Red flags
- Completion date moved by 43 months
- 3 extensions taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Magnolia Cedar Court is a Residential/Group Housing project by Universal Developers in Ramanagara, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/302/PR/181226/002263 on 26 Dec 2018. Possession is promised by 31 Dec 2024. The completion date has moved by 43 months from the original filing.
At a glance
Project
- NameMagnolia Cedar Court
- TypeResidential/Group Housing
- Location
- Ramanagara
- PincodeNot stated
- RERA no.PRM/KA/RERA/1250/302/PR/181226/002263
- ReraGenie IDRG-KA-53645
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on26 Dec 2018
- Promised completion31 Dec 2024
- Revised completionRevised to 31 Dec 2024 (originally 15 May 2021)
- Buildings1 building record
- Documents filed47 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 1 | - | - | - | 62 | 0 | 62 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | Not applicable |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | Yes | - |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterForce Majeure
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed47
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/302/PR/181226/002263 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: REG Certificate.pdf | - |
| Project Details | - |
| Latest Encumbrance CertificateFile: Encumbrance Certificate_compressed.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: NOT SOLD ANY.pdf | - |
| Cedarcourt approval Copy | - |
| GBBSCPA-Approved Plan | - |
| Cedarcourt approval Copy | - |
| Sale deed | - |
| Sale Agreement | - |
| Sale Deed & RTC | - |
| GBBSCPA-Approved Plan | - |
| Allotment Letter | - |
| cedar court e-brochure | - |
| Specification--- | - |
| Encumbrance Certificate | - |
| Khata & Tax Paid | - |
| Conversion Certificate | - |
| KENCHUNAKUPPE _FINAL_PLAN-PDF | - |
| GBBSCPA-Approved Plan | - |
| Balance Sheet 2017 - 2018File: Balance Sheet (3 Years).pdf | - |
| Balance Sheet 2016 - 2017File: Balance Sheet (3 Years).pdf | - |
| Balance Sheet 2015 - 2016File: Balance Sheet (3 Years).pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: P & L (3 years).pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: P & L (3 years).pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: P & L (3 years).pdf | - |
| Cash Flow Statement 2017 - 2018File: cash flow statement (3 years).pdf | - |
| Cash Flow Statement 2016 - 2017File: cash flow statement (3 years).pdf | - |
| Auditor's Report 2017 - 2018File: Auditors' Report (3 years).pdf | - |
| Auditor's Report 2016 - 2017File: Auditors' Report (3 years).pdf | - |
| Auditor's Report 2015 - 2016File: Auditors' Report (3 years).pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: ITR18-19.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR17-18.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR15-16.pdf | - |
| Form B | - |
| Prospectus/BrochureFile: cedar court e-brochure new.pdf | - |
| Advertisement Copy 1File: Magnolia-Cedar Court Leaflet.pdf | - |
| Tower Excel SheetFile: PRMKARERA1250302PR181226002263-3.xlsx | - |
| Stability CertificateFile: 3033916209.pdf | - |
| Occupancy CertificateFile: OC.pdf | - |
| Consent for operation issued by KSPCBFile: Universal KSPCB ack.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: ESCOM CEDAR COURT NOC .pdf | - |
| Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: Form6-CC-MAGNOLIA CEDAR COURT.pdf | - |
| Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: NOT SOLD ANY.pdf | - |
| Details of undivided share of land handed over to the association of allotteesFile: NOT SOLD ANY.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: Form5 - A Closure C-MAGNOLIA CEDAR COURT.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: Form4-ColsureC-MAGNOLIA CEDAR COURT.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: AFFIDAVIT.pdf | - |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Magnolia Temple valleywoods | - | Completed | - | No date filed |
| Magnolia Temple Tree | - | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ramanagara
Computed across the 81 Ramanagara projects on ReraGenie, from their own filings.
Keep Magnolia Cedar Court on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ramanagara81 in Ramanagara
SALARPURIA SATTVA ASHRAYA
NEELANCHAL DWELLINGS LLP
PRIME SYMPHONY
PRIME ESTATES
Construction of 286 houses at Channapattana to
CMC Channaptna
SAIBYA SQUARE
SAIBYA STRUCTURES PVT LTD
Svamitva Terravana Phase 2
Svamitva Landmarks
43 Dus of PKGBY at Kanakpura
Municipal commissioner
See every Ramanagara project, with the district possession charts
Builder: Universal Developers
Universal Developers has 4 registrations on RERA Karnataka, including Magnolia Temple Tree and Magnolia Cedar Court. Its filings declare 4 earlier projects, 4 of them declared completed. Read the full track record. See more projects on the Ramanagara district page.
Frequently asked questions
What are my rights if Magnolia Cedar Court is delayed beyond 31 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Magnolia Cedar Court?
The registered promoter entity is Universal Developers, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Magnolia Cedar Court?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in Magnolia Cedar Court?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback