Home / Browse projects / Mumbai Suburban, Maharashtra / Commercial Wing - NL Plaza and Residential Wing - NL Krishna

Registration lapsed Litigation declared Residential / Group Housing project

Commercial Wing - NL Plaza and Residential Wing - NL Krishna

By BEAUTIFUL PROPERTIES PRIVATE LIMITED

RG-MH-92604 · RERA P51800048076 · Last updated on MahaRERA portal: 17 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 2 months past the filed date
  • Litigation declared, 8 cases
  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 55.00 crore secured on the land, in favour of TATA CAPITAL HOUSING FINANCE LIMITED

Clear

  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Aug 2026Possession promised2 months past this date
3 of 8Construction stages donefurthest along: Internal walls, 95%
144 of 164Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 214 documents Report an error

Commercial Wing - NL Plaza and Residential Wing - NL Krishna is a Residential / Group Housing project by BEAUTIFUL PROPERTIES PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800048076 on 8 Dec 2022. Possession was promised by 3 Aug 2026 and is now 2 months past that date. The completion date has moved by 12 months from the original filing. 20 of the 164 units on this registration are recorded sold or booked, and 3 of 8 construction stages are filed complete.

At a glance

Project

  • NameCommercial Wing - NL Plaza and Residential Wing - NL Krishna
  • TypeResidential / Group Housing
  • Location
    • S N Dubey Road
    • Dahisar East
    • Borivali
    • Mumbai Suburban
    • 400068
  • Pincode400068
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800048076
  • ReraGenie IDRG-MH-92604

Builder

  • NameBEAUTIFUL PROPERTIES PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorRAJESH HIMATLAL
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

2 months past promisethis monthRegisteredDec 2022First promiseAug 2025Revised toAug 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Dec 2022
  • Promised completion3 Aug 2026
  • Revised completionRevised to 3 Aug 2026 (originally 31 Aug 2025)
  • Buildings1 building record
  • Documents filed214 files

Current status

12%20 of 164 units booked
100.0%Work done, per cost certificate

Figures as on 17 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Bldg - NL Krishna / Wing - A, B and C3131310559164

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 8 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

Bldg - NL Krishna / Wing - A, B and C · wing 3: 97% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 17 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed150

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots150
Closed/Covered150

Land and ownership3

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,552 sq m
Land owned byNot the promoter
Named landowners3
Encumbrance on the landDeclared present
Charge in favour ofTATA CAPITAL HOUSING FINANCE LIMITED
Secured amountRs 55.00 crore
CERSAI search filedYes
Declared on27 Mar 2026
LandownerVillageDistrict
Daulat Co-op. Hsg. Soc. Ltd.BorivaliMumbai Suburban
Satyam Co-op. Hsg. Soc. Ltd.BorivaliMumbai Suburban
Sahyog Co-op. Hsg. Soc. Ltd.BorivaliMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI8305.69
Proposed, not sanctioned8,306 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., Shop No. 02, Rawal Building 01, DR.Bhadkamkar Marg,Opera House, Mumbai.400004
Estimated costRs 89.42 cr
Cost incurredRs 89.42 cr
Work done100.0%
BuildingWingEstimatedIncurred
Bldg - NL Krishna / Wing - A, B and C3Rs 89.42 crRs 89.42 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architectbnm associates & architects
EngineerSterling Engineering Consultancy Services Pvt Ltd
EngineerPRAKASH V PARAB
Chartered AccountantPragnesh Vinodkumar Thakkar
Chartered AccountantP V Thaker & Company
Chartered AccountantSunil Vankawala and Associates
PartnerRole in project
BEAUTIFUL PROPERTIES PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA28072502216Aug 2025 → Aug 2026

Reason as filed by the promoterDue to some unforeseen reasons, Project is taking the more time to complete. As of today, 5% to 7% of the work of the project is pending for which we have applied for extension of CC. We have attached the Order for extension of CC for your ready reference. All the Customers have also grant the assent for the extension which is also attached herewith for your ready reference. Kindly grant the extension for project.

Litigation declared8

CaseCourtStatus
16255/2022High Court Of BombayClosed
16295/2022High Court Of BombayClosed
139/2022High Court Of BombayClosed
16255/2022High Court Of BombayClosed
2892 of 2022/2022City Civil Court DindoshiOngoing
3567 of 2023/2023High Court BombayOngoing
868 of 2024/2024City Civil Court DindoshiOngoing
1595 of 2025/2025High Court BombayOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Nov 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Jun 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed214

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 214 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 NL Krishna 15_07_2026.pdf17 Jul 2026
Withdrawal Update Form 2File: Form 2 NL Krishna 15_07_2026.pdf17 Jul 2026
Withdrawal Update Form 3File: Form 3 NL Krishna 15_07_2026.pdf17 Jul 2026
Building plan approvalFile: 2026-06-02 NL KRISHNA FURTHER CC 02-06-2026.pdf3 Jun 2026
Building plan approvalFile: AMENDED LETTER SIGNED 06-05-2026.pdf27 May 2026
Building plan approvalFile: AMENDED DRAWING 06-05-2026_Page 1.pdf27 May 2026
Building plan approvalFile: AMENDED DRAWING 06-05-2026_Page 2.pdf27 May 2026
Building plan approvalFile: AMENDED DRAWING 06-05-2026_Page 3.pdf27 May 2026
Building plan approvalFile: AMENDED DRAWING 06-05-2026_Page 4.pdf27 May 2026
Building plan approvalFile: AMENDED DRAWING 06-05-2026_Page 5.pdf27 May 2026
Building plan approvalFile: AMENDED DRAWING 06-05-2026_Page 6.pdf27 May 2026
Building plan approvalFile: AMENDED DRAWING 06-05-2026_Page 7.pdf27 May 2026
Building plan approvalFile: AMENDED DRAWING 06-05-2026_Page 8.pdf27 May 2026
Building plan approvalFile: AMENDED DRAWING 06-05-2026_Page 9.pdf27 May 2026
Building plan approvalFile: AMENDED DRAWING 06-05-2026_Page 10.pdf27 May 2026
Building plan approvalFile: AMENDED DRAWING 06-05-2026_Page 11.pdf27 May 2026
Building plan approvalFile: AMENDED DRAWING 06-05-2026_Page 12.pdf27 May 2026
Building plan approvalFile: AMENDED DRAWING 06-05-2026_Page 13.pdf27 May 2026
Building plan approvalFile: AMENDED APPROVAL PLANS 02-03-2022 -1.pdf22 Apr 2026
Building plan approvalFile: AMENDED APPROVAL PLANS 02-03-2022 -2.pdf22 Apr 2026
Building plan approvalFile: AMENDED APPROVAL PLANS 02-03-2022 -3.pdf22 Apr 2026
Building plan approvalFile: AMENDED APPROVAL PLANS 02-03-2022 -4.pdf22 Apr 2026
Building plan approvalFile: AMENDED APPROVAL PLANS 02-03-2022 -5.pdf22 Apr 2026
Building plan approvalFile: AMENDED APPROVAL PLANS 02-03-2022 -6.pdf22 Apr 2026
Building plan approvalFile: AMENDED APPROVAL PLANS 02-03-2022 -7.pdf22 Apr 2026
Building plan approvalFile: AMENDED APPROVAL PLANS 02-03-2022 -8.pdf22 Apr 2026
Building plan approvalFile: AMENDED APPROVAL PLANS 02-03-2022 -9.pdf22 Apr 2026
Building plan approvalFile: AMENDED APPROVAL PLANS 02-03-2022 -10.pdf22 Apr 2026
Building plan approvalFile: AMENDED APPROVAL PLANS 02-03-2022 -11.pdf22 Apr 2026
Building plan approvalFile: AMENDED APPROVAL PLANS 02-03-2022 -12.pdf22 Apr 2026
Building plan approvalFile: AMENDED APPROVAL PLANS 02-03-2022 -13.pdf22 Apr 2026
Withdrawal Update Form 1File: Withdrawal Application Form1 20_04_2026.pdf20 Apr 2026
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf20 Apr 2026
Withdrawal Update Form 3File: Withdrawal Application Form3 20_04_2026.pdf20 Apr 2026
Withdrawal Update Form 1File: FORM NO-1 NL Krishna 31_12_25.pdf21 Feb 2026
Withdrawal Update Form 2File: FORM NO-2 NL Krishna 31_12_25.pdf21 Feb 2026
Withdrawal Update Form 3File: FORM NO-3 NL Krishna 31_12_25_compressed.pdf21 Feb 2026
Withdrawal Update Form 1File: Form-1 NL Krishna 31_08_25.pdf14 Oct 2025
Withdrawal Update Form 2File: Form-2 NL Krishna 31_08_25.pdf14 Oct 2025
Withdrawal Update Form 3File: Form-3 NL Krishna 31_08_25_compressed.pdf14 Oct 2025
Form 2A (FY 2025-2026)File: Form 2A - NL Krishna.pdf29 Sep 2025
Form 5 (FY 2024-2025)File: Form 5 - NL Krishna.pdf26 Sep 2025
Withdrawal Update Form 1File: Form 1_NL Krishna_30_06_24.pdf20 Jul 2025
Withdrawal Update Form 2File: FORM 2 NL Krishna.pdf20 Jul 2025
Withdrawal Update Form 3File: Form 3 - NL Krishna 30_06_2025_compressed.pdf20 Jul 2025
Commencement certificateFile: NL KRISHNA FULL C C.pdf19 Jul 2025
Withdrawal Update Form 1File: Form 1_NL Krishna_30_06_24.pdf19 Jul 2025
Withdrawal Update Form 2File: FORM 2 NL Krishna.pdf19 Jul 2025
Withdrawal Update Form 3File: Form 3 - NL Krishna 30_06_2025_compressed.pdf19 Jul 2025
Form 2A (FY 2024-2025)File: FORM-2A NL Krishna.pdf19 Jul 2025
Form 1File: Form 1 - Architect Certificate nl krishna signed 1301.pdf18 Jul 2025
Form 2File: FORM-2 ENGNR CERTIFICATE NLK signed 1301.pdf18 Jul 2025
Form 3File: Form 3 BPPL NL KRISHNA.PDF18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory 31_12_2022.pdf18 Jul 2025
Form 1File: Form 1 NL Krishna 11 04 23.pdf18 Jul 2025
Form 2File: Form 2 NL Krishna 11 04 23.pdf18 Jul 2025
Form 3File: Form 3 NL Krishna 11 04 23.PDF18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory 31_03_2023.pdf18 Jul 2025
Form 1File: Form 1 NL Krishna_300623.pdf18 Jul 2025
Form 2File: Form 2 NL Krishna_300623.pdf18 Jul 2025
Form 3File: Form - 3 NL Krishna_300623.PDF18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory 30_06_2023.pdf18 Jul 2025
Form 1File: Form 1 NL Krishna 07102023.pdf18 Jul 2025
Form 2File: Form 2 NL Krishna 07102023.pdf18 Jul 2025
Form 3File: Form 3 - NL Krishna 30092023.PDF18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory 30_09_2023.pdf18 Jul 2025
Form 1File: NL Krishna Form 1 13012024.pdf18 Jul 2025
Form 2File: NL Krishna Form 2 13012024.pdf18 Jul 2025
Form 3File: Form 3 RERA 130124.PDF18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory 31_12_2023.pdf18 Jul 2025
Form 1File: NL Krishna Form 1 - Architect Certificate.pdf18 Jul 2025
Form 2File: NL Krishna Form 2 - Engineers Certificate.pdf18 Jul 2025
Form 3File: RERA Certificate Form 3.PDF18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory 31_03_2024.pdf18 Jul 2025
Form 1File: Form 1_NL Krishna_30_06_24.pdf18 Jul 2025
Form 2File: Form 2_NL Krishna_30_06_24.pdf18 Jul 2025
Form 3File: Form 3_NL Krsihna_30_06_24.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory 30_06_2024.pdf18 Jul 2025
Form 1File: FORM 1 - NL Krishna 30_09_24.pdf18 Jul 2025
Form 2File: FORM 2 - NL Krishna 30_09_24.pdf18 Jul 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
BHAVESHA CO-OPERATIVE HOUSING SOCIETY LTDP51800033264ANDHERI (WEST), Mumbai SuburbanFeb 2022CompletedNov 2023May 2023

