Home / Browse projects / Raigarh, Maharashtra / CHINMAY PLAZA

Registered No litigation declared Residential / Group Housing project

CHINMAY PLAZA

By ATMARAM NARAYAN SHINDE

RG-MH-18268 · RERA P52000056422 · Last updated on MahaRERA portal: 9 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 24 months from the original
2 of 11Construction stages donefurthest along: Stilt Floor, 85%
75 of 85Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

CHINMAY PLAZA is a Residential / Group Housing project by ATMARAM NARAYAN SHINDE in Raigarh, Maharashtra, registered with MahaRERA as P52000056422 on 31 May 2024. Possession is promised by 31 Dec 2028. The completion date has moved by 24 months from the original filing. 10 of the 85 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete.

At a glance

Project

  • NameCHINMAY PLAZA
  • TypeResidential / Group Housing
  • Location
    • At Bhadav
    • Village Bhadav
    • Bhadav
    • Mangaon
    • Raigarh
    • 402104
  • Pincode402104
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000056422
  • ReraGenie IDRG-MH-18268

Builder

  • NameATMARAM NARAYAN SHINDE
  • Entity typeIndividual

Key dates

this monthRegisteredMay 2024First promiseDec 2026Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 May 2024
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 31 Dec 2026)
  • Buildings1 building record
  • Documents filed59 files

Current status

12%10 of 85 units booked
45.2%Work done, per cost certificate

Figures as on 9 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CHINMAY PLAZANA88701585

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 85%.

CHINMAY PLAZA: 40% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor85%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 9 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed52

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots52
Closed/Covered52

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,720 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMangaon Nagar Panchayat
Permissible FSI3883.7
Proposed, not sanctioned3,884 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, MTNL BUILDING, NEAR SHIVAJI CHOWK, PANVEL, DISTT.RAIGAD, NAVI MUMBAI. MH-410206
Estimated costRs 6.20 cr
Cost incurredRs 2.80 cr
Work done45.16%
BuildingWingEstimatedIncurred
CHINMAY PLAZANARs 5.36 crRs 2.80 cr
-NARs 84.00 lakh-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAR MANASI MAYEKAR
EngineerPRAPTI ASSOCIATES
Chartered AccountantMANISH K RAMAWATI AND COMPANY
Chartered AccountantMs K HEMANT & CO
Chartered Accountantsanjeet kumar
PartnerRole in project
ATMARAM NARAYAN SHINDE-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA10092622508Dec 2026 → Dec 2028

Reason as filed by the promoter1) Poor booking response from customer. 2) Because of poor response our work was very slow.

P52000056422/WarDec 2026 → Apr 2027

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 May 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 30-6-26.pdf9 Sep 2026
Withdrawal Update Form 2File: Form 2 .pdf9 Sep 2026
Withdrawal Update Form 3File: Form 3 Chinmay Ent 30-06-26 updated.pdf9 Sep 2026
Form 2A (FY 2024-2025)File: Form 2A 2024-25 Signed.pdf9 Sep 2026
Form 2A (FY 2025-2026)File: Form 2A 2025-26 Signed.pdf9 Sep 2026
Form 5 (FY 2024-2025)File: Form 5 24-25.pdf9 Sep 2026
Form 5 (FY 2025-2026)File: Form 5 25-26.pdf9 Sep 2026
Withdrawal Update Form 1File: Form 1 30-6-26.pdf2 Sep 2026
Withdrawal Update Form 2File: Form 2 .pdf2 Sep 2026
Withdrawal Update Form 3File: Form 3 Chinmay Ent 30-06-26 updated.pdf2 Sep 2026
Withdrawal Update Form 1File: Form 1 30-6-26.pdf3 Aug 2026
Withdrawal Update Form 2File: Form 2 .pdf3 Aug 2026
Withdrawal Update Form 3File: Form 3 Chinmay Ent 31-03-26.pdf3 Aug 2026
Withdrawal Update Form 1File: Form 1 Chinmay Ent 31-3-26.pdf4 May 2026
Withdrawal Update Form 2File: Form 2 Chinmay Ent 31-03-2026.pdf4 May 2026
Withdrawal Update Form 3File: Form 3 Chinmay Ent 31-03-26.pdf4 May 2026
Withdrawal Update Form 1File: Form 1-RERA-30-12-25 sign.pdf21 Apr 2026
Withdrawal Update Form 2File: Form 2 31-12-2025.pdf21 Apr 2026
Withdrawal Update Form 3File: Form 3 Chinmay Ent 31-12-25 signed.pdf21 Apr 2026
Withdrawal Update Form 1File: Form 1 30-09-25.pdf25 Nov 2025
Withdrawal Update Form 2File: Form 2 30-09-25.pdf25 Nov 2025
Withdrawal Update Form 3File: Form 3 30-09-25.pdf25 Nov 2025
Withdrawal Update Form 1File: Form 1 30-06-25.pdf6 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf6 Oct 2025
Withdrawal Update Form 3File: Form 3 Chinamay Ent 30-06-25 new.pdf6 Oct 2025
Withdrawal Update Form 1File: Form 1.pdf4 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf4 Oct 2025
Withdrawal Update Form 3File: Form 3 Chinamay Ent 30-06-25 new.pdf4 Oct 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - converted.pdf23 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31-12-24 - converted.pdf23 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf23 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf22 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf22 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (7 files merged).pdf22 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_007 (7 files merged).pdf22 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf22 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf22 Dec 2024
Other - TechnicalFile: ANNEXURE -A.pdf9 May 2024
Declaration in FORM BFile: form b.pdf7 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf7 May 2024
Proforma of Agreement for saleFile: AFS.pdf7 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A bank account decla (8).pdf7 May 2024
Other - LegalFile: KHAREDIKAT 1.pdf7 May 2024
Other - LegalFile: KHAREDIKAT 2.pdf7 May 2024
Layout approvalFile: Plan.pdf1 May 2024
Building plan approvalFile: Plan.pdf1 May 2024
PAN CardFile: pan card (1).pdf1 May 2024
Copy of the legal title reportFile: TITLE REPORT.pdf1 May 2024
Details of encumbrances concerned to FinanceFile: No encumbrances Certificate FINANCE and LEGAL.pdf1 May 2024
Details of encumbrances concerned to LegalFile: No encumbrances Certificate FINANCE and LEGAL.pdf1 May 2024
Copy of Layout Approval (in case of layout)File: Plan.pdf1 May 2024
Building Plan Approval / NA Order for plotted developmentFile: Plan.pdf1 May 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf1 May 2024
Declaration about Commencement CertificateFile: declaration about comm cert.pdf1 May 2024
CERSAI detailsFile: Cersai_Declaration.pdf1 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclouser of Interest in other.pdf1 May 2024
Proforma of Allotment letterFile: ALLOTMENT DRAFT NEW.pdf1 May 2024
Deviation Report with respect to Allotment letterFile: deviation-allotment.pdf1 May 2024
Deviation Report with respect to model copy of AgreementFile: deviation-draft sale.pdf1 May 2024

How this compares with Raigarh

12%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 24 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CHINMAY PLAZA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Village Bhadav5,900+ in Raigarh

Builder: ATMARAM NARAYAN SHINDE

ATMARAM NARAYAN SHINDE has 1 registration on MahaRERA, including CHINMAY PLAZA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if CHINMAY PLAZA is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CHINMAY PLAZA?

The registered promoter entity is ATMARAM NARAYAN SHINDE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CHINMAY PLAZA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CHINMAY PLAZA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CHINMAY PLAZA?

The professionals named in the filing: Architect: AR MANASI MAYEKAR; Engineer: PRAPTI ASSOCIATES; Chartered Accountant: MANISH K RAMAWATI AND COMPANY; Chartered Accountant: Ms K HEMANT & CO; Chartered Accountant: sanjeet kumar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CHINMAY PLAZA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CHINMAY PLAZA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CHINMAY PLAZA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.