ReraGenieLog inGet a buyer report

Home / Browse projects / Ramanagara, Karnataka / Construction of 286 houses at Channapattana town

Registration approved No litigation declared Residential/Group Housing project

Construction of 286 houses at Channapattana town

By CMC Channaptna

RG-KA-41647 · RERA PRM/KA/RERA/1270/300/PR/261124/007246 · Last updated on RERA Karnataka portal: 31 May 2024

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
May 2028Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 75 documents Report an error

Construction of 286 houses at Channapattana town is a Residential/Group Housing project by CMC Channaptna in Ramanagara, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1270/300/PR/261124/007246 on 26 Nov 2024. Possession is promised by 31 May 2028.

At a glance

Project

  • NameConstruction of 286 houses at Channapattana town
  • TypeResidential/Group Housing
  • Location
    • Channapatna
    • Ramanagara
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1270/300/PR/261124/007246
  • ReraGenie IDRG-KA-41647

Builder

  • NameCMC Channaptna
  • Entity typeRajiv Gandhi Housing Corporation Limited
  • GSTIN29AAQCA4579B1ZC
  • Authorized SignatoryCommissioner

Key dates

this monthRegisteredNov 2024PromisedMay 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on26 Nov 2024
  • Promised completion31 May 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed75 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---2860286

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 31 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)Not applicable
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 31 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes-
LiftsNoNot applicable
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
Commissioner--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 31.01 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 22.70 cr-
On-site expenditure-Salaries of workersRs 6.81 cr-
On-site expenditure-Consultants FeesRs 1.50 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectACS Design consultants Pvt ltd
EngineerSathish
Chartered AccountantAccount superintendent

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed75

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1270/300/PR/261124/007246 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Construction of 286 houses at Channapattana townFile: Work order.pdf31 May 2024
RTC, survey 71/1 71/2 71/3 74/1 74/3 74/5-
Mutation, survey 71/1 71/2 71/3 74/1 74/3 74/5-
Encumbrance Certificate, survey 71/1 71/2 71/3 74/1 74/3 74/5-
Khatha, survey 71/1 71/2 71/3 74/1 74/3 74/5-
Registration CertificateFile: Ashpra GST Certificate.pdf-
Certificate issued by CA Form 1File: Letter.pdf-
Certificate issued by Architect Form 2File: Letter site.pdf-
Certificate issued by Engineer Form 3File: Letter site.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Letter site.pdf-
Certificate from Chartered AccountFile: Letter.pdf-
Balance Sheet 2022 - 2023File: Account statement.pdf-
Balance Sheet 2021 - 2022File: Account statement.pdf-
Balance Sheet 2020 - 2021File: Account statement.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Bank statement audit.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Bank statement audit.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Bank statement audit.pdf-
Director's Report 2022 - 2023File: DC letter.pdf-
Director's Report 2021 - 2022File: DC letter.pdf-
Director's Report 2020 - 2021File: DC letter.pdf-
Cash Flow Statement 2022 - 2023File: Bank statement audit.pdf-
Cash Flow Statement 2021 - 2022File: Bank statement audit.pdf-
Auditor's Report 2022 - 2023File: Letter.pdf-
Auditor's Report 2021 - 2022File: Letter.pdf-
Auditor's Report 2020 - 2021File: Letter.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: Account statement.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: Account statement.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: Account statement.pdf-
Account statement-
Letter-
Letter-
Applroval layout-
Layout plan-
Layout plan-
Applroval layout-
Structural drwings-
Plan elevation-
Applroval layout-
Applroval layout-
Structural drwings-
Letter-
Letter-
DC letter-
DC letter-
DC letter-
Mutation-
DC letter-
DC letter-
DC letter-
Letter-
Approval ltr 2-
DC letter-
DC letter-
Letter-
Approval ltr 2-
Approval ltr 2-
Letter-
Unnamed document-
Approval ltr 2-
Certificate-
Letter-
Letter-
Letter-
Applroval layout-
Applroval layout-
Approval ltr 2-
Approval ltr 2-
Approval ltr 2-
Letter-
Letter-
Letter-
Letter-

How this compares with Ramanagara

22%of Ramanagara projects moved their completion datethis one has not
1%of Ramanagara registrations are shown as withdrawn or revokedthis one is not

Computed across the 81 Ramanagara projects on ReraGenie, from their own filings.

Keep Construction of 286 houses at Channapattana on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ramanagara81 in Ramanagara

Builder: CMC Channaptna

CMC Channaptna has 1 registration on RERA Karnataka, including Construction of 286 houses at Channapattana town. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Ramanagara district page.

Frequently asked questions

What are my rights if Construction of 286 houses at Channapattana town is delayed beyond 31 May 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Construction of 286 houses at Channapattana town?

The registered promoter entity is CMC Channaptna, a rajiv gandhi housing corporation limited as per the filing. Its GSTIN 29AAQCA4579B1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Construction of 286 houses at Channapattana town?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Construction of 286 houses at Channapattana town?

The professionals named in the filing: Architect: ACS Design consultants Pvt ltd; Engineer: Sathish; Chartered Accountant: Account superintendent. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Construction of 286 houses at Channapattana town?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Construction of 286 houses at Channapattana town. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Construction of 286 houses at Channapattana to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.