How this compares with Mumbai Suburban

12%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Commercial Wing - NL Plaza and Residential W on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dahisar East6,700+ in Mumbai Suburban

2 kmCommercial Wing - NL PlaCompleted 56Lapsed / revoked 34Other 94Dot size: filed unitsN

Filed coordinates, straight-line distance. 184 registered projects within 2 km.

Builder: BEAUTIFUL PROPERTIES PRIVATE LIMITED

BEAUTIFUL PROPERTIES PRIVATE LIMITED has 3 registrations on MahaRERA, including BHAVESHA CO-OPERATIVE HOUSING SOCIETY LTD and Commercial Wing - NL Plaza and Residential Wing - NL Krishna. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Commercial Wing - NL Plaza and Residential Wing - NL Krishna shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Commercial Wing - NL Plaza and Residential Wing - NL Krishna is delayed beyond 3 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Commercial Wing - NL Plaza and Residential Wing - NL Krishna?

The registered promoter entity is BEAUTIFUL PROPERTIES PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Commercial Wing - NL Plaza and Residential Wing - NL Krishna?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Commercial Wing - NL Plaza and Residential Wing - NL Krishna?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Commercial Wing - NL Plaza and Residential Wing - NL Krishna?

The professionals named in the filing: Architect: bnm associates & architects; Engineer: Sterling Engineering Consultancy Services Pvt Ltd; Engineer: PRAKASH V PARAB; Chartered Accountant: Pragnesh Vinodkumar Thakkar; Chartered Accountant: P V Thaker & Company; Chartered Accountant: Sunil Vankawala and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Commercial Wing - NL Plaza and Residential Wing - NL Krishna?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Commercial Wing - NL Plaza and Residential Wing - NL Krishna. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Commercial Wing - NL Plaza and Residential W to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.