Home / Browse projects / Dakshina Kannada, Karnataka / CONCORD RESIDENCY

Registration approved No litigation declared Residential/Group Housing project

CONCORD RESIDENCY

By ZAKARIYA SAMPYA

RG-KA-46054 · RERA PRM/KA/RERA/1257/335/PR/210524/006921 · Last updated on RERA Karnataka portal: 17 May 2024

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Mar 2023Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 87 documents Report an error

CONCORD RESIDENCY is a Residential/Group Housing project by ZAKARIYA SAMPYA in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/335/PR/210524/006921 on 21 May 2024. Possession is promised by 4 Mar 2023.

At a glance

Project

  • NameCONCORD RESIDENCY
  • TypeResidential/Group Housing
  • Location
    • Puttur
    • Dakshina Kannada
    • 574202
  • Pincode574202
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/335/PR/210524/006921
  • ReraGenie IDRG-KA-46054

Builder

  • NameZAKARIYA SAMPYA
  • Entity typeProprietorship
  • Authorized SignatoryZAKARIYA SAMPYA

Key dates

Registered
21 May 2024
Promised
4 Mar 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 May 2024
  • Promised completion4 Mar 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed87 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CONCORD RESIDENCY---16016

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 17 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)Not applicable
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 17 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes-
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes-
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area727 sq m
Named landowners1
LandownerVillageDistrict
ZAKARIYA SAMPYA--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 2.02 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 2.00 cr-
On-site expenditure-Salaries of workersRs 2.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHALINI SURESH
EngineerDINESH R
Chartered AccountantABHINAYA

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed87

As listed on the registration, under the names the promoter filed them with; the newest 80 of 87 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/335/PR/210524/006921 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
VILLAGE mapFile: village map.pdf17 May 2024
commencement certificateFile: commencement certificate.pdf17 May 2024
BUILDING LICENCEFile: Building licence.pdf17 May 2024
OCFile: OC.pdf17 May 2024
CLARIFICATIONFile: clarification.pdf17 May 2024
RTC, survey 231/2(P9)-
Mutation, survey 231/2(P9)-
Encumbrance Certificate, survey 231/2(P9)-
Conversion/Alienation Order, survey 231/2(P9)-
Sale/Title/Gift Deed, survey 231/2(P9)-
Khatha, survey 231/2(P9)-
Registration CertificateFile: MSME.pdf-
Certificate issued by CA Form 1File: CA Certificate _compressed.pdf-
Certificate issued by Architect Form 2File: architect certifiate form 2.pdf-
Certificate issued by Engineer Form 3File: Form 3 engineer certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: litigation affidavit.pdf-
Certificate from Chartered AccountFile: CA Certificate _compressed.pdf-
Balance Sheet 2022 - 2023File: BS AY 2023-24.pdf-
Balance Sheet 2021 - 2022File: BS AY 2022-23.pdf-
Balance Sheet 2020 - 2021File: BS AY 2021-22.pdf-
Audited Profit and Loss Statement 2022 - 2023File: PL AY 2023-24.pdf-
Audited Profit and Loss Statement 2021 - 2022File: PL AY 2022-23.pdf-
Audited Profit and Loss Statement 2020 - 2021File: PL AY 2021-22.pdf-
Cash Flow Statement 2022 - 2023File: IS AY 2023-24.pdf-
Cash Flow Statement 2021 - 2022File: IS AY 2022-23.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR AY 2023-24.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR AY 2022-23.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR AY 2021-22.pdf-
Revised licence-
revised plan-
revised plan-
revised plan-
revised plan-
revised plan-
specification-
revised plan-
single layout clarification-
stability certificate-
search report-
title deed-
Conversion-
Conversion-
mother deed-
proforma AOS-
Proforma allotment letter-
BROUCHER-
form b-
affidavit 3(1)-
mescom noc order copy-
water noc-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
estimation cost by engineer-
village map-
OC-
Stp drawing-
bank affidavit by promoter-
affidavit for sold unsold unit-
Building licence-
Residency Plan-
architect certifiate form 5-
Form 6 engineer certificate-
katha Flats_compressed-

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep CONCORD RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmCONCORD RESIDENCYOther 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: ZAKARIYA SAMPYA

ZAKARIYA SAMPYA has 1 registration on RERA Karnataka, including CONCORD RESIDENCY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if CONCORD RESIDENCY is delayed beyond 4 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of CONCORD RESIDENCY?

The registered promoter entity is ZAKARIYA SAMPYA, a proprietorship as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in CONCORD RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at CONCORD RESIDENCY?

The professionals named in the filing: Architect: SHALINI SURESH; Engineer: DINESH R; Chartered Accountant: ABHINAYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CONCORD RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CONCORD RESIDENCY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CONCORD RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.