phase IVMaharashtra--Completed
Western India MillMaharashtra--Completed
R-4 mankhurdMumbai Suburban, Maharashtra--Completed
Construction of Bldg no.22 B at Kopari powaiMumbai Suburban, Maharashtra--Registration lapsed
MIG / LIG Ts CTS No 165 at Tagore Nagar, Vikhroli, EMumbai Suburban, Maharashtra--Registration lapsed
TUNGWA POWAIMumbai Suburban, Maharashtra--Registration lapsed
Construction of 406 TR TS 442 EWS 258 MIG TS at Gavanpada Mulund east MumbaiMumbai Suburban, Maharashtra--Completed
Const of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli eastMumbai Suburban, Maharashtra--Registration lapsed
Construction of Mill Workers Tenements at Shrinivas MIll Lower ParelMaharashtra--Registration lapsed
Construction of Transit and EWS tenements at Antop Hill WadalaMaharashtra--Registration lapsed
Construction of MIG t/s on open plot on land bearing S.No.01 pt. on CTS No. 1/3 village kopari powaiMumbai Suburban, Maharashtra--Registration lapsed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Piramal Mill
6 May 201024 May 2012+25 months
Shriram Mill
6 May 20107 Apr 2012+23 months
Simplex Mill
7 May 201030 Sep 2011+17 months
Standard Mill Sewree
5 Jun 201017 Mar 2012+21 months
Standard Mill Prabhadevi
5 Jun 201016 Dec 2011+18 months
Dwan Mill Swan Mill
21 Sep 201021 Sep 2010On time
New Hind Mill
9 Nov 201025 May 2012+19 months
R-10 MANKHURD EWS AND LIG
24 Feb 201230 Jun 2016+52 months
Pratiksha Nagar Ph IV
21 Aug 201521 Aug 2015On time
TUNGWA POWAI
31 Mar 201831 Mar 2019+12 months

Frequently asked questions

How do I verify MHADA as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with MHADA?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.