Red flags
- 3 complaints at RERA Karnataka
- Completion date moved by 12 months
- 1 extension taken
Clear
- Separate project account declared
Saved.
CK ADIITHYA is a Plotted Development project by M/s Prajwal Promoters Private Limited in Ramanagara, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/305/PR/171019/001055 on 19 Oct 2017. Possession is promised by 29 May 2018. The completion date has moved by 12 months from the original filing. 3 complaints are on record with the regulator.
At a glance
Project
- NameCK ADIITHYA
- TypePlotted Development
- Location
- Kanakapura
- Ramanagara
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1250/305/PR/171019/001055
- ReraGenie IDRG-KA-59630
Builder
- NameM/s Prajwal Promoters Private Limited
- Entity typePartnership Firm
- CINU45201KA2008PTC048610
- Authorized SignatoryMr. C Ajay Kumar
- DirectorMrs. Savitha Nekundi Chandrashekar
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on19 Oct 2017
- Promised completion29 May 2018
- Revised completionRevised to 29 May 2018 (originally 29 May 2017)
- BuildingsNot stated in filing
- Documents filed44 files
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterothers
Complaints filed with RERA Karnataka3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| 00947/2025 | - | M/s Prajwal Promoters Private Limited | 17/07/2025 |
| 00028/2026 | - | M/s Prajwal Promoters Private Limited | 08/01/2026 |
| 00127/2026 | - | M/s Prajwal Promoters Private Limited | 17/02/2026 |
Documents filed44
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/305/PR/171019/001055 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Prajwal Promoters Registration.jpg | - |
| Architect Certificate for Work Completion Schedule till DateFile: KEY PLAN096.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Approved plan.pdf | - |
| CA Certificate for Funds UtilizationFile: CA Audit Report 2015-16-compressed.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: KEY PLAN096.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Approved plan.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: CA Audit Report 2015-16-compressed.pdf | - |
| AffidavitFile: FORM -B095.pdf | - |
| Latest Encumbrance CertificateFile: EC094.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx | - |
| Approved plan | - |
| Approved plan | - |
| Sale Deed | - |
| Sale Agreement | - |
| Sale Deed and RTC | - |
| Approved plan | - |
| KEY PLAN096 | - |
| Allotment Letter | - |
| Broucher | - |
| NOC | - |
| Specification | - |
| EC | - |
| Khata | - |
| joint development agrement139 | - |
| Conversion Mutation & Advocate Report | - |
| Relinquishment Deed | - |
| Balance Sheet 2015 - 2016File: BALANCE SHEET 2016-17079.pdf | - |
| Balance Sheet 2014 - 2015File: BALANCE SHEET 2015-16085.pdf | - |
| Balance Sheet 2013 - 2014File: BALANCE SHEET 2014-15090.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: P&L STATEMENT 2016-17080.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: P&L ACCOUNT084.pdf | - |
| Audited Profit and Loss Statement 2013 - 2014File: P&LACCOUNT 2014-15088.pdf | - |
| Director's Report 2015 - 2016File: Director.pdf | - |
| Director's Report 2014 - 2015File: Director.pdf | - |
| Director's Report 2013 - 2014File: Director.pdf | - |
| Cash Flow Statement 2015 - 2016File: CAH FLOW 2016-17081.pdf | - |
| Cash Flow Statement 2014 - 2015File: CASH FLOW 2015-16086.pdf | - |
| Auditor's Report 2015 - 2016File: Audit 16.pdf | - |
| Auditor's Report 2014 - 2015File: Audit 15.pdf | - |
| Auditor's Report 2013 - 2014File: Audit 14.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: IT RETURN ACKNOWLEDGEMENT 2016-17082.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: IT RETURN ACKNOWLEDGEMENT 2015-16083.pdf | - |
| Income Tax Return Acknowledgement 2013 - 2014File: IT RETURN 2014-15087.pdf | - |
| FORM -B095 | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ramanagara
Computed across the 81 Ramanagara projects on ReraGenie, from their own filings.
Keep CK ADIITHYA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ramanagara81 in Ramanagara
SALARPURIA SATTVA ASHRAYA
NEELANCHAL DWELLINGS LLP
PRIME SYMPHONY
PRIME ESTATES
Construction of 286 houses at Channapattana to
CMC Channaptna
SAIBYA SQUARE
SAIBYA STRUCTURES PVT LTD
Svamitva Terravana Phase 2
Svamitva Landmarks
Magnolia Cedar Court
Universal Developers
See every Ramanagara project, with the district possession charts
Builder: M/s Prajwal Promoters Private Limited
M/s Prajwal Promoters Private Limited has 1 registration on RERA Karnataka, including CK ADIITHYA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Ramanagara district page.
Frequently asked questions
What are my rights if CK ADIITHYA is delayed beyond 29 May 2018?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of CK ADIITHYA?
The registered promoter entity is M/s Prajwal Promoters Private Limited, a partnership firm as per the filing. Its CIN U45201KA2008PTC048610 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in CK ADIITHYA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against CK ADIITHYA?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
What should I check before booking in CK ADIITHYA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback